Jonathan May
/ Categories: Uncategorized

Project Update - Week of November 13th, 2023

Please see the below project update and list of activities scheduled for the week of November 13th 2023

  • The metal panel contractor will continue the cafeteria canopy ceiling installation 
  • The general trades contractor will continue metal framing activities in the cafeteria and kitchen
  • The generla trades contractor will continue drywall activities on level 1 A
  • The general trades contractor will continue taping level 1 area D
  • The painting contractor will continue level 2 and level 1 classrooms
  • The painting contractor will continue preperation of the gym CMU for paint
  • The ceiling contractor will commence ceiling grid on level 1
  • The fire protection contractor will continue overhead rough in of the exterior stem patio, cafeteria, and platform
  • The plumbing contractor will continue level 1 A in wall rough-in and insulation install
  • The mechanical contractor will continue VAV duct connections on level 1 D
  • The mechanical contractor will continue setting radiant panels into ceiling grid
  • The electrical contractor will continue overhead rough-in on level 1 area B gym and cafeteria
  • The electrical contractor will continue installation of level 2 lighting area C lighting fixtures
  • The tile contractor will continue installation of level 2 group bathroom floor and wall tile
  • The tile contractor will continue level 2 individual bathroom floor tile
  • The elevator contractor will continue installation and assist other trades work within the elevator pit
Previous Article Project Update - Week of November 6th, 2023
Next Article Project Update - Week of November 20th, 2023
Print
208 Rate this article:
No rating

Theme picker