Saturday Work - August 5th 2023 The project will be working on the site this Saturday 8/5/23. Activities will consist of the following: Jonathan May / Friday, August 4, 2023 0 41 Article rating: No rating The general trades contractor will continue instllation of the low roof skylight framing and blocking. The plumbing continue will continue with plumbing installation on level 1 area C as well as gas pipping on level 1. The mechanical piping contractor will continue pipping installation in the mechanical room. The electrical contractor will continue in-wall rough-in on level 2. Read more
Project Update - Week of August 7th, 2023 Please see the below project update and list of activities scheduled for the week of August 7th, 2023. Jonathan May / Friday, August 4, 2023 0 36 Article rating: No rating The general trades contractor will continue drywall and taping of the level 2 area C & D electric rooms. The general trades contractor will continue interior framing on level 1 areas C & D. The general trades contractor will commence interior drywall and insulation on level 2 C. The concrete contractor will form and place the Stair B elevated slab. The concrete contractor will form and place the platform stairs and ramps. The concrete contractor will pour the main electric room slab on grade. The mechanical contractor will continue duct installation on level 1 D & A. The mechanical contractor will continue duct insulation install on level 2. The plumbing contractor will continue in-wall rough in on level 1 C The plumbing contractor will continue gas pipe installation on level 1. The plumbing contractor will commence roof drain tie-in in the gym. The roofing contractor will continue roof edge metal installation. The electrical contractor will continue in-wall rough in on level 2 A and level 1 C. The electrical contractor will continue buildout of the level 2 area C & D electrical rooms. The fireproofing contractor will continue sprinkler pipe installation on level 1 A & B. The masonry contractor will continue masonry veneer installation on A & B exterior elevations. The waterproofing contractor will continue waterproofing membrane on the west elevation of area A & B. The metal panel contractor will continue panel installation on area C & D east bump outs. The metal windows contractor will continue window installation on level 2 A & Read more
Saturday Work - July 29th 2023 The project will be working on the site this Saturday 7/29/23. Activities will consist of the following: Tripp McElroy III / Thursday, July 27, 2023 0 35 Article rating: No rating The window contractor shall continue with window installation on the South elevation of Area D. The general trades contractor shall continue with setting of door frames and installation of in-wall blocking on Level 2 of Area C. The site contractor shall backfill and prep the subgrade around the electrical vault in the Main Electrical room. The electrical contractor shall complete the underground rough-in to the electrical vault in the Main Electrical room. This trade shall also continue with in-wall rough-in on Level 2 of Area D. The plumbing contractor shall continue with the installation of gas piping in the mechanical room. The mechanical contractor shall continue layout and coordination of the mechanical piping in the mechancial room. The mechanical contractor shall continue with overhead duct installation on Level 1 of Area D. Read more
Saturday Work - July 22nd, 2023 The project will be working on the site this Saturday 7/22/23. Activities will consist of the following: Jonathan May / Friday, July 21, 2023 0 39 Article rating: No rating The plumbing contractor will commence installation of the mechanical room gas piping. The mechanical contractor will continue layout and coordination of the mechancial room mechanical piping. The mechanical contractor will continue overhead duct instllation on Level C. Read more
Project Update - Week of July 24th, 2023 Please see the below project update and list of activities scheduled for the week of July 24th 2023. Jonathan May / Friday, July 21, 2023 0 43 Article rating: No rating The general trades contractor will complete exterior framing & sheathing in Areas A & B. The general trades contractor will continue layout and interior framing on level 2 Areas A & B and Level 1 C. The general trades contractor will commence level 2 C and D wood blocking installation. The waterproofing contractor will continue waterproofing Areas A & B. The masonry contractor will continue installation of exterior masonry veneer in Areas A & B The masonry contractor will complete the gymnasium CMU wall. The concrete contractor will place the stage platform concrete stairs. The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. The mechanical contractor will continue installation of in-wall duct drops to displacement diffusers and installation of duct insulation. The plumbing contractor will continue installation of overhead and in-wall plumbing on Level 2 Areas D & A, and Level 1 Area D. The plumbing contractor will commence gas line installation in the mechanical room. The electrical contractor will continue in-wall rough-in on level 2 D. The electrical contractor will continue the build out of the level 2 electrical rooms. The electrical contractor will continue overhead rough-in on level 1. The fire protection contractor will continue installation of fire protection pipe on Level 1 Area D. The window contractor will continue with installation of the metal windows in Area D. The metal panel contractor will continue installation of the exterior metal panel system on areas C&D facade. Read more