Jonathan May / Friday, June 7, 2024 / Categories: Uncategorized Project Update - Week of June 10th, 2024 Please see the below project update and list of activities scheduled for the week of June 10th, 2024 The site contractor will conduct the existing Florence Roche water and sewer disconnections. The project team will conduct final coordination of electrical disconnection of the existing FloRo with GELD. The landscape contractor will continue hydroseed and spreading of mulch around the building. The landscape contractor will continue installation of the kindergarten playground, curbs, and poured-in-place surface. The misc. metals contractor will continue the installation of the exterior loading dock rails and front retaining wall railing. The painting contractor will continue painting of exterior rails and structural steel. The resilient flooring contractor will continue final setting of transition strips and wall base. The painting contractor will continue final patching and painting of level 1. The millwork and casework contractor will continue installation of the media center seating & desks and the lobby countertop. The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. The electrical contractor will continue security system programming. The food service contractor will commence initial pre-functional testing of the equipment. The tile contractor will continue installation of the cafeteria and main vestibule wall tile. The carpet contractor will continue carpet installation in the vestibules. The project's Architect, Studio G Architects, will continue completing the punchlist of the building. All contractor's will commence addressing punchlist items. Previous Article Project Update - Week of June 3rd, 2024 Next Article Project Update - Week of June 17th, 2024 Print 133 Rate this article: 5.0