Project Update - Week of May 23rd 2022

Tripp McElroy III 0 80 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 5/23.

  • The site contractor shall continue with stripping topsoil activities at the new track location.  The project's LSP shall continue on-site monitoring of these activities as required.  
  • Tentatively start exporting topsoil materials offsite to the Department of Public Works property.  This activity may shift to commence the following week of 5/30. 
  • Tree removal is scheduled to commence on Monday 5/23 and will continue through the week.  This crew shall commence their work in the area of the Battery Emergency Storage System (BESS) on the project site, which is adjacent to the existing School District Offices.
  • The site contractor shall commence stripping of topsoil at the new building location this week.  

Project Update - Week of May 13th 2022

Please see the below project update and list of activities scheduled for the week of 5/16.

Jonathan May 0 128 Article rating: 5.0
  • Complete Con-Com and Stormwater Agent inspection of erosion control measures. 
  • The site contractor will begin stripping topsoil at the new track & field location.
  • The site contractor will begin demolition of existing field equipment, fencing, benches, etc.
  • Electrical and plumbing contractors will complete the construction trailer electrical and plumbing hookups. 

 

Project Update - Week of May 6th 2022

Please see the below project update and list of activities scheduled for the week of 5/9.

Jonathan May 0 91 Article rating: 5.0
  • The fence contractor will complete the driven post and fence installation.
  • The site contractor will complete the installation of erosion control measures along the perimeter of the construction site. 
  • The project will conduct the perimeter erosion control and SWPPP inspections with the town Conservation Committee Inspector and the Storm Water Advisory Agent.  
  • The site contractor will complete the implementation of the temporary construction access road. 
  • The site contractor will also mobilize additional earth moving equipment. 

Project Update - Week of April 29th 2022

Jonathan May 0 112 Article rating: 5.0

Site mobilization activities have continued this week. Please see the below project update and list of activities scheduled for the week of 5/2. 

  • The Surveyor's and layout engineers will continue to establish the construction area boundaries allowing all further work to be laid out. 
  • The temporary construction fence installation will continue: 
    • Continue layout of the remaining construction fence around the rear of the site. 
    • Continue driving posts and hanging of fence along the rear of the site. 
    • Begin preparation for all remaining auxiliary construction fence access gates. 
  • The site contractor will commence instllation of erosion control measures. 
  • The temporary construction access road activities will commence. 
  • Initial tree removal will commence. 

Project Update - Week of April 25th 2022

Tripp McElroy III 0 105 Article rating: 5.0

The Florence Roche Elementary School construction project has commenced!  Site mobilization activites commenced this week on-site during school vacation.  Please see below a project update and list of activities scheduled for the week of 4/25.

  • Temporary construction fence:
    • Complete the hanging of fence on posts previously driven behind Middle School South, adjacent to the existing ball field on Monday 4/25.
    • Continue driving posts and hanging of fence along the access road that connects to Champney Street.
    • Prep and set the fence gates at Gates A, B1, B2.  The balance of ancillary Gates shall follow.
    • Installation of fencing shall continue around the perimeter of the project site.
  • Setting, leveling and assembly of the double wide office trailer shall commence on Monday 4/25.
  • The site contractor shall commence establishing site and building layout control onsite Tuesday 4/26.
  • Installation of erosion control measures on the project site are scheduled to commence on Wednesday 4/27
RSS
123456

Theme picker