Project Update - Week of February 20th, 2024

Please see the below project update and list of activities scheduled for the week of February 20th, 2024

Jonathan May 0 39 Article rating: No rating
  • The general trades contractor will continue installation of level 2 doors and hardware. 
  • The general trades contractor will metal framing and drywall install of the Stair C & D closure walls. 
  • The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. 
  • The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. 
  • The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center.
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 area D classroom, corridor, and media center casework installation.
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue with level 2 classroom and bathroom sink installation.
  • The plumbing contractor will continue final plumbing connections in the Mechanical Room. 
  • The mechanical contractor will continue ceiling diffuser installation on level 1. 
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid.
  • The mechanical contractor will continue final duct connections to the roof top units received last week. 
  • The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. 
  • The electrical contractor will continue fire alarm finish installation on level 1.
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center.  
  • The tile contractor will continue level 1 corridor and admin area tile.
  • The tile contractor will continue level 1 group bathroom floor and wall tile. 
  • The specialties contractor will continue markerboard and tack board installation in the level 2 and level 1 classrooms. 

Project Update - Week of February 12th, 20234

Please see the below project update and list of activities scheduled for the week of February 12th, 2024

Jonathan May 0 60 Article rating: No rating
  • The general trades contractor will continue installation of level 2 doors and hardware. 
  • The general trades contractor will continue stair A drywall and taping.
  • The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. 
  • The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. 
  • The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center.
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will commence level 1 area D classroom and corridor casework installation.
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue with level 2 classroom and bathroom sink installation.
  • The plumbing contractor will continue final plumbing connections in the Mechanical Room. 
  • The mechanical contractor will continue ceiling diffuser installation on level 1. 
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid.
  • The mechanical contractor will continue final duct connections to the roof top units received last week. 
  • The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. 
  • The electrical contractor will continue fire alarm finish installation on level 1.
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1.  
  • The tile contractor will continue level 1 corridor tile.
  • The tile contractor will continue level 1 group bathroom floor and wall tile. 
  • The specialties contractor will continue tectum panel install in the gymnasium. 
  • The specialties contractor will continue markerboard and tack board installation in the level 2 classrooms. 

Saturday Work - February 3rd, 2024

The project will be working on the site this Saturday 2/3/24. Activities will consist of the following:

Jonathan May 0 59 Article rating: No rating
  • The general trades contractor will continue soffit mechanical chase construction in the admin and quiet eats area. 

Project Update - Week of February 5th, 2024

Please see the below project update and list of activities scheduled for the week of February 5th, 2024

Jonathan May 0 71 Article rating: No rating
  • The general trades contractor will continue hanging and taping of the Fire Pump room and the Lobby skylight soffits.
  • The general trades contractor will receive the level 2 door and hardware delivery. 
  • The resilient flooring contractor will continue flooring installation on level 1 area C classrooms. 
  • The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. 
  • The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center.
  • The ceiling contractor will continue ceiling grid install of the level 1 staff and student bathrooms. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will commence level 1 area D classroom casework installation.
  • The millwork and casework contractor will continue level 2 corridor cubby installation.
  • The millwork and casework contractor will continue window sill installation on level 2.
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue with level 2 classroom and bathroom sink installation. 
  • The plumbing contractor will continue final plumbing connections to mechanical equipment in the Mechanical Room. 
  • The mechanical contractor will continue ceiling diffuser installation on level 2. 
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid.
  • The electrical contractor will continue installation and wiring of level 1 admin area and media center light fixtures
  • The electrical contractor will continue fire alarm finish installation on level 1.
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1.  
  • The tile contractor will continue level 1 area corridor tile.
  • The tile contractor will continue level 1 group bathroom floor and wall tile. 
  • The gym equipment contractor will commence overhead gym equipment installation.

Project Update - Week of January 29th, 2024

Please see the below project update and list of activities scheduled for the week of January 29th, 2024

Jonathan May 0 55 Article rating: No rating
  • The general trades contractor will continue hanging and taping drywall in the Platform, Cafeteria, and Kitchen.
  • The general trades contractor will complete hanging and taping drywall in the Stair A.
  • The resilient flooring contractor will continue flooring installation on level 2 area A.
  • The resilient flooring contractor will commence flooring installation on level 1 area C classrooms. 
  • The painting contractor will continue painting the level 1 admin area and lobby. 
  • The painting contractor will continue painting the gym ceiling. 
  • The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center.
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 area C classroom casework installation.
  • The millwork and casework contractor will commence level 1 area D classroom casework installation.
  • The millwork and casework contractor will continue level 2 corridor cubby installation.
  • The millwork and casework contractor will continue window sill installation on level 2.
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue with level 2 classroom and bathroom sink installation. 
  • The plumbing contractor will continue final plumbing connections to mechanical equipment in the Mechanical Room. 
  • The mechanical contractor will continue ceiling diffuser installation on level 2. 
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid.
  • The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnasium
  • The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. 
  • The electrical contractor will continue wiring of the level 2 corridor and level 1 classroom light fixtures. 
  • The electrical contractor will continue fire alarm finish installation on level 2.
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1.  
  • The tile contractor will continue level 2 corridor tile. 
  • The tile contractor will continue level 1 area C corridor tile. 
  • The tile contractor will continue level 1 group bathroom tile. 