Jonathan May / Friday, May 31, 2024 / Categories: Uncategorized Project Update - Week of June 3rd, 2024 Please see the below project update and list of activities scheduled for the week of June 3rd, 2024. The site contractor will prepare for the existing Florence Roche utility disconnection. The landscape contractor will continue spreading of loam, layout of trees and shrubs, and finalize irrigiation system install. The landscape contractor will continue hydroseading of the project's lawn areas around the building. The landscape contractor will continue installation of the kindergarten playground, curbs, and poured-in-place surface. The misc. metals contractor will continue the installation of the exterior loading dock rails and front retaining wall railing. The resilient flooring contractor will continue final setting of transition strips. The painting contractor will continue final patching and painting of level 1. The millwork and casework contractor will continue installation of the stair B and platform stair treads and media center seating & desks. The specialties contractor will commence admin accoustic panel install. The wood flooring contractor will complete the stage flooring and commence the stair B platform flooring. The plumbing contractor will be setting hot water valves at all sinks and continue the commissioning process. The mechanical contractor will continue with equipment commissioning all all equipment. The mechanical contractor will continue balancing the supply and return air system. The controls contractor will continue integrating equipment into the building management system. The controls contractor will commense building commissioning effort with the MSBA third party commissioning agent. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1. The fire protection contractor will continue sprinkler head install in the stem patio ceiling. The electrical contractor will continue stem patio light installation. The electrical contractor will continue security system programming. The third party commissioning agent will continue review of all MEP systems. The tile contractor will continue installation of the cafeteria and main vestibule wall tile. The carpet contractor will continue carpet installation in the vestibules. Previous Article Project Update - Week of May 27th, 2024 Next Article Project Update - Week of June 10th, 2024 Print 152 Rate this article: 5.0