Project Update - Week of July 15th, 2024 Please see the below project update and list of activities scheduled for the week of July 15th, 2024 Jonathan May / Monday, July 15, 2024 0 76 Article rating: 5.0 The demolition & abatement contractor has completed abatement of all ACM from the existing FloRo The demolition of the existing FloRo will continue with the 1960s & 50s wings. The site contractor will be completing initial paving of the bus loop entrance road. The site contractor will be finalizing installation of the south retaining wall. The site contractor will be setting grade of the parent drop off entrance road. The site contractor will continue setting curb for the entrance roads. The concrete contractor will commence forming and reinforcing of the remaining entrance concrete. The project will conduct final MEP inspections and NFPA 72 testing. All contractor's will continue addressing punchlist items. Read more
Project Update - Week of July 8th, 2024 Please see the below project update and list of activities scheduled for the week of July 8th, 2024 Jonathan May / Saturday, July 6, 2024 0 75 Article rating: 4.0 The demolition & abatement contractor has completed abatement of all interior spaces and will continue abatement of the roof. The demolition & abatement contractor will continue demolition of the existing FloRo Area C. The site contractor will continue subgrade preparation of all pavement areas. The site contractor will continue final grade setting in new pavement areas. The site contractor will commence layout and setting of granite curb. The concrete contractor will continue forming and reinforcing of the middle school sidewalk area and the loading dumpster pad. The painting contractor will continue painting of exterior rails. The millwork and casework contractor will continue installation of the exterior benches. The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. The MEP contractors will continue system pre-functional testing of the kitchen equipment. The electrical contractor will continue final system programming and pre-functional testing. All contractor's will continue addressing punchlist items. Read more
Saturday Work - June 29th, 2024 The project will be working on the site this Saturday 6/29/24. Activities will consist of the following: Jonathan May / Friday, June 28, 2024 0 82 Article rating: 5.0 The demolition and abatement contractor will continue abatement of the 1950s area A wing and demolition of the 1980s Area C wing. The electrical contractor will continue final programming and setting of devices. Read more
Project Update - Week of July 1st, 2024 Please see the below project update and list of activities scheduled for the week of July 1st, 2024 Jonathan May / Friday, June 28, 2024 0 60 Article rating: 5.0 The demolition & abatement contractor has completed abatement of the existing FloRo area B and will continue abatement of Area A. The demolition & abatement contractor will continue demolition of the existing FloRo Area C. The site contractor will complete the installation of the entry road infiltration system. The site contractor will continue subgrade preparation of all pavement areas. The site contractor will commence final grade setting in new pavement areas. The concrete contractor will commence forming and reinforcing of the middle school sidewalk area and the dumpster pad. The painting contractor will continue painting of exterior rails. The millwork and casework contractor will continue installation of the exterior benches. The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. The MEP contractors will continue system pre-functional testing of the kitchen equipment. The electrical contractor will continue final system programming. All contractor's will continue addressing punchlist items. Read more
Saturday Work - June 22nd, 2024 The project will be working on the site this Saturday 6/22/24. Activities will consist of the following: Jonathan May / Friday, June 21, 2024 0 77 Article rating: 5.0 The demolition and abatement contractor will continue abating the existing FloRo. The site contractor will continue subgrade preperation of the areas scheduled for new pavement. Read more