Saturday Work - March 9th, 2024

The project will be working on the site this Saturday 3/9/24. Activities will consist of the following:

Jonathan May 0 134 Article rating: No rating
  • The electrical contractor will work with GELD to energize the project's permenant electrical service. 

Project Update - Week of March 11th, 2024

Please see the below project update and list of activities scheduled for the week of March 11th, 2024

Jonathan May 0 152 Article rating: No rating
  • The general trades contractor will continue installation of level 2 and commence level 1 doors and hardware. 
  • The general trades contractor will continue metal framing and drywall install of the Stair C, D, & A closure walls. 
  • The general trades contractor will frame & drywall the main stair knee wall ahead of floor finishes. 
  • The resilient flooring contractor will continue the level 2 corridor flooring. 
  • The painting contractor will continue final painting of the level 2 area C classrooms. 
  • The ceiling contractor will continue cafeteria and kitchen ceiling installation. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 admin area casework install. 
  • The millwork and casework contractor will commence the stem patio cubby installation. 
  • The plumbing contractor will continue level 1 classroom sink installation. 
  • The plumbing and mechanical contractor will continue installing valve tags on level 2. 
  • The mechanical contractor will continue ceiling diffuser installation on level 1. 
  • The mechanical contractor will continue installing the cafeteria wall diffusers. 
  • The mechanical contractor will install the gym fan blades. 
  • The electrical contractor will continue installation of the lobby and kitchen light fixtures. 
  • The electrical contractor will commence energizing electrical panels supported by permenant power. 
  • The electrical contractor will continue fire alarm finish installation on level 1. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center.  
  • The tile contractor will continue level 1 corridor and admin area tile.
  • The tile contractor will commence the cafeteria wall tile.
  • The specialties contractor will continue installation of the toilet partitions. 
  • The site contractor will commence courtyard sitework preperation. 
  • The waterproofing and masonry contractor will re-mobilize to close in the project's level 2 loadout elevation. 
  • The misc. metals contractor will commence installation of the main stair railings. 

Project Update - Week of March 4th, 2024

Please see the below project update and list of activities scheduled for the week of March 4th, 2024

Jonathan May 0 167 Article rating: No rating
  • The general trades contractor will continue installation of level 2 doors and hardware. 
  • The general trades contractor will continue metal framing and drywall install of the Stair C, D, & A closure walls. 
  • The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. 
  • The resilient flooring contractor will commence the level 2 area D corridor flooring. 
  • The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. 
  • The painting contractor will continue final painting of the level 2 area C classrooms. 
  • The ceiling contractor will continue ceiling grid installation on level 1 admin area, media center, cafeteria, and lobby.
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 area D classroom, corridor, and media center casework installation.
  • The millwork and casework contractor will continue level 1 area a Admin Area caswork installation. 
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue with level 2 classroom and bathroom sink installation.
  • The plumbing contractor will commence level 1 classroom sink installation. 
  • The plumbing contractor will continue final plumbing connections in the Mechanical Room. 
  • The plumbing and mechanical contractor will continue installing valve tags on level 2. 
  • The mechanical contractor will continue ceiling diffuser installation on level 1. 
  • The mechanical contractor will continue installing the cafeteria wall diffusers. 
  • The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. 
  • The electrical contractor will continue fire alarm finish installation on level 1.
  • The electrical contractor will continue making final electrical wiringing connections in the main electric room. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center.  
  • The tile contractor will continue level 1 corridor and admin area tile.
  • The tile contractor will continue level 1 group bathroom floor and wall tile. 
  • The specialties contractor will continue markerboard and tack board installation in the level 2 and level 1 classrooms. 

Project Update - Week of February 26th, 2024

Please see the below project update and list of activities scheduled for the week of February 26th 2024

Jonathan May 0 141 Article rating: No rating
  • The general trades contractor will continue installation of level 2 doors and hardware. 
  • The general trades contractor will continue metal framing and drywall install of the Stair C & D closure walls. 
  • The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. 
  • The resilient flooring contractor will commence the level 2 area C corridor flooring. 
  • The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. 
  • The painting contractor will commence final painting of the level 2 area C classrooms. 
  • The ceiling contractor will continue ceiling grid installation on level 1 admin area, media center, and cafeteria. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 area D classroom, corridor, and media center casework installation.
  • The millwork and casework contractor will continue level 1 area a Admin Area caswork installation. 
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue with level 2 classroom and bathroom sink installation.
  • The plumbing contractor will commence level 1 classroom sink installation. 
  • The plumbing contractor will continue final plumbing connections in the Mechanical Room. 
  • The mechanical contractor will continue ceiling diffuser installation on level 1. 
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid on level 1. 
  • The mechanical contractor will continue making final connections to the entry vestibule cabinet unit heaters. 
  • The mechanical contractor will continue final duct connections to the roof top units.  
  • The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. 
  • The electrical contractor will continue fire alarm finish installation on level 1.
  • The electrical contractor will continue making final electrical wiringing connections in the main electric room. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center.  
  • The tile contractor will continue level 1 corridor and admin area tile.
  • The tile contractor will continue level 1 group bathroom floor and wall tile. 
  • The specialties contractor will continue markerboard and tack board installation in the level 2 and level 1 classrooms. 

Project Update - Week of February 20th, 2024

Please see the below project update and list of activities scheduled for the week of February 20th, 2024

Jonathan May 0 148 Article rating: No rating
  • The general trades contractor will continue installation of level 2 doors and hardware. 
  • The general trades contractor will metal framing and drywall install of the Stair C & D closure walls. 
  • The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. 
  • The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. 
  • The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center.
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 area D classroom, corridor, and media center casework installation.
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue with level 2 classroom and bathroom sink installation.
  • The plumbing contractor will continue final plumbing connections in the Mechanical Room. 
  • The mechanical contractor will continue ceiling diffuser installation on level 1. 
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid.
  • The mechanical contractor will continue final duct connections to the roof top units received last week. 
  • The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. 
  • The electrical contractor will continue fire alarm finish installation on level 1.
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center.  
  • The tile contractor will continue level 1 corridor and admin area tile.
  • The tile contractor will continue level 1 group bathroom floor and wall tile. 
  • The specialties contractor will continue markerboard and tack board installation in the level 2 and level 1 classrooms. 