Project Update - Week of June 12th, 2023

Please see the below project update and list of activities scheduled for the week of June 12th 2023

Tripp McElroy III 0 158 Article rating: No rating
  • The concrete contractor shall commence with the preperation of the Slab on Grades in Area A and Gymnasium of the building.
  • Concrete placement of Stairs A & D are tentatively scheduled for next week.
  • The misc metals contractor is scheduled to deliver and commence erection of Stair C. 
  • The general trades contractor will continue exterior framing in areas A & B. 
  • The waterproofing contractor will continue installation of waterproofing membrane in areas A & B.
  • The masonry contractor will continue installation of exterior masonry veneer in Areas C & D. 
  • The general trades contractor will continue interior framing in Area C & D Level 2 classroom wings. 
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas C, D, & A, and Level 1 Area C. 
  • The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and commence in-wall rough-in on Level 2 Areas C & D. 
  • The fire protection contractor will continue installation of fire protection pipe on Level 2 Area D.

Project Update - Week of June 6th, 2023

Please see the below project update and list of activities scheduled for the week of June 6th, 2023.

Jonathan May 0 159 Article rating: No rating
  • The sitework contractor will commence preperation of the Slab on Grade in Area A and the Gym
  • The general trades contractor will continue exterior framing in areas A & B. 
  • The waterproofing contractor will continue installation of waterproofing membrane in areas A & B.
  • The masonry contractor will continue installation of masonry veneer in areas C & D. 
  • The general trades contractor will continue interior framing in Area C & D Level 2 classroom wings. 
  • The mechanical contractor will continue installation of overhead mechanical duct and pipping in level 2 A and level 1 C & D. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping in level 2 C, D, & A, and level 1 C. 
  • The electrical contractor will continue installation of temporary lighting in the Gym. 
  • The electrical contractor will continue installation of overhead rough-in on level 2 A and in-wall rough-in on level 2 C&D. 
  • The fire protection contractor will continue installation of fire protection pipe on level 2.

Project Update - Week of May 22nd 2023

Please see the below project update and list of activities scheduled for the week of May 22nd 2023

Tripp McElroy III 0 161 Article rating: No rating
  • The general trades contractor will continue layout, framing & sheathing of exterior walls on the 1st & 2nd levels of Areas C & D. 
  • The general trades contractor shall continue with layout and commence top track installation of interior wall framing on the 2nd levels of Areas C & D.
  • The mechanical contractor will continue with the lay-out of duct hangers on the second level of Areas C & D of the building and continue with the installation of ductwork & mechanical piping.
  • The plumbing contractor will continue with the lay-out and installation of plumbing piping on the second level of Areas C & D of the building. 
  • The electrical contractor shall continue with the installation of temp power and lighting provisions on the first level of Areas A & B of the building.
  • The electrical contractor shall continue with in-wall electrical rough-in at the gymnasium CMU walls.
  • The electrical contractor shall continue with the overhead rough-in of electrical feeders on the second level of Areas C & D of the building.
  • The fire protection contractor shall commence with overhead rough-in of sprinkler piping on the second level of Area C.
  • The masonry contractor shall continue construction of the CMU walls in the gymnasium. 
  • The masonry shall continue with masonry veneer starter course on Area C of the building.  Masonry veneer activites on the exterior mock-up shall continue next week.
  • The waterproofing contractor shall continue with the installation of the waterproofing membrane on the exterior walls of Areas C & D of the building. 

Project Update - Week of May 8th 2023

Please see the below project update and list of activities scheduled for the week of May 8th 2023

Tripp McElroy III 0 177 Article rating: No rating
  • The general trades contractor shall continue with the lay-out and installation of roof blocking at mechanical equipment and penetration locations on the cafeteria roof.
  • The general trades contractor will continue layout, framing & sheathing of exterior walls on the 1st & 2nd levels of Areas C & D. 
  • The general trades contractor shall continue with layout of interior wall framing on the 2nd levels of Areas C & D.
  • The concrete contractor shall continue with slab on grade prep activities in Area A & B of the building.  Slab on grade placement in Area B of the building is tentatively scheduled for Thursday 5/11.  Concrete trucks are scheduled to arrive to the site at 9AM after morning drop-off for the campus is complete. 
  • The mechanical contractor will continue with the lay-out of duct hangers on the second level of Areas C & D of the building and continue with the installation of ductwork & mechanical piping.
  • The plumbing contractor will continue with the lay-out and installation of plumbing piping on the second level of Areas C & D of the building. 
  • The roofing contractor shall continue with the installation of roof dense deck and AVB on Areas B of the building.  
  • The electrical contractor shall continue with the installation of temp power and lighting provisions on the first level of Areas C & D of the building.
  • The electrical contractor shall continue with in-wall electrical rough-in at the gymnasium CMU walls.
  • The electrical contractor shall commence with the overhead rough-in of electrical feeders on the second level of Areas C & D of the building.
  • The masonry contractor shall continue construction of the CMU walls in the gymnasium. 
  • The waterproofing contractor shall continue with the installation of the waterproofing membrane on the exterior walls of Area C of the building. 

Saturday Work - May 6th 2023

The project will be working on the site this Saturday 5/6/23. Activities will consist of the following:

Tripp McElroy III 0 157 Article rating: No rating
  • The mechanical contractor shall continue with the installation of mechanical piping on the second level of Area C in the building.
  • The general trades contractor shall continue with the installation of exterior sheathing on Areas C & D of the building.   

This weekend work schedule has been communicated and coordinated with the Town Manager's Office.

RSS
First89101113151617Last

Theme picker