Jonathan May
/ Categories: Uncategorized

Project Update - Week of June 3rd, 2024

Please see the below project update and list of activities scheduled for the week of June 3rd, 2024.

  • The site contractor will prepare for the existing Florence Roche utility disconnection. 
  • The landscape contractor will continue spreading of loam, layout of trees and shrubs, and finalize irrigiation system install. 
  • The landscape contractor will continue hydroseading of the project's lawn areas around the building. 
  • The landscape contractor will continue installation of the kindergarten playground, curbs, and poured-in-place surface. 
  • The misc. metals contractor will continue the installation of the exterior loading dock rails and front retaining wall railing. 
  • The resilient flooring contractor will continue final setting of transition strips. 
  • The painting contractor will continue final patching and painting of level 1.
  • The millwork and casework contractor will continue installation of the stair B and platform stair treads and media center seating & desks. 
  • The specialties contractor will commence admin accoustic panel install. 
  • The wood flooring contractor will complete the stage flooring and commence the stair B platform flooring. 
  • The plumbing contractor will be setting hot water valves at all sinks and continue the commissioning process. 
  • The mechanical contractor will continue with equipment commissioning all all equipment. 
  • The mechanical contractor will continue balancing the supply and return air system.
  • The controls contractor will continue integrating equipment into the building management system.
  • The controls contractor will commense building commissioning effort with the MSBA third party commissioning agent. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1. 
  • The fire protection contractor will continue sprinkler head install in the stem patio ceiling. 
  • The electrical contractor will continue stem patio light installation. 
  • The electrical contractor will continue security system programming. 
  • The third party commissioning agent will continue review of all MEP systems.  
  • The tile contractor will continue installation of the cafeteria and main vestibule wall tile. 
  • The carpet contractor will continue carpet installation in the vestibules. 
Previous Article Project Update - Week of May 27th, 2024
Next Article Project Update - Week of June 10th, 2024
Print
152 Rate this article:
5.0

Theme picker