Jonathan May
/ Categories: Uncategorized

Project Update - Week of June 10th, 2024

Please see the below project update and list of activities scheduled for the week of June 10th, 2024

  • The site contractor will conduct the existing Florence Roche water and sewer disconnections. 
  • The project team will conduct final coordination of electrical disconnection of the existing FloRo with GELD. 
  • The landscape contractor will continue hydroseed and spreading of mulch around the building. 
  • The landscape contractor will continue installation of the kindergarten playground, curbs, and poured-in-place surface. 
  • The misc. metals contractor will continue the installation of the exterior loading dock rails and front retaining wall railing. 
  • The painting contractor will continue painting of exterior rails and structural steel. 
  • The resilient flooring contractor will continue final setting of transition strips and wall base.  
  • The painting contractor will continue final patching and painting of level 1.
  • The millwork and casework contractor will continue installation of the media center seating & desks and the lobby countertop.   
  • The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. 
  • The electrical contractor will continue security system programming. 
  • The food service contractor will commence initial pre-functional testing of the equipment. 
  • The tile contractor will continue installation of the cafeteria and main vestibule wall tile. 
  • The carpet contractor will continue carpet installation in the vestibules. 
  • The project's Architect, Studio G Architects, will continue completing the punchlist of the building. 
  • All contractor's will commence addressing punchlist items. 
Previous Article Project Update - Week of June 3rd, 2024
Next Article Project Update - Week of June 17th, 2024
Print
133 Rate this article:
5.0

Theme picker