Project Update - Week of February 20th 2023

Tripp McElroy III 0 171 Article rating: No rating
  • The site contractor shall complete the installation of drainage infilitration system IT-1B on the South-West side of the site.
  • The site contractor shall re-commence and complete the 24" drainage line on the South-West side of the site. 
  • The site contractor shall re-commence the excavation and construction of retaining wall #9 on the South-West side of the site.
  • The general trades contractor shall continue with the lay-out and installation of perimeter roof blocking on Area A of the building.  
  • The concrete contractor shall continue with forming and placing the reverse isolation boxes located in the slabs on grade of the building this week.
  • There will not be any work activities on the project site Monday 2/20 due to the President's Day Holiday. 

Project Update - Week of February 13th 2023

Please see the below project update and list of activities scheduled for the week of February 13th 2023

Tripp McElroy III 0 177 Article rating: No rating
  • The site contractor shall continue with the installation of drainage infilitration system IT-1B on the South-West side of the site.
  • The site contractor shall commence with the removal of unsuitable soil materials on Wednesday 2/15 and is tentatively scheduled to be completed by the end of the week.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking on Areas C & D of the building.  
  • The concrete contractor shall commence with forming and placing the reverse isolation boxes located in the slabs on grade of the building this week.
  • There will not be any work activities on the project site Monday 2/20 due to the President's Day Holiday. 

Project Update - Week of February 6th 2023

Please see the below project update and list of activities scheduled for the week of February 6th 2023

Tripp McElroy III 0 188 Article rating: 5.0
  • The site contractor shall commence with the installation of crushed stone materials below the slab on grade in Area C of the building.
  • The structural steel contractor shall continue with decking & detailing activities in Area B of the building.  Portions of this work is weather dependant.  They will commence with demobilizing activites on the project site.  
  • The general trades contractor shall commence with the lay-out and installation of roof blocking on Area C of the building.  
  • The roofing contractor is scheduled to complete the set-up of safety railings on the roof levels of the building next week. 

Project Update - Week of January 30th 2023

Please see the below project update and list of activities scheduled for the week of January 30th 2023

Tripp McElroy III 0 187 Article rating: No rating
  • The site contractor shall continue with the excavation and installation of drainage lines in the outdoor learning space between Areas C & D of the building.   
  • The structural steel contractor shall continue with decking & detailing activities in Areas A & B of the building.  Portions of this work is weather dependant.   
  • The general trades contractor shall continue with mobilizing activities, including the delivery of a storage container and building materials to support safety items and roof blocking to the project site.
  • The roofing contractor is scheduled to have a crane onsite Thursday 2/2 to hoist and commence set-up of safety railings on the roof levels of the building. 

Project Update - Week of January 23rd 2023

Please see the below project update and list of activities scheduled for the week of January 23rd 2023

Tripp McElroy III 0 181 Article rating: No rating
  • The site contractor shall commence with the excavation and installation of drainage lines in the outdoor learning space between Areas C & D of the building.   
  • The structural steel contractor shall continue with decking & detailing activities in Area A of the building and is scheduled to commence these activities in Area B of the building.   
  • The structural steel contractor is scheduled to complete steel erection activities in Area B of the building next week.
  • The project has steel joist deliveries scheduled for Tuesday 1/24 and Wednesday 1/25 for the Cafeteria area of the building.
  • The general trades contractor shall continue with mobilizing activities on the project site.
RSS
124678910Last

Theme picker