Project Update - Week of September 23rd, 2024

Please see the below project update and list of activities scheduled for the week of September 23rd, 2024

Jonathan May 0 77 Article rating: 3.0
  • The site contractor will continue setting final grade of the front lawn area and installation of final drainage system components. 
  • The site contractor will continue setting light pole bases and excavation of site lighting conduit paths on the west side of the lawn area.
  • The site contractor will commence curb and sidewalk preparation on the west side of the demo site. 
  • The electrical contractor will continue site lighting conduit installation.
  • The landscape contractor will continue the front area play equipment installation, fence install, and initial spreading of loam of the lawn area. 

Project Update - Week of September 16th, 2024

Please see the below project update and list of activities scheduled for the week of September 16th, 2024

Jonathan May 0 59 Article rating: 5.0
  • The site contractor will continue setting final grade of the front lawn area. 
  • The site contractor will continue setting light pole bases and excavation of site lighting conduit paths on the north side of the lawn area. 
  • The electrical contractor will continue site lighting conduit install and wiring. 
  • The landscape contractor will continue the front area play equipment installation. 

Project Update - Week of September 9th, 2024

Please see the below project update and list of activities scheduled for the week of September 9th, 2024

Jonathan May 0 70 Article rating: 5.0
  • The site contractor will continue setting final grade of the front lawn area. 
  • The site contractor will continue setting light pole bases on the north side of the lawn area. 
  • The electrical contractor will continue site lighting conduit and wire installation. 
  • The landscape contractor will continue the basketball fence installation. 
  • The landscape and concrete contractor will continue pouring the playground perimeter concrete curb. 
  • The landscape contractor will continue subgrade preparation of the playground and planting areas. 

Project Update - Week of August 26th, 2024

Please see the below project update and list of activities scheduled for the week of August 26th, 2024

Jonathan May 0 92 Article rating: 5.0
  • The site contractor will continue preparation of the final landscape area lawns. 
  • The site contractor will commence site lighting conduit routes & setting light pole bases. 
  • The landscape contractor will continue subgrade preparation of the basketball court & the playground area. 
  • The landscape contractor will commence initial paving course of the basketball court. 
  • The concrete contractor will continue forming and pouring the remaining walkways.
  • The FloRo students will return to class for the 2024-2025 school year!!!

Project Update - Week of August 19th, 2024

Please see the below project update and list of activities scheduled for the week of August 19th, 2024.

Jonathan May 0 105 Article rating: 5.0
  • The site contractor will continue preparation of the demolition phase concrete walks. 
  • The site contractor will continue subgrade preparation of the grade 1-4 playground and the basketball asphalt area. 
  • The site contractor will commence excavation of the demolition phase site lighting conduit paths. 
  • The concrete contractor will continue forming and pouring the demolition phase walkways.
  • The landscape contractor will remobilize and focus on the final landscaping hardscape areas. 
RSS
135678910Last

Theme picker