Jonathan May / Friday, November 10, 2023 / Categories: Uncategorized Project Update - Week of November 13th, 2023 Please see the below project update and list of activities scheduled for the week of November 13th 2023 The metal panel contractor will continue the cafeteria canopy ceiling installation The general trades contractor will continue metal framing activities in the cafeteria and kitchen The generla trades contractor will continue drywall activities on level 1 A The general trades contractor will continue taping level 1 area D The painting contractor will continue level 2 and level 1 classrooms The painting contractor will continue preperation of the gym CMU for paint The ceiling contractor will commence ceiling grid on level 1 The fire protection contractor will continue overhead rough in of the exterior stem patio, cafeteria, and platform The plumbing contractor will continue level 1 A in wall rough-in and insulation install The mechanical contractor will continue VAV duct connections on level 1 D The mechanical contractor will continue setting radiant panels into ceiling grid The electrical contractor will continue overhead rough-in on level 1 area B gym and cafeteria The electrical contractor will continue installation of level 2 lighting area C lighting fixtures The tile contractor will continue installation of level 2 group bathroom floor and wall tile The tile contractor will continue level 2 individual bathroom floor tile The elevator contractor will continue installation and assist other trades work within the elevator pit Previous Article Project Update - Week of November 6th, 2023 Next Article Project Update - Week of November 20th, 2023 Print 208 Rate this article: No rating