Saturday Work - September 16th, 2023

The project will be working on the site this Saturday 9/16/23. Activities will consist of the following:

  • The general trades contractor will install level 1 door frames. 
  • The general trades contractor will commence installation of the area C exterior framing and sheathing leaveout. 
  • The electrical contractor will commence level 2 area C classroom overhead fixture accessory installation. 
  • The plumbing contractor will continue gas line installation in the gym and ktichen. 
  • The plumbing contractor will continue in-wall rough in on level 1 area D. 
  • The window contractor will continue weatherproofing the area C level 1 windows. 