Saturday Work - August 3rd, 2024 The project will be working on the site this Saturday 8/3/24. Activities will consist of the following: Jonathan May / Friday, August 2, 2024 0 42 Article rating: No rating The concrete contractor will continue forming and reinforcing the parent drop off loop concrete walks. The demolition contractor will continue demolition of the 1950s wing. The specialties contractor will continue addressing punchlist items. The site contractor will continue preparation for paving activities next week. The electrical contractor will continue addressing punchlist items. Read more
Project Update - Week of August 5th, 2024 Please see the below project update and list of activities scheduled for the week of August 5th, 2024 Jonathan May / Friday, August 2, 2024 0 44 Article rating: 5.0 The demolition of the existing FloRo will continue the below grade cafeteria and mechanical spaces as well as slab on grade and footing removal of the 1950s wing. The demolition contractor will continue hauling of demolition debris. The site contractor will continue preparation of the phase 2B concrete walks. The site contractor will conduct final preparation for top course paving around the new FloRo. The paving contractor will pave the roadways. The concrete contractor will continue forming and pouring the bus loop, parent drop off loop, and phase 2B perimeter walks. All contractors’ will continue addressing punchlist items. Read more
Project Update - Week of July 29th, 2024 Please see the below project update and list of activities scheduled for the week of July 29th, 2024 Jonathan May / Sunday, July 28, 2024 0 43 Article rating: 5.0 The demolition of the existing FloRo will continue the below grade cafeteria and mechanical spaces as well as slab on grade and footing removal. The site contractor will continue granite curb installation around the perimeter of Phase 2B. The site contractor will continue raising manhole frames and covers in preperation for final paving. The concrete contractor will continue forming and pouring the bus loop, parent drop off loop, and phase 2B perimeter walks. The landscape contractor will set the front entrance granite benches. All contractor's will continue addressing punchlist items. Read more
Saturday Work - July 20th, 2024 The project will be working on the site this Saturday 7/20/24. Activities will consist of the following: Jonathan May / Saturday, July 20, 2024 0 54 Article rating: 5.0 The demolition contractor will continue with the 1950's classroom wing removal. The site contractor will continue road way paving preperation and setting of veritical granite curb. The carpeting contractor will continue installation of the front entrance walk-off grille. The electrical contractor will continue terminations and programming. Read more
Project Update - Week of July 22nd, 2024 Please see the below project update and list of activities scheduled for the week of July 22nd, 2024 Jonathan May / Saturday, July 20, 2024 0 65 Article rating: 5.0 The demolition of the existing FloRo will continue with the 1950s wings. The site contractor will continue granite curb installation at the bus and parent drop off loops. The site contractor will be finalizing installation of the south retaining wall. The site contractor will be setting grade of the parent drop off entrance road and pave initial binder course. The concrete contractor will continue forming and reinforcing of the remaining bus and parent drop of loop concrete areas. The project will conduct initial pre-inspection walk throughs ahead of final occupancy inspections. All contractor's will continue addressing punchlist items. Read more