Saturday Work - August 10th, 2023

The project will be working on the site this Saturday 8/10/24. Activities will consist of the following:

Jonathan May 0 109 Article rating: 5.0
  • The concrete contractor will continue preparation of the phase 2B walkways. 
  • The electrical and general trades contractors will continue addressing punchlist items. 

Project Update - Week of August 12th, 2024

Please see the below project update and list of activities scheduled for the week of August 12th, 2024

Jonathan May 0 91 Article rating: 5.0
  • The demolition contractor will demobilize from the site. 
  • The site contractor will continue preparation of the phase 2B concrete walks. 
  • The site contractor will continue subgrade preperation of the grade 1-4 playground and the basketball asphalt area. 
  • The paving contractor will pave the roadways. 
  • The concrete contractor will continue forming and pouring the phase 2B walkways. 
  • All contractors’ will continue addressing punchlist items. 

Saturday Work - August 3rd, 2024

The project will be working on the site this Saturday 8/3/24. Activities will consist of the following:

Jonathan May 0 104 Article rating: 5.0
  • The concrete contractor will continue forming and reinforcing the parent drop off loop concrete walks. 
  • The demolition contractor will continue demolition of the 1950s wing. 
  • The specialties contractor will continue addressing punchlist items. 
  • The site contractor will continue preparation for paving activities next week. 
  • The electrical contractor will continue addressing punchlist items.

Project Update - Week of August 5th, 2024

Please see the below project update and list of activities scheduled for the week of August 5th, 2024

Jonathan May 0 123 Article rating: 5.0
  • The demolition of the existing FloRo will continue the below grade cafeteria and mechanical spaces as well as slab on grade and footing removal of the 1950s wing. 
  • The demolition contractor will continue hauling of demolition debris.  
  • The site contractor will continue preparation of the phase 2B concrete walks. 
  • The site contractor will conduct final preparation for top course paving around the new FloRo. 
  • The paving contractor will pave the roadways. 
  • The concrete contractor will continue forming and pouring the bus loop, parent drop off loop, and phase 2B perimeter walks. 
  • All contractors’ will continue addressing punchlist items. 

Project Update - Week of July 29th, 2024

Please see the below project update and list of activities scheduled for the week of July 29th, 2024

Jonathan May 0 87 Article rating: 5.0
  • The demolition of the existing FloRo will continue the below grade cafeteria and mechanical spaces as well as slab on grade and footing removal. 
  • The site contractor will continue granite curb installation around the perimeter of Phase 2B. 
  • The site contractor will continue raising manhole frames and covers in preperation for final paving. 
  • The concrete contractor will continue forming and pouring the bus loop, parent drop off loop, and phase 2B perimeter walks. 
  • The landscape contractor will set the front entrance granite benches. 
  • All contractor's will continue addressing punchlist items. 
RSS
124678910Last

Theme picker