Saturday Work - March 9th, 2024 The project will be working on the site this Saturday 3/9/24. Activities will consist of the following: Jonathan May / Friday, March 8, 2024 0 134 Article rating: No rating The electrical contractor will work with GELD to energize the project's permenant electrical service. Read more
Project Update - Week of March 11th, 2024 Please see the below project update and list of activities scheduled for the week of March 11th, 2024 Jonathan May / Friday, March 8, 2024 0 152 Article rating: No rating The general trades contractor will continue installation of level 2 and commence level 1 doors and hardware. The general trades contractor will continue metal framing and drywall install of the Stair C, D, & A closure walls. The general trades contractor will frame & drywall the main stair knee wall ahead of floor finishes. The resilient flooring contractor will continue the level 2 corridor flooring. The painting contractor will continue final painting of the level 2 area C classrooms. The ceiling contractor will continue cafeteria and kitchen ceiling installation. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2. The millwork and casework contractor will continue level 1 admin area casework install. The millwork and casework contractor will commence the stem patio cubby installation. The plumbing contractor will continue level 1 classroom sink installation. The plumbing and mechanical contractor will continue installing valve tags on level 2. The mechanical contractor will continue ceiling diffuser installation on level 1. The mechanical contractor will continue installing the cafeteria wall diffusers. The mechanical contractor will install the gym fan blades. The electrical contractor will continue installation of the lobby and kitchen light fixtures. The electrical contractor will commence energizing electrical panels supported by permenant power. The electrical contractor will continue fire alarm finish installation on level 1. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center. The tile contractor will continue level 1 corridor and admin area tile. The tile contractor will commence the cafeteria wall tile. The specialties contractor will continue installation of the toilet partitions. The site contractor will commence courtyard sitework preperation. The waterproofing and masonry contractor will re-mobilize to close in the project's level 2 loadout elevation. The misc. metals contractor will commence installation of the main stair railings. Read more
Project Update - Week of March 4th, 2024 Please see the below project update and list of activities scheduled for the week of March 4th, 2024 Jonathan May / Friday, March 1, 2024 0 167 Article rating: No rating The general trades contractor will continue installation of level 2 doors and hardware. The general trades contractor will continue metal framing and drywall install of the Stair C, D, & A closure walls. The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. The resilient flooring contractor will commence the level 2 area D corridor flooring. The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. The painting contractor will continue final painting of the level 2 area C classrooms. The ceiling contractor will continue ceiling grid installation on level 1 admin area, media center, cafeteria, and lobby. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2. The millwork and casework contractor will continue level 1 area D classroom, corridor, and media center casework installation. The millwork and casework contractor will continue level 1 area a Admin Area caswork installation. The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. The plumbing contractor will continue with level 2 classroom and bathroom sink installation. The plumbing contractor will commence level 1 classroom sink installation. The plumbing contractor will continue final plumbing connections in the Mechanical Room. The plumbing and mechanical contractor will continue installing valve tags on level 2. The mechanical contractor will continue ceiling diffuser installation on level 1. The mechanical contractor will continue installing the cafeteria wall diffusers. The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. The electrical contractor will continue fire alarm finish installation on level 1. The electrical contractor will continue making final electrical wiringing connections in the main electric room. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center. The tile contractor will continue level 1 corridor and admin area tile. The tile contractor will continue level 1 group bathroom floor and wall tile. The specialties contractor will continue markerboard and tack board installation in the level 2 and level 1 classrooms. Read more
Project Update - Week of February 26th, 2024 Please see the below project update and list of activities scheduled for the week of February 26th 2024 Jonathan May / Thursday, February 22, 2024 0 141 Article rating: No rating The general trades contractor will continue installation of level 2 doors and hardware. The general trades contractor will continue metal framing and drywall install of the Stair C & D closure walls. The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. The resilient flooring contractor will commence the level 2 area C corridor flooring. The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. The painting contractor will commence final painting of the level 2 area C classrooms. The ceiling contractor will continue ceiling grid installation on level 1 admin area, media center, and cafeteria. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2. The millwork and casework contractor will continue level 1 area D classroom, corridor, and media center casework installation. The millwork and casework contractor will continue level 1 area a Admin Area caswork installation. The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. The plumbing contractor will continue with level 2 classroom and bathroom sink installation. The plumbing contractor will commence level 1 classroom sink installation. The plumbing contractor will continue final plumbing connections in the Mechanical Room. The mechanical contractor will continue ceiling diffuser installation on level 1. The mechanical contractor will continue setting radiant panels into completed ceiling grid on level 1. The mechanical contractor will continue making final connections to the entry vestibule cabinet unit heaters. The mechanical contractor will continue final duct connections to the roof top units. The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. The electrical contractor will continue fire alarm finish installation on level 1. The electrical contractor will continue making final electrical wiringing connections in the main electric room. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center. The tile contractor will continue level 1 corridor and admin area tile. The tile contractor will continue level 1 group bathroom floor and wall tile. The specialties contractor will continue markerboard and tack board installation in the level 2 and level 1 classrooms. Read more
Project Update - Week of February 20th, 2024 Please see the below project update and list of activities scheduled for the week of February 20th, 2024 Jonathan May / Friday, February 16, 2024 0 148 Article rating: No rating The general trades contractor will continue installation of level 2 doors and hardware. The general trades contractor will metal framing and drywall install of the Stair C & D closure walls. The resilient flooring contractor will continue flooring installation of the level 1 area D classrooms. The painting contractor will continue painting the level 1 admin area, lobby, and cafeteria. The ceiling contractor will continue ceiling grid installation on level 1 admin area and media center. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2. The millwork and casework contractor will continue level 1 area D classroom, corridor, and media center casework installation. The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. The plumbing contractor will continue with level 2 classroom and bathroom sink installation. The plumbing contractor will continue final plumbing connections in the Mechanical Room. The mechanical contractor will continue ceiling diffuser installation on level 1. The mechanical contractor will continue setting radiant panels into completed ceiling grid. The mechanical contractor will continue final duct connections to the roof top units received last week. The electrical contractor will continue installation and wiring of level 1 admin area, media center, and cafeteria light fixtures. The electrical contractor will continue fire alarm finish installation on level 1. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 and Media Center. The tile contractor will continue level 1 corridor and admin area tile. The tile contractor will continue level 1 group bathroom floor and wall tile. The specialties contractor will continue markerboard and tack board installation in the level 2 and level 1 classrooms. Read more