Project Update - Week of December 4th, 2023 Please see the below project update and list of activities scheduled for the week of 12/4. Jonathan May / Friday, December 1, 2023 0 4 Article rating: No rating The general trades contractor will continue metal framing activities in the cafeteria and kitchen The general trades contractor will continue drywall activities on level 1 A, Lobby and admin area. The general trades contractor will commence drywall of the classroom wing stairwell The general trades contractor will continue in-wall blocking and drywall installation in the media center The general trades contractor will continue taping level 1 area D and A The painting contractor will continue initial coats of level 1 classrooms The painting contractor will continue initial coats of the level 2 corridors The ceiling contractor will continue ceiling grid on level 1 C. The ceiling contractor will continue ceiling grid install in the level 2 area C corridor The millwork and casework contractor will continue casework installation on level 2 area C classrooms The fire protection contractor will continue overhead rough in of the cafeteria and platform The fire protection contractor will commence sprinkler head finish install into ceiling tile on level 2 area C The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation install The mechanical contractor will continue VAV duct connections on level 1 A The mechanical contractor will continue duct installation in the gym The mechanical contractor will continue setting radiant panels into completed ceiling grid The mechanical contractor will prepare for initial roof top unit deliveries in December The electrical contractor will continue overhead and in wall rough-in on level 1 area B cafeteria The electrical contractor will continue installation and wiring of level 2 area A light fixtures The tile contractor will continue grouting of level 2 single bathrooms The tile contractor will continue level 2 corridor tile The metal windows contractor will continue installation of the lobby skylights The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge Read more
Project Update - Week of November 27th, 2023 Please see the below project update and list of activities scheduled for the week of 11/27. Jonathan May / Monday, November 27, 2023 0 7 Article rating: No rating The general trades contractor will continue metal framing activities in the cafeteria and kitchen The generla trades contractor will continue drywall activities on level 1 A, Lobby and admin area. The general trades contractor will continue taping level 1 area D The general trades contractor will continue insulation and drywall installation of the project areas and stair D The painting contractor will continue initial coats of level 1 classrooms The panting contractor will prime and paint the Platform exposed structure The painting contractor will continue priming of the gym CMU The ceiling contractor will continue ceiling grid on level 1 C. The ceiling contractor will commence ceiling grid install in the level 2 area C corridor The millwork and casework contractor will commence casework installation on level 2 area C classrooms The fire protection contractor will continue overhead rough in of the cafeteria and platform The fire protection contractor will commence sprinkler head finish install into ceiling tile on level 2 area C The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation insulation install The mechanical contractor will continue VAV duct connections on level 1 D and A The mechanical contractor will continue setting radiant panels into completed ceiling grid The electrical contractor will continue overhead rough-in on level 1 area B cafeteria The electrical contractor will continue installation of level 2 area c light fixtures The electrical contractor will commence installation of level 2 area d light fixtures The electrical contractor will commence level 2 toilet room light fixture install The tile contractor will continue installation of level 2 single bathrooms The elevator contractor will continue installation and assist other trades work within the elevator pit The metal windows contractor will continue installation of the translucent panel in the gym and over the lobby The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge Read more
Saturday Work - November 18th, 2023 The project will be working on the site this Saturday 11/18/23. Activities will consist of the following: Jonathan May / Friday, November 17, 2023 0 18 Article rating: No rating The mechanical contractor will continue VAV duct tie-in on level 1 D. Read more
Project Update - Week of November 20th, 2023 Please see the below project update and list of activities scheduled for the week of November 20th 2023 Jonathan May / Friday, November 17, 2023 0 13 Article rating: No rating The general trades contractor will continue metal framing activities in the cafeteria and kitchen The generla trades contractor will continue drywall activities on level 1 A The general trades contractor will continue taping level 1 area D The general trades contractor will commence drywall of the project areas and the stair D The painting contractor will continue level 2 and level 1 classrooms The panting contractor will prime and paint the Platform exposed structure The ceiling contractor will continue ceiling grid on level 1 C The fire protection contractor will continue overhead rough in of the cafeteria and platform The plumbing contractor will continue level 1 B in wall rough-in and insulation install The mechanical contractor will continue VAV duct connections on level 1 D and A The mechanical contractor will continue setting radiant panels into ceiling grid The mechanical contractor will commence duct tie-in to the roof curbs The electrical contractor will continue overhead rough-in on level 1 area B gym and cafeteria The electrical contractor will continue installation of level 2 area c light fixtures The electrical contractor will commence installation of level 2 area d light fixtures The tile contractor will continue installation of level 2 single bathrooms The elevator contractor will continue installation and assist other trades work within the elevator pit The waterproofing contractor will commence waterproofing of the stem patio ceiling. The metal windows contractor will continue installation of the translucent panel in the gym The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge Read more
Project Update - Week of November 13th, 2023 Please see the below project update and list of activities scheduled for the week of November 13th 2023 Jonathan May / Friday, November 10, 2023 0 18 Article rating: No rating The metal panel contractor will continue the cafeteria canopy ceiling installation The general trades contractor will continue metal framing activities in the cafeteria and kitchen The generla trades contractor will continue drywall activities on level 1 A The general trades contractor will continue taping level 1 area D The painting contractor will continue level 2 and level 1 classrooms The painting contractor will continue preperation of the gym CMU for paint The ceiling contractor will commence ceiling grid on level 1 The fire protection contractor will continue overhead rough in of the exterior stem patio, cafeteria, and platform The plumbing contractor will continue level 1 A in wall rough-in and insulation install The mechanical contractor will continue VAV duct connections on level 1 D The mechanical contractor will continue setting radiant panels into ceiling grid The electrical contractor will continue overhead rough-in on level 1 area B gym and cafeteria The electrical contractor will continue installation of level 2 lighting area C lighting fixtures The tile contractor will continue installation of level 2 group bathroom floor and wall tile The tile contractor will continue level 2 individual bathroom floor tile The elevator contractor will continue installation and assist other trades work within the elevator pit Read more