Saturday Work - July 20th, 2024 The project will be working on the site this Saturday 7/20/24. Activities will consist of the following: Jonathan May / Saturday, July 20, 2024 0 98 Article rating: 5.0 The demolition contractor will continue with the 1950's classroom wing removal. The site contractor will continue road way paving preperation and setting of veritical granite curb. The carpeting contractor will continue installation of the front entrance walk-off grille. The electrical contractor will continue terminations and programming. Read more
Project Update - Week of July 22nd, 2024 Please see the below project update and list of activities scheduled for the week of July 22nd, 2024 Jonathan May / Saturday, July 20, 2024 0 113 Article rating: 5.0 The demolition of the existing FloRo will continue with the 1950s wings. The site contractor will continue granite curb installation at the bus and parent drop off loops. The site contractor will be finalizing installation of the south retaining wall. The site contractor will be setting grade of the parent drop off entrance road and pave initial binder course. The concrete contractor will continue forming and reinforcing of the remaining bus and parent drop of loop concrete areas. The project will conduct initial pre-inspection walk throughs ahead of final occupancy inspections. All contractor's will continue addressing punchlist items. Read more
Project Update - Week of July 15th, 2024 Please see the below project update and list of activities scheduled for the week of July 15th, 2024 Jonathan May / Monday, July 15, 2024 0 122 Article rating: 5.0 The demolition & abatement contractor has completed abatement of all ACM from the existing FloRo The demolition of the existing FloRo will continue with the 1960s & 50s wings. The site contractor will be completing initial paving of the bus loop entrance road. The site contractor will be finalizing installation of the south retaining wall. The site contractor will be setting grade of the parent drop off entrance road. The site contractor will continue setting curb for the entrance roads. The concrete contractor will commence forming and reinforcing of the remaining entrance concrete. The project will conduct final MEP inspections and NFPA 72 testing. All contractor's will continue addressing punchlist items. Read more
Project Update - Week of July 8th, 2024 Please see the below project update and list of activities scheduled for the week of July 8th, 2024 Jonathan May / Saturday, July 6, 2024 0 123 Article rating: 4.2 The demolition & abatement contractor has completed abatement of all interior spaces and will continue abatement of the roof. The demolition & abatement contractor will continue demolition of the existing FloRo Area C. The site contractor will continue subgrade preparation of all pavement areas. The site contractor will continue final grade setting in new pavement areas. The site contractor will commence layout and setting of granite curb. The concrete contractor will continue forming and reinforcing of the middle school sidewalk area and the loading dumpster pad. The painting contractor will continue painting of exterior rails. The millwork and casework contractor will continue installation of the exterior benches. The MEP contractors will continue testing, balancing and commissioning of all equipment working with the project's commissioning agent. The MEP contractors will continue system pre-functional testing of the kitchen equipment. The electrical contractor will continue final system programming and pre-functional testing. All contractor's will continue addressing punchlist items. Read more
Saturday Work - June 29th, 2024 The project will be working on the site this Saturday 6/29/24. Activities will consist of the following: Jonathan May / Friday, June 28, 2024 0 145 Article rating: 5.0 The demolition and abatement contractor will continue abatement of the 1950s area A wing and demolition of the 1980s Area C wing. The electrical contractor will continue final programming and setting of devices. Read more