Project Update - Week of June 13th 2022

Tripp McElroy III 0 142 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 6/13.

  • The site contractor shall continue their cut to fill effort of the onsite soil materials at the new track & field area of the project site.   The applicable project consultants shall be onsite to witness these work activities.  
  • Exporting excess materials from the site shall continue this week. 
  • Continue subgrade prep for the retaining walls adjacent to the new athletic track.  The retaining wall block materials commenced delivery to the site on Friday 6/10 and shall continue next week.       
  • The site contractor shall sawcut the existing roadway to support utility construction between the existing Florence Roche Elementary and Middle School South on Friday 6/17.  This is to allow excavation for utility construction to commence on Monday 6/20.  There is no school on Friday 6/17 and this work activity has been coordinated with the School District.  
  • A series of material deliveries are scheduled for the project site next week including but not limited to crushed stone to support retaining wall construction, concrete drainage structures and drainage infilitration system components.    

Project Update - Week of June 6th 2022

Tripp McElroy III 0 158 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 6/6.

  • The site contractor shall continue their cut to fill effort of the onsite soil materials at the new track & field area of the project site.   The applicable project consultants shall be onsite to witness these work activities.  
  • Exporting excess materials from the site shall continue this week. 
  • Commence subgrade prep for the retaining walls adjacent to the new athletic track.  The retaining wall block materials are tentatively scheduled to be delivered to the site this week.  This delivery may shift to the following week of 6/13.     
  • The project's groundbreaking event has been rescheduled for Monday 6/6 at 4pm! 

Project Update - Week of May 30th 2022

Tripp McElroy III 0 182 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 5/30.

  • Due to the holiday on Monday 5/30, there will not be any work on the project site.
  • The site contractor shall continue with stripping topsoil activities at the new building location.  
  • Exporting topsoil materials offsite to the Department of Public Works property shall commence on Tuesday 5/31.  This has been coordinated with the department. 
  • The site contractor shall commence their cut to fill effort of the onsite soil materials at the new track & field area of the project site.   The applicable project consultants shall be onsite to witness the start of this work.
  • The project's groundbreaking event is scheduled for Wednesday 6/1 at 4pm! 

Memorial Day Weekend Work Schedule

Tripp McElroy III 0 174 Article rating: 5.0

There will not be any work activities on the project site Friday 5/27 and Monday 5/30.  Due to the upcoming holiday weekend the site contractor has been working extended hours this week to allow Friday 5/27 be a non-work day for their crew.  Monday 5/30 is Memorial Day and recognized as a holiday by the trades.     

Project Update - Week of May 23rd 2022

Tripp McElroy III 0 176 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 5/23.

  • The site contractor shall continue with stripping topsoil activities at the new track location.  The project's LSP shall continue on-site monitoring of these activities as required.  
  • Tentatively start exporting topsoil materials offsite to the Department of Public Works property.  This activity may shift to commence the following week of 5/30. 
  • Tree removal is scheduled to commence on Monday 5/23 and will continue through the week.  This crew shall commence their work in the area of the Battery Emergency Storage System (BESS) on the project site, which is adjacent to the existing School District Offices.
  • The site contractor shall commence stripping of topsoil at the new building location this week.  