Project Update - Week of March 6th 2023

Please see the below project update and list of activities scheduled for the week of March 6th 2023

Jonathan May 0 176 Article rating: No rating
  • The site contractor will continue with the installation of drainage infilitration system IT-1A on the South-West side of the site.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking.
  • The general trades contractor shall commence with framing activities including knee walls on the roof levels and exterior beam infills on the perimeter of Areas C & D of the building.  
  • The concrete contractor shall continue and complete forming and placing the reverse isolation boxes located in the slabs on grade of the building this week.  Concrete placements will be weather-temperature dependant.
  • The concrete contractor will continue preparation of the slab on deck and installation of concrete rebar and welded wire mesh in all level 2 areas.
  • The roofing contractor will continue installation of various roof AVB details needed to support the continuation of roof blocking activities. 
  • The building electrical contractor will mobilize to site and layout and installation of underslab electrical and telecommunications conduit. 

Project Update - Week of December 19th 2022

Please see the below project update and list of activities scheduled for the week of December 19th 2022

Jonathan May 0 187 Article rating: No rating
  • The electrical enabling contractor shall complete permanent power conduit installation to the main electric room. 
  • The site contractor shall continue with the excavation and installation of the new drainage line and structures along the projects site access road. 
  • The structural steel contractor will mobilize to site and begin receiving steel deliveries. 
  • The structural steel contractor shall commence steel erection of the Area C Classroom Wing. 

Project Update - Week of October 11th 2022

Jonathan May 0 204 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of October 11th 2022. 

  • The athletic track line stripper will commence track markings. 
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas B.  
  • The site contractor will commence loading dock footing backfill. 
  • The site contractor will continue installation of the site drainage system below the proposed perimeter access road.
  • The site contractor will continue installation of the site water utility system below the proposed perimeter access road. 
  • The site contractor will continue various grading activities around the site.
  • The site contractor will continue underslab plumbing excavation. 
  • The site contractor will prep and set the BESS system vault and transformer pad. 
  • The concrete contractor will continue forming and placing the loading dock and site wall foundation. 
  • The concrete contractor will continue pouring the interior gym strip footing. 
  • The concrete contractor will continue forming and placing the Area A & B interior concrete foundations.
  • The plumbing enabling contractor will continue layout and installation of the underslab plumbing in Area C.  

Project Update - Week of October 3rd 2022

Jonathan May 0 219 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of October 3rd 2022. 

  • The track surface contractor will continue the track surface installation
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas A & B.  
  • The site contractor will continue foundation excavation of the Area B site wall, the loading dock, and the gym interior strip footing. 
  • The site contractor will continue installation of the site drainage system below the proposed perimeter access road.
  • The site contractor will continue installation of the site water utility system below the proposed perimeter access road. 
  • The site contractor will continue various grading activities around the site.
  • The site contractor will begin building underslab plumbing excavation. 
  • The concrete contractor will continue forming and placing perimeter concrete foundations in Area B. 
  • The concrete contractor will begin forming and installing rebar for the loading dock deep footing. 
  • The concrete contractor will continue pouring the interior gym strip footing. 
  • The concrete contractor will continue forming and placing the Area A & B interior concrete foundations.
  • The plumbing enabling contractor will begin layout and installation of the underslab plumbing in Area C.  

Project Update - Week of September 26th 2022

Jonathan May 0 208 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of September 26th 2022. 

  • The track surface contractor will finalize layout and commence the track surface installation.
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas A & B.  
  • The site contractor will continue foundation excavation of Area B. 
  • The site contractor will continue installation of the site drainage system below the proposed perimeter access road.
  • The site contractor will continue installation of the site water utility system below the proposed perimeter access road. 
  • The site contractor will continue various grading activities around the site.
  • The concrete contractor will continue forming and placing perimeter concrete foundations in Area B. 
  • The concrete contractor will continue forming and placing the Area A & B interior concrete foundations.

 