Saturday Work - September 16th, 2023

The project will be working on the site this Saturday 9/16/23. Activities will consist of the following:

Jonathan May 0 157 Article rating: No rating
  • The general trades contractor will install level 1 door frames. 
  • The general trades contractor will commence installation of the area C exterior framing and sheathing leaveout. 
  • The electrical contractor will commence level 2 area C classroom overhead fixture accessory installation. 
  • The plumbing contractor will continue gas line installation in the gym and ktichen. 
  • The plumbing contractor will continue in-wall rough in on level 1 area D. 
  • The window contractor will continue weatherproofing the area C level 1 windows. 

Project Update - Week of September 18th, 2023

Please see the below project update and list of activities scheduled for the week of 9/18.

Jonathan May 0 159 Article rating: No rating
  • The site contractor will commence subgrade preperation of the outdoor learning lab concrete walks. 
  • The masonry contractor will continue masonry install at the courtyard bump outs. 
  • The window contractor will continue installation of windows on level 1 area B.
  • The window contractor will continue waterproofing of installed windows on level 1 area C &D. 
  • The window contractor will commence installation of exterior storefronts.
  • The metal panel contractor will continue metal panel installation of the low roof translucent panel perimeter and the area A west bumpout. 
  • The general trades contractor will continue interior metal framing on level 1 area A. 
  • The general trades contractor will continue in-wall blocking on level 1 area A. 
  • The general trades contractor will commence interior insulation on level 1 area C. 
  • The general trades contractor will continue gypsum board installation on level 2 area A and level 1 area C & D
  • The general trades contractor will continue taping on level 2 area A. 
  • The general trades contractor will continue buildout of the telecommunciations rooms. 
  • The painting contractor will continue painting of level 2 area C & D. 
  • The fire protection contractor will continue sprinkler rough in on level 1 area A. 
  • The plumbing contractor will continue in-wall rough in on level 1 Area D & A. 
  • The plumbing contractor will continue pipe insullation on level 2 A and level 1 C. 
  • The plumbing contractor will continue installation of the cafeteria canopy roof drains. 
  • The plumbing and mechanical contractor will continue buildout of the mechanical room. 
  • The plumbing contractor will commence kitchen underground installation. 
  • The mechanical contractor will continue installation of the level 2 VAVs. 
  • The mechanical contractor will continue duct insulation on level 1 area D and C. 
  • The mechanical contractor will commence radiant heat panel installation in the level 2 area C classrooms. 
  • The electrical contractor will continue buildout of the electric rooms. 
  • The electrical contractor will continue overhead rough in in the gym and cafeteria. 
  • The electrical contractor will continue in-wall rough in on level 1 area A. 
  • The electrical contractor will commence classroom overhead fixture accessory installation on level 2 area C. 
  • The electrical contractor will continue telecommunications room buildout. 

Project Update - Week of September 11th, 2023

Please see the below project update and list of activities scheduled for the week of 9/11.

Jonathan May 0 150 Article rating: No rating
  • The site contractor will commence subgrade preperation of the loading dock ramp and stairs. 
  • The roofing contractor will continue installation of the canopy roofing and the metal roof edge. 
  • The masonry contractor will continue masonry install at the courtyard bump outs. 
  • The window contractor will continue installation of windows on level 1 area B.
  • The window contractor will continue waterproofing of installed windows on level 1 area C &D. 
  • The metal panel contractor will continue metal panel installation of the low roof translucent panel perimeter. 
  • The general trades contractor will continue interior metal framing on level 1 area A. 
  • The general trades contractor will continue interior insulation on level 2. 
  • The general trades contractor will continue gypsum board installation on level 2 area A and level 1 area C & D
  • The general trades contractor will continue taping on level 2 area D & A. 
  • The general trades contractor will continue buildout of the telecommunciations rooms. 
  • The painting contractor will commence painting of level 2 area C & D. 
  • The concrete contractor will continue preperation of the loading dock ramp and stairs. 
  • The concrete contractor will pour the platform and stair B landing stairs. 
  • The fire protection contractor will continue sprinkler rough in on level 1 area A. 
  • The plumbing contractor will continue in-wall rough in on level 1 Area D & A. 
  • The plumbing contractor will continue pipe insullation on level 2 A and level 1 C. 
  • The plumbing contractor will continue installation of the cafeteria canopy roof drains. 
  • The plumbing and mechanical contractor will continue buildout of the mechanical room. 
  • The mechanical contractor will continue installation of the level 2 VAVs. 
  • The mechanical contractor will continue duct insulation on level 1 area D and C. 
  • The electrical contractor will continue buildout of the electric rooms. 
  • The electrical contractor will continue overhead rough in in the gym and cafeteria. 
  • The electrical contracotr will continue telecommunications room buildout. 
  • The electrical contractor will continue in-wall rough in on level 1 area D. 

Saturday Work - August 26th, 2023

The project will be working on the site this Saturday 8/26/23. Activities will consist of the following:

Jonathan May 0 192 Article rating: No rating
  • The plumbing contractor will continue gas pipe installation in the mechanical room. 
  • The mechanical contractor will continue mechanical pipe installation in the mechanical room. 

Project Update - Week of August 28th, 2023

Please see the below project update and list of activities scheduled for the week of August 28th, 2023

Jonathan May 0 164 Article rating: No rating
  • The metal panel contractor will continue installation of the the Area D metal panel bump out.
  • The window contractor will continue waterproofing of the window systems. 
  • The window contractor will continue window installation on level 2 A. 
  • The roofing contractor will continue installation metal roof edge install and low roof roofing system install. 
  • The general trades contractor will complete the low roof and main canopy roof edge blocking. 
  • The general trades contractor continue level 2 area A perimeter wall insulation. 
  • The general trades contractor will continue drywall installation on level 2 area D & A. 
  • The general trades contractor will continue in-wall blocking installation on level 1 C. 
  • the general trades contractor will continue taping in level 2 area C. 
  • The electrical contractor will continue electrical room build-out.
  • The electrical contractor continue in-wall electrical rough-in on level 1 area D. 
  • The fire protection contractor will continue sprinkler pipe rough-in on level 1 area A & B. 
  • The mechanical contractor will continue overhead duct installation on level 1 Area A. 
  • The mechanical contractor will continue in-wall duct installation on level 2 area B and level 1 area C. 
  • The mechanical controls contractor will continue in-wall rough-in on level 1 area C & D. 
  • The mechanical and plumbing contractors will continue mechanical room build-out. 
  • The plumbing contractor will continue plumbing pipe installation on level 1 area A. 
  • The concrete contractor will continue preperation and pouring of the platform and stair B subfloor concrete stairs. 
RSS
First7891012141516Last

Theme picker