Project Update - Week of December 26th, 2023

Please see the below project update and list of activities scheduled for the week of December 26th 2023

Jonathan May 0 66 Article rating: No rating
  • The general trades contractor will continue hanging drywall in the cafeteria and media center
  • The general trades contractor will commence drywall of the Stair D
  • The general trades contractor will continue taping level 1 area A & B
  • The painting contractor will continue painting of level 1 classrooms and corridors
  • The ceiling contractor will continue ceiling grid on level 2 bathrooms and level 2 corridors
  • The millwork and casework contractor will continue casework installation on level 2 area A & D classrooms.
  • The fire protection contractor will continue sprinkler head finish install into ceiling tile on level 2
  • The plumbing contractor will continue the kitchen in wall rough-in and pipe insulation
  • The mechanical contractor will continue duct installation in the gym, cafe, kitchen, and platform
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The electrical contractor will continue overhead rough in on level 1 area B cafeteria, kitchen, and gymnsium
  • The electrical contractor will continue installation and wiring of level 1 area C and D light fixtures. 
  • The tile contractor will continue level 2 corridor tile
  • The tile contractor will continue level 1 group bathroom floor and wall tile preperation
  • The resilient flooring contractor will continue floor tile installation on level 2 area C classrooms

Project Update - Week of December 18th 2022

Please see the below project update and list of activities scheduled for the week of December 18th 2023

Jonathan May 0 77 Article rating: No rating
  • The general trades contractor will continue hanging drywall in the cafeteria and media center
  • The general trades contractor will continue drywall activities on level 1 A, Lobby and admin area
  • The general trades contractor will continue drywall of the classroom wing stairwell
  • The general trades contractor will continue in-wall blocking and drywall installation in the media center
  • The general trades contractor will continue taping level 1 area D and A
  • The painting contractor will continue painting of level 1 classrooms and corridors
  • The ceiling contractor will continue ceiling grid on level 1 2 area C corridor
  • The millwork and casework contractor will continue casework installation on level 2 area C and D classrooms.
  • The fire protection contractor will continue sprinkler head finish install into ceiling tile on level 2 area C
  • The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation install
  • The mechanical contractor will continue duct installation in the gym
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The mechancial contractor will continue overhead duct rough-in in the platform
  • The electrical contractor will continue overhead rough in on level 1 area B cafeteria
  • The electrical contractor will continue installation and wiring of level 2 area A and level 1 area C/D light fixtures. 
  • The electrical contractor will commence installing the level 2 area C corridor light fixtures
  • The tile contractor will continue level 2 corridor tile
  • The tile contractor will continue level 1 group bathroom floor and wall tile preperation. 

Saturday Work - December 16th, 2023

The project will be working on the site this Saturday 12/16/23. Activities will consist of the following:

Jonathan May 0 84 Article rating: No rating
  • The ceiling contractor will continue ceiling grid installation in the level 2 area C corridor. 
  • The general trades contractor will continue hanging drywall in the level 1 admin area. 

Project Update - Week of December 11, 2023

Please see the below project update and list of activities scheduled for the week of December 11th, 2023

Jonathan May 0 64 Article rating: No rating
  • The general trades contractor will continue metal framing activities in the cafeteria and kitchen
  • The general trades contractor will continue drywall activities on level 1 A, Lobby and admin area. 
  • The general trades contractor will commence drywall of the classroom wing stairwell
  • The general trades contractor will commence drywall installation in the cafeteria and media center
  • The general trades contractor will continue in-wall blocking and drywall installation in the media center
  • The general trades contractor will continue taping level 1 area D and A
  • The painting contractor will continue initial coats of level 1 classrooms
  • The ceiling contractor will commence ceiling grid on level 1 C. 
  • The ceiling contractor will continue ceiling grid install in the level 2 area C corridor
  • The millwork and casework contractor will continue casework installation on level 2 area C classrooms and commence area D classrooms
  • The fire protection contractor will continue overhead rough in of the cafeteria and platform
  • The fire protection contractor will continue sprinkler head finish install into ceiling tile on level 2 area C
  • The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation install
  • The mechanical contractor will continue duct installation in the gym
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The mechanical contractor will receive the first delivery of roof top units. 
  • The mechancial contractor will commence overhead duct rough-in in the cafeteria & lobby
  • The electrical contractor will continue overhead and in wall rough-in on level 1 area B cafeteria
  • The electrical contractor will continue installation and wiring of level 2 area A and level 1 area C light fixtures
  • The tile contractor will continue level 2 corridor tile
  • The tile contractor will commence level 1 group bathroom floor and wall tile preperation. 
  • The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge
  • The metal windows contractor will continue installation of the courtyard storefronts

Saturday Work - December 9th, 2023

The project will be working on the site this Saturday 12/9/23. Activities will consist of the following:

Jonathan May 0 65 Article rating: No rating
  • The ceiling contractor will commence ceiling grid install on level 2 area C
  • The general trades contractor will continue taping level 2 area B
  • The general trades contractor will remove the temporary protection from the gymnasium translucent panel
RSS
123578910Last

Theme picker