Project Update - Week of October 24th 2022

Tripp McElroy III 0 89 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of October 24th 2022. 

  • The athletic field storage shed construction shall be completed.  
  • The site contractor will be completing general clean-up and placing remaining loam materials around the long jump areas and other misc landscape areas at the perimeter of the track.  Seeding of these lawn areas is tentatively scheduled for the end of the week.   
  • The site contractor will continue with installation of foundation insulation and backfill of foundation walls in Area B.  
  • The site contractor will continue with excavation and sub-grade prep for interior footings in Area B at the Gymnasium.
  • The site contractor will continue with excavation of underground plumbing trenches in Area D of the building.
  • The site contractor shall continue with the installation of the underground sewer line on the South elevation of the building located in the perimeter access road.
  • The site contractor shall continue with the excavation and construction of retaining wall #2 on the South elevation of the building. 
  • The concrete contractor will continue forming and pouring the loading dock foundation walls. 
  • The concrete contractor will continue forming and placing the interior footings in Area B at the Gymnasium.
  • The plumbing enabling contractor shall continue with the installation of the underground plumbing in Area D of the building.
  • The electrical enabling contractor shall continue with the electrical ductbank installation from a previously installed manhole to the BESS vault location.   

Project Update - Week of October 17th 2022

Tripp McElroy III 0 75 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of October 17th 2022. 

  • The athletic field storage shed construction shall be completed.  
  • The site contractor will be completing general clean-up and placing remaining loam materials around the long jump areas and other misc landscape areas at the perimeter of the track.  Seeding of these lawn areas is tentatively scheduled for the end of the week.   
  • The site contractor will continue with installation of foundation insulation and backfill of foundation walls in Area B.  
  • The site contractor will continue with excavation and sub-grade prep for interior isolated footings in Area A.
  • The site contractor will complete back-filling of the underground plumbing trenches in Area C and shall commence with excavation for underground plumbing in Area D of the building.
  • The site contractor shall commence with the installation of the underground sewer line on the South elevation of the building located in the perimeter access road.
  • The site contractor shall commence with the excavation and construction of retaining wall #2 on the South elevation of the building. 
  • The concrete contractor will continue reinforcing, forming and placing portions of the loading dock foundation walls. 
  • The concrete contractor will continue forming and placing the interior isolated footings in Area A.
  • The plumbing enabling contractor shall commence with the installation of the underground plumbing in Area D. 

Town of Groton Special Town Meeting Information

Tripp McElroy III 0 125 Article rating: No rating

The Town of Groton Special Town Meeting is MONDAY, September 12, 2022 at 7:00 p.m. at the Groton Middle School Performing Arts Center

The purpose of the meeting is to request authorization to increase the borrowing for the Florence Roche Elementary School Project by $9.5 million.

 

To review the VIDEO OF THE INFORMATION SESSION (presented at the FRBC, last night, 09/08/22) please see the link below:

https://us02web.zoom.us/.../KlQBkfAldgZGXO7aYDZlGSIxVO0Kt...

Passcode: #4AZLdhK

 

For those with Kids - BABYSITTING IS AVAILABLE (6:30 PM until end of Meeting, Ages 5 thru 12) - SIGN UP BELOW:

https://docs.google.com/.../1bAjArPe839hJpimQ9jzokQW.../edit

Project Update - Week of September 5th 2022

Tripp McElroy III 0 122 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of 9/5.  

  • The fencing contractor will commence with the fence installation on the West side of the new track and field. 
  • The electrical contractor will continue with the electrical work to support power to the new athletic field shed location.
  • The site contractor shall commence prepping and raking out the atheltic field loam in preparation for Sod materials to be delivered the week of 9/12.
  • The track surfacing contractor is scheduled to mobilize to the project site on Tuesday 9/6 and commence their pre-work inspection of the track surface.
  • The electrical and site contractors will continue the electrical ductbank installation towards the BESS system pad. 
  • The site contractor will continue various grading activities around the site.
  • The site contractor shall continue with foundation insulation installation and back-filling activities in Areas C & D. 
  • The concrete contractor will continue and complete foundation construction for the classroom wings in Areas C & D. 
  • The site contractor will continue to excavate for foundations in Areas A & B. 
  • The contractor shall commence with the construction of footings in Area A.
  • The concrete contractor is scheduled to receive a rebar delivery for Area A on Wednesday 9/7 and Anchor Bolts for Area A on Friday 9/9.  
  • Concrete placements are tentatively scheduled for Wednesday 9/7 and Friday 9/9.
  • Due to the Labor Day holiday on Monday 9/5 there will not be any work activities onsite.

Project Update - Week of August 22nd 2022

Tripp McElroy III 0 113 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 8/22.

  • Exporting excess materials from the site shall continue this week.   
  • Complete the construction of the long jump pits at the new track area. 
  • Commence the installation of the irrigation system in the new athletic field.
  • Continue with site restoration and re-establishment of the temporary construction fence line shall continue this week adjacent to the Middle School South building.   
  • The site and electrical contractor shall continue with the construction of the underground electrical & communications ductbank working South on the site towards Champney Street. 
  • The site contractor shall continue with excavation and subgrade prep for concrete foundations in Area A of the building.      
  • The site contractor shall continue importing and placing structural fill materials in Area B of the new building. 
  • The concrete contractor shall continue construction of foundation formwork in Area C  and commence in Area A of the new building.  Foundation wall construction shall commence in Area D of the new building.  Concrete placements are tentatively scheduled for Wednesday 8/24 and Friday 8/26 this week.  