Project Update - Week of July 8th, 2024

Please see the below project update and list of activities scheduled for the week of July 8th, 2024

Jonathan May 0 16 Article rating: 1.0
  • The demolition & abatement contractor has completed abatement of all interior spaces and will continue abatement of the roof. 
  • The demolition & abatement contractor will continue demolition of the existing FloRo Area C. 
  • The site contractor will continue subgrade preparation of all pavement areas. 
  • The site contractor will continue final grade setting in new pavement areas. 
  • The site contractor will commence layout and setting of granite curb. 
  • The concrete contractor will continue forming and reinforcing of the middle school sidewalk area and the loading dumpster pad.
  • The painting contractor will continue painting of exterior rails. 
  • The millwork and casework contractor will continue installation of the exterior benches.
  • The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. 
  • The MEP contractors will continue system pre-functional testing of the kitchen equipment. 
  • The electrical contractor will continue final system programming and pre-functional testing. 
  • All contractor's will continue addressing punchlist items. 

Saturday Work - June 29th, 2024

The project will be working on the site this Saturday 6/29/24. Activities will consist of the following:

Jonathan May 0 28 Article rating: No rating
  • The demolition and abatement contractor will continue abatement of the 1950s area A wing and demolition of the 1980s Area C wing.
  • The electrical contractor will continue final programming and setting of devices. 

Project Update - Week of July 1st, 2024

Please see the below project update and list of activities scheduled for the week of July 1st, 2024

Jonathan May 0 23 Article rating: No rating
  • The demolition & abatement contractor has completed abatement of the existing FloRo area B and will continue abatement of Area A.
  • The demolition & abatement contractor will continue demolition of the existing FloRo Area C. 
  • The site contractor will complete the installation of the entry road infiltration system. 
  • The site contractor will continue subgrade preparation of all pavement areas. 
  • The site contractor will commence final grade setting in new pavement areas. 
  • The concrete contractor will commence forming and reinforcing of the middle school sidewalk area and the dumpster pad.
  • The painting contractor will continue painting of exterior rails. 
  • The millwork and casework contractor will continue installation of the exterior benches.
  • The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. 
  • The MEP contractors will continue system pre-functional testing of the kitchen equipment. 
  • The electrical contractor will continue final system programming. 
  • All contractor's will continue addressing punchlist items. 

Saturday Work - June 22nd, 2024

The project will be working on the site this Saturday 6/22/24. Activities will consist of the following:

Jonathan May 0 31 Article rating: No rating
  • The demolition and abatement contractor will continue abating the existing FloRo. 
  • The site contractor will continue subgrade preperation of the areas scheduled for new pavement.  

Project Update - Week of June 24th, 2024

Please see the below project update and list of activities scheduled for the week of June 24th, 2024

Jonathan May 0 31 Article rating: No rating
  • The demolition contractor will continue abatement of the existing FloRo area B & A. 
  • The demolition contractor will continue disposal of the modular unit demolition material. 
  • The site contractor will continue infiltration system installation now that the south modular unit has been demolished. 
  • The site contractor will continue subgrade preperation of all pavement areas. 
  • The concrete contractor will continue prepparing front entrance concrete walks. 
  • The painting contractor will continue painting of exterior rails and structural steel. 
  • The millwork and casework contractor will continue installation of the media center desk and the exterior benches. 
  • The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. 
  • The MEP contractors will continue system pre-functional testing of the kitchen equipment. 
  • The electrical contractor will continue final system programming. 
  • All contractor's will continue addressing punchlist items. 