Jonathan May / Friday, May 24, 2024 / Categories: Uncategorized Project Update - Week of May 27th, 2024 Please see the below project update and list of activities scheduled for the week of May 27, 2024 The concrete contractor will continue forming and pouring the stem patio. The landscape contractor will continue spreading of loam, layout of trees and shrubs, and finalize irrigiation system install. The landscape contractor will commence hydroseading of the project's lawn areas around the building. The landscape contractor will continue installation of the kindergarten playground, curbs, and poured-in-place surface. The misc. metals contractor will continue the installation of the exterior rails. The waterproofing contractor will continue exterior expansion joint caulking and remaining interior caulking. The resilient flooring contractor will continue the level 1 lobby flooring. The resilient flooring contractor will finalize the floor landing and transition strips throughout the building. The painting contractor will continue final patching and painting of level 1. The ceiling contractor will continue installation of ceiling tiles on level 2 and level 1. The millwork and casework contractor will continue installation of the stair B and platform stair treads and media center seating. The wood flooring contractor will commence stage and stair B platform wood flooring system. The plumbing contractor will be setting hot water valves at all sinks and continue the commissioning process. The mechanical contractor will continue with equipment commissioning of the building's hot water system. The mechanical contractor will continue balancing the supply and return air system. The controls contractor will continue integrating equipment into the building management system. The controls contractor will commense building commissioning effort with the MSBA third party commissioning agent. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1. The fire protection contractor will commence sprinkler head install in the stem patio ceiling. The electrical contractor will continue stem patio light installation. The electrical contractor will continue security system programming. The specialties contractor will continue installation of the toilet accessories and partitions and lobby acoustic panels. The tile contractor will continue installation of the cafeteria and main vestibule wall tile. The carpet contractor will continue carpet installation in the media center and the vestibules. Previous Article Project Update - Week of May 20th, 2024 Next Article Project Update - Week of June 3rd, 2024 Print 151 Rate this article: 5.0