Project Update - Week of January 15th, 2024

Please see the below project update and list of activities scheduled for the week of January 15th, 2024

Jonathan May 0 152 Article rating: No rating
  • The general trades contractor will continue hanging and taping drywall in the Lobby, Cafeteria, and Kitchen.
  • The general trades contractor will continue hanging and taping drywall in the Stair D.
  • The resilient flooring contractor will continue flooring installation on level 2 area D and A.
  • The painting contractor will continue painting the level 1 classrooms, corridors, and admin area. 
  • The ceiling contractor will continue ceiling grid installation on level 2 bathrooms and and level 1 classroom wings.
  • The ceiling contractor will commence ceiling grid installation of the admin area.
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 2.  
  • The millwork and casework contractor will continue level 1 area C classroom casework installation
  • The millwork and casework contractor will continue level 2 corridor cubby installation
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue the kitchen in wall rough-in and pipe insulation.
  • The plumbing contractor will commence with level 2 classroom and bathroom sink installation. 
  • The plumbing contractor will commence final plumbing connections to mechanical equipment in the Mechanical Room. 
  • The mechanical contractor will continue ceiling diffuser installation on level 2.
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid.
  • The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnasium
  • The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. 
  • The electrical contractor will continue wiring of the level 2 corridor and level 1 classroom light fixtures. 
  • The electrical contractor will continue fire alarm finish installation on level 2. 
  • The tile contractor will continue level 2 corridor tile. 
  • The tile contractor will continue level 1 group bathroom floor and wall tile preperation. 

Project Update - Week of January 8th, 2024

Please see the below project update and list of activities scheduled for the week of January 8th 2024

Jonathan May 0 183 Article rating: No rating
  • The general trades contractor will continue hanging drywall in the Lobby, Cafeteria, and Kitchen
  • The general trades contractor will continue hanging drywall in the Stair D
  • The general trades contractor will continue taping level 1 area A & B as well as Stair C and D 
  • The resilient flooring contractor will continue withflooring installation on level 2 area D. 
  • The painting contractor will continue painting the level 1 classrooms, corridors, and admin area. 
  • The ceiling contractor will continue ceiling grid on level 2 bathrooms and level 2 corridors.
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 2.  
  • The millwork and casework contractor will continue window sill installation on level 2. 
  • The millwork and casework contractor will commence level 1 area C classroom casework installation
  • The millwork and casework contractor will commence level 2 corridor cubby installation
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue the kitchen in wall rough-in and pipe insulation
  • The mechanical contractor will continue ceiling diffuser installation on level 2 
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnasium
  • The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. 
  • The electrical contractor will commence wiring of the level 2 corridor light fixtures
  • The tile contractor will continue level 2 corridor tile
  • The tile contractor will continue level 1 group bathroom floor and wall tile preperation

Project Update - Week of January 2nd, 2024

Please see the below project update and list of activities scheduled for the week of January 2nd, 2024

Jonathan May 0 187 Article rating: No rating
  • The general trades contractor will continue metal framing and hanging drywall in the Media Center, Lobby, and Cafeteria. 
  • The general trades contractor will continue hanging drywall of the Stair D
  • The general trades contractor will continue taping level 1 area A & B as well as Stair C. 
  • The flooring contractor will continue resilient flooring on level 2 area C and commence the level 2 area D classrooms. 
  • The painting contractor will continue painting the level 1 classrooms and corridors
  • The ceiling contractor will continue ceiling grid on level 2 bathrooms and level 2 corridors. 
  • The millwork and casework contractor will continue casework installation on level 2 area A & D classrooms.
  • The millwork contractor will receive the level 1 area C classroom casework and the level 2 corridor casework. 
  • The metal windows contractor will continue installation of the interior storefronts in the Media Center and Admin area. 
  • The plumbing contractor will continue the kitchen in wall rough-in and pipe insulation
  • The mechanical contractor will continue duct installation in the gym, cafe, kitchen, and platform
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The mechanical contractor will commence final setting of the level 2 ceiling diffusers. 
  • The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnsium
  • The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. 
  • The tile contractor will continue level 2 corridor tile
  • The tile contractor will continue level 1 group bathroom floor and wall tile preperation

Project Update - Week of December 26th, 2023

Please see the below project update and list of activities scheduled for the week of December 26th 2023

Jonathan May 0 199 Article rating: No rating
  • The general trades contractor will continue hanging drywall in the cafeteria and media center
  • The general trades contractor will commence drywall of the Stair D
  • The general trades contractor will continue taping level 1 area A & B
  • The painting contractor will continue painting of level 1 classrooms and corridors
  • The ceiling contractor will continue ceiling grid on level 2 bathrooms and level 2 corridors
  • The millwork and casework contractor will continue casework installation on level 2 area A & D classrooms.
  • The fire protection contractor will continue sprinkler head finish install into ceiling tile on level 2
  • The plumbing contractor will continue the kitchen in wall rough-in and pipe insulation
  • The mechanical contractor will continue duct installation in the gym, cafe, kitchen, and platform
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnsium
  • The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. 
  • The tile contractor will continue level 2 corridor tile
  • The tile contractor will continue level 1 group bathroom floor and wall tile preperation
  • The resilient flooring contractor will continue floor tile installation on level 2 area C classrooms

Project Update - Week of December 18th 2022

Please see the below project update and list of activities scheduled for the week of December 18th 2023

Jonathan May 0 165 Article rating: No rating
  • The general trades contractor will continue hanging drywall in the cafeteria and media center
  • The general trades contractor will continue drywall activities on level 1 A, Lobby and admin area
  • The general trades contractor will continue drywall of the classroom wing stairwell
  • The general trades contractor will continue in-wall blocking and drywall installation in the media center
  • The general trades contractor will continue taping level 1 area D and A
  • The painting contractor will continue painting of level 1 classrooms and corridors
  • The ceiling contractor will continue ceiling grid on level 1 2 area C corridor
  • The millwork and casework contractor will continue casework installation on level 2 area C and D classrooms.
  • The fire protection contractor will continue sprinkler head finish install into ceiling tile on level 2 area C
  • The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation install
  • The mechanical contractor will continue duct installation in the gym
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The mechancial contractor will continue overhead duct rough-in in the platform
  • The electrical contractor will continue overhead rough in on level 1 area B cafeteria
  • The electrical contractor will continue installation and wiring of level 2 area A and level 1 area C/D light fixtures. 
  • The electrical contractor will commence installing the level 2 area C corridor light fixtures
  • The tile contractor will continue level 2 corridor tile
  • The tile contractor will continue level 1 group bathroom floor and wall tile preperation. 
RSS
First567810121314Last

Theme picker