Project Update - Week of May 6th 2022

Please see the below project update and list of activities scheduled for the week of 5/9.

Jonathan May 0 328 Article rating: 5.0
  • The fence contractor will complete the driven post and fence installation.
  • The site contractor will complete the installation of erosion control measures along the perimeter of the construction site. 
  • The project will conduct the perimeter erosion control and SWPPP inspections with the town Conservation Committee Inspector and the Storm Water Advisory Agent.  
  • The site contractor will complete the implementation of the temporary construction access road. 
  • The site contractor will also mobilize additional earth moving equipment. 

Project Update - Week of April 29th 2022

Jonathan May 0 370 Article rating: 5.0

Site mobilization activities have continued this week. Please see the below project update and list of activities scheduled for the week of 5/2. 

  • The Surveyor's and layout engineers will continue to establish the construction area boundaries allowing all further work to be laid out. 
  • The temporary construction fence installation will continue: 
    • Continue layout of the remaining construction fence around the rear of the site. 
    • Continue driving posts and hanging of fence along the rear of the site. 
    • Begin preparation for all remaining auxiliary construction fence access gates. 
  • The site contractor will commence instllation of erosion control measures. 
  • The temporary construction access road activities will commence. 
  • Initial tree removal will commence. 

Project Update - Week of April 25th 2022

Tripp McElroy III 0 336 Article rating: 5.0

The Florence Roche Elementary School construction project has commenced!  Site mobilization activites commenced this week on-site during school vacation.  Please see below a project update and list of activities scheduled for the week of 4/25.

  • Temporary construction fence:
    • Complete the hanging of fence on posts previously driven behind Middle School South, adjacent to the existing ball field on Monday 4/25.
    • Continue driving posts and hanging of fence along the access road that connects to Champney Street.
    • Prep and set the fence gates at Gates A, B1, B2.  The balance of ancillary Gates shall follow.
    • Installation of fencing shall continue around the perimeter of the project site.
  • Setting, leveling and assembly of the double wide office trailer shall commence on Monday 4/25.
  • The site contractor shall commence establishing site and building layout control onsite Tuesday 4/26.
  • Installation of erosion control measures on the project site are scheduled to commence on Wednesday 4/27