Project Update - Week of June 3rd, 2024

Please see the below project update and list of activities scheduled for the week of June 3rd, 2024.

Jonathan May 0 58 Article rating: 5.0
  • The site contractor will prepare for the existing Florence Roche utility disconnection. 
  • The landscape contractor will continue spreading of loam, layout of trees and shrubs, and finalize irrigiation system install. 
  • The landscape contractor will continue hydroseading of the project's lawn areas around the building. 
  • The landscape contractor will continue installation of the kindergarten playground, curbs, and poured-in-place surface. 
  • The misc. metals contractor will continue the installation of the exterior loading dock rails and front retaining wall railing. 
  • The resilient flooring contractor will continue final setting of transition strips. 
  • The painting contractor will continue final patching and painting of level 1.
  • The millwork and casework contractor will continue installation of the stair B and platform stair treads and media center seating & desks. 
  • The specialties contractor will commence admin accoustic panel install. 
  • The wood flooring contractor will complete the stage flooring and commence the stair B platform flooring. 
  • The plumbing contractor will be setting hot water valves at all sinks and continue the commissioning process. 
  • The mechanical contractor will continue with equipment commissioning all all equipment. 
  • The mechanical contractor will continue balancing the supply and return air system.
  • The controls contractor will continue integrating equipment into the building management system.
  • The controls contractor will commense building commissioning effort with the MSBA third party commissioning agent. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1. 
  • The fire protection contractor will continue sprinkler head install in the stem patio ceiling. 
  • The electrical contractor will continue stem patio light installation. 
  • The electrical contractor will continue security system programming. 
  • The third party commissioning agent will continue review of all MEP systems.  
  • The tile contractor will continue installation of the cafeteria and main vestibule wall tile. 
  • The carpet contractor will continue carpet installation in the vestibules. 

Project Update - Week of May 27th, 2024

Please see the below project update and list of activities scheduled for the week of May 27, 2024

Jonathan May 0 77 Article rating: 5.0
  • The concrete contractor will continue forming and pouring the stem patio. 
  • The landscape contractor will continue spreading of loam, layout of trees and shrubs, and finalize irrigiation system install. 
  • The landscape contractor will commence hydroseading of the project's lawn areas around the building. 
  • The landscape contractor will continue installation of the kindergarten playground, curbs, and poured-in-place surface. 
  • The misc. metals contractor will continue the installation of the exterior rails. 
  • The waterproofing contractor will continue exterior expansion joint caulking and remaining interior caulking. 
  • The resilient flooring contractor will continue the level 1 lobby flooring.
  • The resilient flooring contractor will finalize the floor landing and transition strips throughout the building. 
  • The painting contractor will continue final patching and painting of level 1.
  • The ceiling contractor will continue installation of ceiling tiles on level 2 and level 1. 
  • The millwork and casework contractor will continue installation of the stair B and platform stair treads and media center seating. 
  • The wood flooring contractor will commence stage and stair B platform wood flooring system. 
  • The plumbing contractor will be setting hot water valves at all sinks and continue the commissioning process. 
  • The mechanical contractor will continue with equipment commissioning of the building's hot water system.
  • The mechanical contractor will continue balancing the supply and return air system. 
  • The controls contractor will continue integrating equipment into the building management system.
  • The controls contractor will commense building commissioning effort with the MSBA third party commissioning agent. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1. 
  • The fire protection contractor will commence sprinkler head install in the stem patio ceiling. 
  • The electrical contractor will continue stem patio light installation. 
  • The electrical contractor will continue security system programming. 
  • The specialties contractor will continue installation of the toilet accessories and partitions and lobby acoustic panels. 
  • The tile contractor will continue installation of the cafeteria and main vestibule wall tile. 
  • The carpet contractor will continue carpet installation in the media center and the vestibules. 

Project Update - Week of May 20th, 2024

Please see the below project update and list of activities scheduled for the week of May 20th, 2024

Jonathan May 0 67 Article rating: 5.0
  • The concrete contractor will continue forming and pouring of the front entrance concrete.
  • The landscape contractor will continue spreading of loam, layout of trees and shrubs, and finalize irrigiation system install. 
  • The landscape contractor will continue installation of the kindergarten playground. 
  • The misc. metals contractor will continue the installation of the exterior rails. 
  • The waterproofing contractor will continue exterior expansion joint caulking. 
  • The resilient flooring contractor will continue the level 1 lobby flooring.
  • The painting contractor will continue final patching and painting of level 1.
  • The ceiling contractor will continue installation of ceiling tiles on level 2. 
  • The millwork and casework contractor will continue installation of the stair B and platform stair treads and media center seating. 
  • The plumbing contractor will be setting hot water valves at all sinks. 
  • The mechanical contractor will continue with equipment commissioning of the building's hot water system. 
  • The mechanical contractor will continue balancing the supply and return air system. 
  • The controls contractor will continue integrating equipment into the building management system. 
  • The controls contractor will commense building commissioning. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1. 
  • The fire protection contractor will commence sprinkler head install in the stem patio ceiling. 
  • The electrical contractor will commence stem patio light installation. 
  • The electrical contractor will commence security system programming. 
  • The specialties contractor will continue installation of the toilet accessories and partitions.

Project Update - Week of May 13th, 2024

Please see the below project update and list of activities scheduled for the week of May 13th, 2024

Jonathan May 0 70 Article rating: 5.0
  • The site contractor will continue preperation of the perimeter front concrete subgrade and setting of light pole bases. 
  • The concrete contractor will continue forming and pouring of the front entrance concrete.
  • The landscape contractor will continue spreading of loam and layout of trees and shrubs. 
  • The landscape contractor will continue installation of the kindergarten playground. 
  • The misc. metals contractor will continue the installation of the exterior rails. 
  • The waterproofing contractor will continue exterior expansion joint caulking. 
  • The general trades contractor will continue framing of the stem patio ceiling. 
  • The resilient flooring contractor will continue the level 1 lobby flooring.
  • The painting contractor will continue final painting of level 1.
  • The ceiling contractor will continue installation of ceiling tiles. 
  • The millwork and casework contractor will continue installation of the stair B and platform stair treads and media center seating. 
  • The plumbing contractor will continue final connections of kitchen equipment. 
  • ALL MEP contractor's will continue final connections to the food service equipment. 
  • The mechanical contractor will continue with equipment commissioning. 
  • The controls contractor will continue integrating equipment into the building management system. 
  • The controls contractor will commense building commissioning. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1  
  • The specialties contractor will continue installation of the toilet accessories and partitions.
  • The shade contractor will continue shade installation in the level 1 classrooms. 

Project Update - Week of April 22nd, 2024

Please see the below project update and list of activities scheduled for the week of April 22nd, 2024

Jonathan May 0 84 Article rating: No rating
  • The site contractor will continue preperation of the perimeter front concrete subgrade
  • The concrete contractor will continue pouring of the outdoor learning lab. 
  • The waterproofing contractor will continue exterior expansion joint caulking. 
  • The general trades contractor will continue level 1 door and hardware installation. 
  • The general trades contractor will commence insulation and framing of the stem patio ceiling. 
  • The resilient flooring contractor will continue the level 1 corridor flooring.
  • The painting contractor will continue final painting of the level 2 and level 1. 
  • The ceiling contractor will continue the lobby ceiling grid and panel installation. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1.
  • The millwork and casework contractor will continue installation of the cafeteria acoustic panels. 
  • The millwork and casework contractor will continue the platform subfloor installation and the media center seating. 
  • The plumbing contractor will continue level 1 classroom sink installation and kitchen equipment connections. 
  • ALL MEP contractor's will continue final connections to the food service equipment. 
  • The mechanical contractor will continue with equipment commissioning. 
  • The controls contractor will continue integrating equipment into the building management system. 
  • The electrical contractor will continue installation of the lobby light fixtures. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1  
  • The specialties contractor will continue installation of the toilet accessories and partitions.
  • The shade contractor will continue shade installation in the level 1 classrooms. 
RSS
135678910Last

Theme picker