Revised Topping Off Beam Signing Schedule

Tripp McElroy III 0 168 Article rating: No rating

Due to the inclement weather today (1/13/23) the project has closed the beam signing area to the public. 

The project will have the beam signing area open to the public on Monday 1/16 from 7:30AM - 3:00PM to offer an additional opportunity to sign the beam.   

Project Update - Week of January 16th 2023

Please see the below project update and list of activities scheduled for the week of January 16th 2023

Tripp McElroy III 0 170 Article rating: No rating
  • The site contractor shall continue with the excavation and sub-grade prep to construct the site retaining wall along the projects site access road. 
  • The structural steel contractor shall continue with welding & detailing activities for Areas C & D of the building.
  • The structural steel contractor shall continue with decking & detailing activities in Area A of the building.   
  • The structural steel contractor shall continue with steel erection in Area B of the building.
  • The project has structural steel and/or metal deck deliveries scheduled for Monday 1/16 through Wednesday 1/18 and Friday 1/20.
  • The general trades contractor is scheduled to mobilize onsite Tuesday 1/17 and commence stair tower construction to provide access to all floor levels in Areas C & D of the building. 
  • The project's Steel Topping Off Ceremony is scheduled for Tuesday 1/17 at 9:30AM.  Please refer to the School District's website for additional information about the event.  

Project Update - Week of January 9th 2023

Please see the below project update and list of activities scheduled for the week of January 9th 2023

Tripp McElroy III 0 183 Article rating: No rating
  • The site contractor shall continue with the excavation and sub-grade prep to construct the site retaining wall along the projects site access road. 
  • The structural steel contractor shall continue with welding & detailing activities for Area C of the building.
  • The structural steel contractor is scheduled to commence welding of the composite nelson studs for Area D of the building.  Note this is a weather dependant activity. 
  • The structural steel contractor shall continue steel erection for Area A of the building and commence decking & detailing activities in this area. 
  • The project has structural steel and/or metal deck deliveries scheduled for Monday 1/9 through Thursday 1/12.

Project Update - Week of December 12th, 2022

Tripp McElroy III 0 184 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of December 12th 2022. 

  • The electrical enabling contractor shall complete the rough-in and prep to support future temporary power needs on the project and shall commence with clean-up and demoblizing from the project site.
  • The site contractor shall continue with the excavation and installation of the new drainage line, structures and water quality units on the West elevation of the new building. 
  • The site contractor is scheduled to tag the existing trees scheduled for removal along the existing Florence Roche parking lot on the South elevation of the project site.

Project Update - Week of December 5th, 2022

Tripp McElroy III 0 204 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of December 5th 2022. 

  • The plumbing enabling contractor shall commence with clean-up and demoblizing from the project site.
  • The site contractor shall commence with the continuation of sewer line on the West elevation of the new building.  This work continues the new sewer line that was stubbed into the project site over the Summer from the Middle School utility corridor work.  
  • The site contractor shall commence with the excavation and installation of the new drainage line and structures on the West elevation of the new building. 
  • The site contractor is scheduled to tag the existing trees scheduled for removal along the existing Florence Roche parking lot on the South elevation of the project site.
  • Temporary fence shall be relocated to seperate the new athletic track and field from the new building project site.  
RSS
123578910Last

Theme picker