Project Update - Week of December 19th 2022 Please see the below project update and list of activities scheduled for the week of December 19th 2022 Jonathan May / Friday, December 16, 2022 0 361 Article rating: No rating The electrical enabling contractor shall complete permanent power conduit installation to the main electric room. The site contractor shall continue with the excavation and installation of the new drainage line and structures along the projects site access road. The structural steel contractor will mobilize to site and begin receiving steel deliveries. The structural steel contractor shall commence steel erection of the Area C Classroom Wing. Read more
Project Update - Week of October 11th 2022 Jonathan May / Friday, October 7, 2022 0 361 Article rating: No rating Please see the below project update and list of activities scheduled for the week of October 11th 2022. The athletic track line stripper will commence track markings. The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas B. The site contractor will commence loading dock footing backfill. The site contractor will continue installation of the site drainage system below the proposed perimeter access road. The site contractor will continue installation of the site water utility system below the proposed perimeter access road. The site contractor will continue various grading activities around the site. The site contractor will continue underslab plumbing excavation. The site contractor will prep and set the BESS system vault and transformer pad. The concrete contractor will continue forming and placing the loading dock and site wall foundation. The concrete contractor will continue pouring the interior gym strip footing. The concrete contractor will continue forming and placing the Area A & B interior concrete foundations. The plumbing enabling contractor will continue layout and installation of the underslab plumbing in Area C. Read more
Project Update - Week of October 3rd 2022 Jonathan May / Friday, September 30, 2022 0 379 Article rating: No rating Please see the below project update and list of activities scheduled for the week of October 3rd 2022. The track surface contractor will continue the track surface installation The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas A & B. The site contractor will continue foundation excavation of the Area B site wall, the loading dock, and the gym interior strip footing. The site contractor will continue installation of the site drainage system below the proposed perimeter access road. The site contractor will continue installation of the site water utility system below the proposed perimeter access road. The site contractor will continue various grading activities around the site. The site contractor will begin building underslab plumbing excavation. The concrete contractor will continue forming and placing perimeter concrete foundations in Area B. The concrete contractor will begin forming and installing rebar for the loading dock deep footing. The concrete contractor will continue pouring the interior gym strip footing. The concrete contractor will continue forming and placing the Area A & B interior concrete foundations. The plumbing enabling contractor will begin layout and installation of the underslab plumbing in Area C. Read more
Project Update - Week of September 26th 2022 Jonathan May / Friday, September 23, 2022 0 384 Article rating: No rating Please see the below project update and list of activities scheduled for the week of September 26th 2022. The track surface contractor will finalize layout and commence the track surface installation. The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas A & B. The site contractor will continue foundation excavation of Area B. The site contractor will continue installation of the site drainage system below the proposed perimeter access road. The site contractor will continue installation of the site water utility system below the proposed perimeter access road. The site contractor will continue various grading activities around the site. The concrete contractor will continue forming and placing perimeter concrete foundations in Area B. The concrete contractor will continue forming and placing the Area A & B interior concrete foundations. Read more
Project Update - Week of September 19th 2022 Jonathan May / Friday, September 16, 2022 0 459 Article rating: No rating Please see the below project update and list of activities scheduled for the week of September 19th 2022. The irrigation with complete final position of irrigation heads. The track surface contractor will begin placing of the synthetic track surface. The electrical contractor in coordiantion with GELD will complete the ductbanks to Champney Street and connect to the new utility poles provided by GELD. The concrete contractor will continue forming and placing concrete foundations in Areas A & B. Concrete placements are tentatively scheduled for Monday, 9/19, Wednesday, 9/21, and Friday, 9/23. The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas C & D. The site contractor will continue foundation excavation of Areas A & B. The site contractor will continue utility installation below the proposed perimeter access road. The site contractor will continue various grading activities around the site. Read more