Project Update - Week of October 21th, 2024

Please see the below project update and list of activities scheduled for the week of October 21th, 2024

Jonathan May 0 34 Article rating: No rating
  • The site contractor will continue with the construction entrance re-establishment. 
  • The landscape contractor will continue the front lawn loam spreading & irrigation install, protective playgorund surface installation, fence installation, and final plantings. 

Project Update - Week of October 14th, 2024

Please see the below project update and list of activities scheduled for the week of October 14th, 2024

Jonathan May 0 43 Article rating: No rating
  • The site contractor will continue with the construction entrance re-establishment. 
  • The landscape contractor will continue the front area play equipment installation, fence install, loam & irrigation install, and playground surface installation. 

Saturday Work - October 5th, 2024

The project will be working on the site this Saturday 10/5/24. Activities will consist of the following:

Jonathan May 0 46 Article rating: No rating
  • The electrical contractor will commence setting and final wiring of light poles. 
  • The landscape contractor will commence installation of the flagpole.

Project Update - Week of October 7th, 2024

Please see the below project update and list of activities scheduled for the week of October 7th, 2024

Jonathan May 0 49 Article rating: No rating
  • The site contractor will commence the construction road re-establishment.
  • The concrete contractor will continue preparation work for pouring the west walk. 
  • The electrical contractor will continue site lighting conduit, wire, and light pole installation.
  • The landscape contractor will continue the front area play equipment installation, fence install, loam & irrigation install, and playground surface installation. 

Project Update - Week of September 30th, 2024

Please see the below project update and list of activities scheduled for the week of September 30th, 2024

Jonathan May 0 44 Article rating: 5.0
  • The site contractor will continue setting final grade of the front lawn area and installation of final drainage system components. 
  • The site contractor will continue setting light pole bases and excavation of site lighting conduit paths on the west side of the lawn area.
  • The site contractor will commence curb and sidewalk preparation on the west side of the demo site. 
  • The electrical contractor will continue site lighting conduit, wire, and light pole installation.
  • The concrete contractor will re-mobilize to begin forming the west walk.  
  • The landscape contractor will continue the front area play equipment installation, fence install, and initial spreading of loam of the lawn area. 
RSS
245678910Last

Theme picker