Saturday Work - August 3rd, 2024

The project will be working on the site this Saturday 8/3/24. Activities will consist of the following:

Jonathan May 0 42 Article rating: No rating
  • The concrete contractor will continue forming and reinforcing the parent drop off loop concrete walks. 
  • The demolition contractor will continue demolition of the 1950s wing. 
  • The specialties contractor will continue addressing punchlist items. 
  • The site contractor will continue preparation for paving activities next week. 
  • The electrical contractor will continue addressing punchlist items.

Project Update - Week of August 5th, 2024

Please see the below project update and list of activities scheduled for the week of August 5th, 2024

Jonathan May 0 44 Article rating: 5.0
  • The demolition of the existing FloRo will continue the below grade cafeteria and mechanical spaces as well as slab on grade and footing removal of the 1950s wing. 
  • The demolition contractor will continue hauling of demolition debris.  
  • The site contractor will continue preparation of the phase 2B concrete walks. 
  • The site contractor will conduct final preparation for top course paving around the new FloRo. 
  • The paving contractor will pave the roadways. 
  • The concrete contractor will continue forming and pouring the bus loop, parent drop off loop, and phase 2B perimeter walks. 
  • All contractors’ will continue addressing punchlist items. 

Project Update - Week of July 29th, 2024

Please see the below project update and list of activities scheduled for the week of July 29th, 2024

Jonathan May 0 43 Article rating: 5.0
  • The demolition of the existing FloRo will continue the below grade cafeteria and mechanical spaces as well as slab on grade and footing removal. 
  • The site contractor will continue granite curb installation around the perimeter of Phase 2B. 
  • The site contractor will continue raising manhole frames and covers in preperation for final paving. 
  • The concrete contractor will continue forming and pouring the bus loop, parent drop off loop, and phase 2B perimeter walks. 
  • The landscape contractor will set the front entrance granite benches. 
  • All contractor's will continue addressing punchlist items. 

Saturday Work - July 20th, 2024

The project will be working on the site this Saturday 7/20/24. Activities will consist of the following:

Jonathan May 0 54 Article rating: 5.0
  • The demolition contractor will continue with the 1950's classroom wing removal. 
  • The site contractor will continue road way paving preperation and setting of veritical granite curb. 
  • The carpeting contractor will continue installation of the front entrance walk-off grille. 
  • The electrical contractor will continue terminations and programming. 

Project Update - Week of July 22nd, 2024

Please see the below project update and list of activities scheduled for the week of July 22nd, 2024

Jonathan May 0 65 Article rating: 5.0
  • The demolition of the existing FloRo will continue with the 1950s wings. 
  • The site contractor will continue granite curb installation at the bus and parent drop off loops. 
  • The site contractor will be finalizing installation of the south retaining wall. 
  • The site contractor will be setting grade of the parent drop off entrance road and pave initial binder course. 
  • The concrete contractor will continue forming and reinforcing of the remaining bus and parent drop of loop concrete areas. 
  • The project will conduct initial pre-inspection walk throughs ahead of final occupancy inspections. 
  • All contractor's will continue addressing punchlist items. 
RSS
245678910Last

Theme picker