Project Update - Week of September 26th 2022 Jonathan May / Friday, September 23, 2022 0 60 Article rating: No rating Please see the below project update and list of activities scheduled for the week of September 26th 2022. The track surface contractor will finalize layout and commence the track surface installation. The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas A & B. The site contractor will continue foundation excavation of Area B. The site contractor will continue installation of the site drainage system below the proposed perimeter access road. The site contractor will continue installation of the site water utility system below the proposed perimeter access road. The site contractor will continue various grading activities around the site. The concrete contractor will continue forming and placing perimeter concrete foundations in Area B. The concrete contractor will continue forming and placing the Area A & B interior concrete foundations. Read more
Project Update - Week of September 19th 2022 Jonathan May / Friday, September 16, 2022 0 80 Article rating: No rating Please see the below project update and list of activities scheduled for the week of September 19th 2022. The irrigation with complete final position of irrigation heads. The track surface contractor will begin placing of the synthetic track surface. The electrical contractor in coordiantion with GELD will complete the ductbanks to Champney Street and connect to the new utility poles provided by GELD. The concrete contractor will continue forming and placing concrete foundations in Areas A & B. Concrete placements are tentatively scheduled for Monday, 9/19, Wednesday, 9/21, and Friday, 9/23. The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas C & D. The site contractor will continue foundation excavation of Areas A & B. The site contractor will continue utility installation below the proposed perimeter access road. The site contractor will continue various grading activities around the site. Read more
Town of Groton Special Town Meeting Information Tripp McElroy III / Friday, September 9, 2022 0 104 Article rating: No rating The Town of Groton Special Town Meeting is MONDAY, September 12, 2022 at 7:00 p.m. at the Groton Middle School Performing Arts Center The purpose of the meeting is to request authorization to increase the borrowing for the Florence Roche Elementary School Project by $9.5 million. To review the VIDEO OF THE INFORMATION SESSION (presented at the FRBC, last night, 09/08/22) please see the link below: https://us02web.zoom.us/.../KlQBkfAldgZGXO7aYDZlGSIxVO0Kt... Passcode: #4AZLdhK For those with Kids - BABYSITTING IS AVAILABLE (6:30 PM until end of Meeting, Ages 5 thru 12) - SIGN UP BELOW: https://docs.google.com/.../1bAjArPe839hJpimQ9jzokQW.../edit Read more
Project Update - Week of September 5th 2022 Tripp McElroy III / Friday, September 2, 2022 0 100 Article rating: No rating Please see the below project update and list of activities scheduled for the week of 9/5. The fencing contractor will commence with the fence installation on the West side of the new track and field. The electrical contractor will continue with the electrical work to support power to the new athletic field shed location. The site contractor shall commence prepping and raking out the atheltic field loam in preparation for Sod materials to be delivered the week of 9/12. The track surfacing contractor is scheduled to mobilize to the project site on Tuesday 9/6 and commence their pre-work inspection of the track surface. The electrical and site contractors will continue the electrical ductbank installation towards the BESS system pad. The site contractor will continue various grading activities around the site. The site contractor shall continue with foundation insulation installation and back-filling activities in Areas C & D. The concrete contractor will continue and complete foundation construction for the classroom wings in Areas C & D. The site contractor will continue to excavate for foundations in Areas A & B. The contractor shall commence with the construction of footings in Area A. The concrete contractor is scheduled to receive a rebar delivery for Area A on Wednesday 9/7 and Anchor Bolts for Area A on Friday 9/9. Concrete placements are tentatively scheduled for Wednesday 9/7 and Friday 9/9. Due to the Labor Day holiday on Monday 9/5 there will not be any work activities onsite. Read more
Project Update - Week of August 29th 2022 Jonathan May / Saturday, August 27, 2022 0 90 Article rating: No rating Please see the below project update and list of activities scheduled for the week of 8/29. Exporting excess materials from the site shall continue this week. The fencing contractor will complete the athletic field retaining wall fence installation. The irrigation system will be completed The drainage structure covers will be installed The electrical contractor will commence providing power to the new athletic field shed location The concrete contractor will continue foundation construction for the classroom wings Area C & D. The site contractor will continue to excavate the Area A & B foundations. The electrical and site contractors will continue the electrical ductbank installation down Champney Street. The site contractor will continue various grading activities around the site. Read more