Project Update - Week of July 10th 2023

Please see the below project update and list of activities scheduled for the week of July 10th 2023

Jonathan May 0 130 Article rating: No rating
  • The general trades contractor will continue exterior framing & sheathing in Areas A & B. 
  • The general trades contractor will continue layout and interior framing on level 2 Areas A & B. 
  • The waterproofing contractor will continue installation of waterproofing membrane in Areas A & B. 
  • The masonry contractor will continue installation of exterior masonry veneer in Areas A & B
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas D & A, and Level 1 Area D. 
  • The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. 
  • The fire protection contractor will continue installation of fire protection pipe on Level 1 Area C. 
  • The window contractor will continue with installation of the metal windows in Area C & D.

Project Update - Week of June 19th, 2023

Please see the below project update and list of activities scheduled for the week of June 19th 2023

Jonathan May 0 146 Article rating: No rating
  • The concrete contractor shall complete the preperation of the Slab on Grades in Area A and Gymnasium of the building.
  • Concrete placement of of the gymnasium is tentatively scheduled for Thursday, 6.22. 
  • The misc metals contractor will continue erection of Stair C. 
  • The general trades contractor will continue exterior framing in areas A & B. 
  • The general trades contractor will continue layout and interior framing on level 2 areas C & D. 
  • The general trades contractor will continue layout of interior walls on level 2 A. 
  • The waterproofing contractor will continue installation of waterproofing membrane in areas A & B. 
  • The masonry contractor will continue installation of exterior masonry veneer in Areas C & D. 
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas C, D, & A, and Level 1 Area C. 
  • The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. 
  • The fire protection contractor will continue installation of fire protection pipe on Level 2 Area A. 
  • The roofing contractor will ocmmence installation of the roofing system on the Area B low roof. 

Project Update - Week of June 6th, 2023

Please see the below project update and list of activities scheduled for the week of June 6th, 2023.

Jonathan May 0 162 Article rating: No rating
  • The sitework contractor will commence preperation of the Slab on Grade in Area A and the Gym
  • The general trades contractor will continue exterior framing in areas A & B. 
  • The waterproofing contractor will continue installation of waterproofing membrane in areas A & B.
  • The masonry contractor will continue installation of masonry veneer in areas C & D. 
  • The general trades contractor will continue interior framing in Area C & D Level 2 classroom wings. 
  • The mechanical contractor will continue installation of overhead mechanical duct and pipping in level 2 A and level 1 C & D. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping in level 2 C, D, & A, and level 1 C. 
  • The electrical contractor will continue installation of temporary lighting in the Gym. 
  • The electrical contractor will continue installation of overhead rough-in on level 2 A and in-wall rough-in on level 2 C&D. 
  • The fire protection contractor will continue installation of fire protection pipe on level 2.

Project Update - Week of April 10th, 2023

Please see the below project update and list of activities scheduled for the week of April 10th, 2023

Jonathan May 0 170 Article rating: No rating
  • The site contractor will continue placing and compacting gravel for the entrance road way.  Paving of this area is scheduled for the week of 4/17 while the District is on Spring Break.
  • The site contractor will continue with the excavation and sub-grade prep for the remaining UG plumbing in Area B of the building.
  • The site contractor will continue preperation of the classroom wing slab on grade. 
  • The general trades contractor shall continue with the lay-out and installation of roof blocking at mechanical equipment and penetration locations.
  • The concrete contractor will prepare to place the slab on deck for Level 2 Area A & B. 
  • The general trades contractor will continue layout and framing of exterior walls on the 2nd level classroom wings. 
  • The mechanical contractor will continue with the lay-out of duct hangers on the second level of Area C of the building.
  • The plumbing contractor will continue with the installation of roof drain bodies on Areas A & B of the building. 
  • The plumbing contractor will continue with the installation of UG plumbing in Area B of the building.
  • The roofing contractor shall continue with the installation of roof dense deck and AVB on the roof.
  • The electrical contractor shall commence with the installation of temp power and lighting provisions on the second level of Area C of the building.
  • The masonry contractor shall commence errection of the CMU elevator shaft. 
  • The waterproofing contractor shall commence the waterproofing membrane installation at the top of the foundation wall. 

Project Update Week of March 13th 2023

Please see the below project update and list of activities scheduled for the week of March 13th 2023

Jonathan May 0 185 Article rating: No rating
  • The site contractor will begin the installation of drainage infilitration system IT-2 on the South-West side of the site.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking.
  • The general trades contractor will continue framing activities including knee walls on the roof levels and exterior beam infills on the perimeter of Areas C, D, & A.
  • The concrete contractor will continue preparation of the slab on deck and installation of concrete rebar and welded wire mesh in all level 2 areas.
  • The plumbing contractor will continue to layout roof and level 2 openings as well as install level 2 slab on deck sleeves. 
  • The building electrical contractor will continue layout and installation of underslab electrical and telecommunications conduit. 
RSS
First56789101214

Theme picker