Saturday Work - July 22nd, 2023

The project will be working on the site this Saturday 7/22/23. Activities will consist of the following:

Jonathan May 0 152 Article rating: No rating
  • The plumbing contractor will commence installation of the mechanical room gas piping. 
  • The mechanical contractor will continue layout and coordination of the mechancial room mechanical piping. 
  • The mechanical contractor will continue overhead duct instllation on Level  C. 

Project Update - Week of July 24th, 2023

Please see the below project update and list of activities scheduled for the week of July 24th 2023.

Jonathan May 0 142 Article rating: No rating
  • The general trades contractor will complete exterior framing & sheathing in Areas A & B. 
  • The general trades contractor will continue layout and interior framing on level 2 Areas A & B and Level 1 C. 
  • The general trades contractor will commence level 2 C and D wood blocking installation. 
  • The waterproofing contractor will continue waterproofing Areas A & B. 
  • The masonry contractor will continue installation of exterior masonry veneer in Areas A & B
  • The masonry contractor will complete the gymnasium CMU wall. 
  • The concrete contractor will place the stage platform concrete stairs. 
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The mechanical contractor will continue installation of in-wall duct drops to displacement diffusers and installation of duct insulation. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing on Level 2 Areas D & A, and Level 1 Area D. 
  • The plumbing contractor will commence gas line installation in the mechanical room. 
  • The electrical contractor will continue in-wall rough-in on level 2 D. 
  • The electrical contractor will continue the build out of the level 2 electrical rooms. 
  • The electrical contractor will continue overhead rough-in on level 1. 
  • The fire protection contractor will continue installation of fire protection pipe on Level 1 Area D. 
  • The window contractor will continue with installation of the metal windows in Area D.
  • The metal panel contractor will continue installation of the exterior metal panel system on areas C&D facade. 

Saturday Work - July 15th, 2023

The project will be working on the site this Saturday 7/15/23. Activities will consist of the following:

Jonathan May 0 128 Article rating: No rating
  • The general trades contractor will continue interior framing on level 2 A and level 1 C
  • The mechancal contractor will contineu overhead duct installation on level 2 A and level 1 C. 
  • The electrical contractor will commence in-wall rough-in of level 2 C. 

Project Update - Week of July 17th, 2023

Please see the below project update and list of activities scheduled for the week of July 17th 2023.

Jonathan May 0 129 Article rating: No rating
  • The general trades contractor will continue exterior framing & sheathing in Areas A & B. 
  • The general trades contractor will continue layout and interior framing on level 2 Areas A & B and Level 1 C. 
  • The waterproofing contractor will continue installation of waterproofing membrane in Areas A & B. 
  • The masonry contractor will continue installation of exterior masonry veneer in Areas A & B
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas D & A, and Level 1 Area D. 
  • The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. 
  • The fire protection contractor will continue installation of fire protection pipe on Level 1 Area C. 
  • The window contractor will continue with installation of the metal windows in Area C & D.
  • The metal panel contractor will continue installation of the exterior metal panel system on areas C&D facade. 

Saturday Work - July 8th, 2023

The project will be working on the site this Saturday 7/8/23. Activities will consist of the following:

Jonathan May 0 124 Article rating: No rating
  • The general trades contractor will continue interior layout activities. 
  • The waterproofing contractor will contue waterproofing efforts in Area B.