Project Update - Week of September 19th 2022

Jonathan May 0 265 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of September 19th 2022. 

  • The irrigation with complete final position of irrigation heads. 
  • The track surface contractor will begin placing of the synthetic track surface. 
  • The electrical contractor in coordiantion with GELD will complete the ductbanks to Champney Street and connect to the new utility poles provided by GELD. 
  • The concrete contractor will continue forming and placing concrete foundations in Areas A & B.  
  • Concrete placements are tentatively scheduled for Monday, 9/19, Wednesday, 9/21, and Friday, 9/23. 
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas C & D.  
  • The site contractor will continue foundation excavation of Areas A & B. 
  • The site contractor will continue utility installation below the proposed perimeter access road.
  • The site contractor will continue various grading activities around the site. 

Project Update - Week of August 29th 2022

Jonathan May 0 246 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of 8/29.

  • Exporting excess materials from the site shall continue this week.   
  • The fencing contractor will complete the athletic field retaining wall fence installation. 
  • The irrigation system will be completed
  • The drainage structure covers will be installed
  • The electrical contractor will commence providing power to the new athletic field shed location 
  • The concrete contractor will continue foundation construction for the classroom wings Area C & D. 
  • The site contractor will continue to excavate the Area A & B foundations. 
  • The electrical and site contractors will continue the electrical ductbank installation down Champney Street. 
  • The site contractor will continue various grading activities around the site. 

Project Update - Week of May 13th 2022

Please see the below project update and list of activities scheduled for the week of 5/16.

Jonathan May 0 355 Article rating: 5.0
  • Complete Con-Com and Stormwater Agent inspection of erosion control measures. 
  • The site contractor will begin stripping topsoil at the new track & field location.
  • The site contractor will begin demolition of existing field equipment, fencing, benches, etc.
  • Electrical and plumbing contractors will complete the construction trailer electrical and plumbing hookups. 

 

Project Update - Week of May 6th 2022

Please see the below project update and list of activities scheduled for the week of 5/9.

Jonathan May 0 329 Article rating: 5.0
  • The fence contractor will complete the driven post and fence installation.
  • The site contractor will complete the installation of erosion control measures along the perimeter of the construction site. 
  • The project will conduct the perimeter erosion control and SWPPP inspections with the town Conservation Committee Inspector and the Storm Water Advisory Agent.  
  • The site contractor will complete the implementation of the temporary construction access road. 
  • The site contractor will also mobilize additional earth moving equipment. 

Project Update - Week of April 29th 2022

Jonathan May 0 371 Article rating: 5.0

Site mobilization activities have continued this week. Please see the below project update and list of activities scheduled for the week of 5/2. 

  • The Surveyor's and layout engineers will continue to establish the construction area boundaries allowing all further work to be laid out. 
  • The temporary construction fence installation will continue: 
    • Continue layout of the remaining construction fence around the rear of the site. 
    • Continue driving posts and hanging of fence along the rear of the site. 
    • Begin preparation for all remaining auxiliary construction fence access gates. 
  • The site contractor will commence instllation of erosion control measures. 
  • The temporary construction access road activities will commence. 
  • Initial tree removal will commence. 
RSS
First5678910111214

Theme picker