Saturday Work - April 6th, 2024

The project will be working on the site this Saturday 4/6/24. Activities will consist of the following:

Jonathan May 0 140 Article rating: No rating
  • The general trades contractor will continue misc. tapping activities on level 1. 
  • The general trades contractor will continue framing the stem patio ceiling. 
  • The general trades contractor will commence removal of the loading dock platform. 

Project Update - Week of April 8th, 2024

Please see the below project update and list of activities scheduled for the week of April 8th, 2024

Jonathan May 0 130 Article rating: No rating
  • The site contractor will continue preperation of the perimeter road landscape area and the rain garden. 
  • The concrete contractor will continue setting expansion joints for the outdoor learning lab concrete. 
  • The concrete contractor will continue forming of the front entrance CIP stairs. 
  • The waterproofing contractor will continue caulking of exterior masonry and metal panel joints. 
  • The general trades contractor will continue metal framing of the outdoor stem patio ceiling. 
  • The general trades contractor will continue level 1 door and hardware installation. 
  • The resilient flooring contractor will continue the level 1 corridor flooring.
  • The painting contractor will continue final painting of the level 2. 
  • The painting contractor will continue final caulking of all windows.
  • The painting contractor will continue painting of level 1. 
  • The ceiling contractor will continue the lobby ceiling grid and panel installation. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1.
  • The millwork and casework contractor will commence installation of the cafeteria acoustic panels. 
  • The millwork and casework contractor will commence the platform subfloor installation and the media center seating. 
  • The plumbing contractor will continue level 1 classroom sink installation.  
  • The mechanical contractor will continue with project commissioning. 
  • The controls contractor will continue integrating equipment into the building management system. 
  • The electrical contractor will continue installation of the lobby light fixtures. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1  
  • The specialties contractor will continue installation of the toilet accessories and partitions.
  • The misc. metals contractor will continue installation of the interior handrails. 
  • The epoxy flooring contractor will continue the kitchen floor installation. 
  • The shade contractor will continue shade installation in the level 1 classrooms. 

Project Update - Week of April 1st, 2024

Please see the below project update and list of activities scheduled for the week of April 1st, 2024

Jonathan May 0 136 Article rating: No rating
  • The site contractor will continue the outdoor learning lab site preparation and commence the perimeter road landscape area preparation. 
  • The waterproofing contractor will continue caulking of exterior masonry and metal panel joints. 
  • The general trades contractor will commence metal framing of the outdoor stem patio ceiling. 
  • The concrete contractor will commence forming of the outdoor learning lab exterior flatwork. 
  • The general trades contractor will continue level 1 door and hardware installation. 
  • The resilient flooring contractor will continue the level 1 corridor flooring.
  • The painting contractor will continue final painting of the level 2. 
  • The painting contractor will continue final caulking of all windows.
  • The ceiling contractor will continue the lobby ceiling grid and panel installation. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1.
  • The millwork and casework contractor will continue level 1 admin area casework install. 
  • The millwork and casework contractor will commence installation of the cafeteria acoustic panels. 
  • The plumbing contractor will continue level 1 classroom sink installation.  
  • The mechanical contractor will install the RTU catwalks.
  • The mechanical contractor will install the radiant heat panels in the lobby. 
  • The mechanical contractor will continue with initial factory startup of the RTUs. 
  • The controls contractor will continue integrating equipment into the building management system. 
  • The electrical contractor will continue installation of the lobby light fixtures. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1  
  • The specialties contractor will continue installation of the toilet accessories and partitions.
  • The misc. metals contractor will continue installation of the interior handrails. 
  • The epoxy flooring contractor will continue the kitchen floor installation. 
  • The shade contractor will continue shade installation in the level 2 classrooms. 
  • The gym flooring contractor will continue the gym floor installation. 

Saturday Work - March 23, 2024

The project will be working on the site this Saturday 3/23/24. Activities will consist of the following:

Jonathan May 0 135 Article rating: No rating
  • The painting contractor will focus on caulking of the level 2 windows.

Project Update - Week of March 25th, 2024

Please see the below project update and list of activities scheduled for the week of March 25th, 2024

Jonathan May 0 135 Article rating: No rating
  • The site contractor will continue the outdoor learning lab site preperation. 
  • The general trades contrctor will continue installation of interior and exterior expansion joints. 
  • The waterproofing contrator will continue caulking of exterior masonry and metal panel joints. 
  • The concrete contractor will continue forming the front entrance stair foundations and outdoor learning lab concrete sidewalks. 
  • The masonry contractor will continue erecting the final masonry elevation at the project's loading and trashout area. 
  • The general trades contractor will continue  level 1 door and hardware installation. 
  • The general trades contractor will continue taping of stair A closure walls. 
  • The resilient flooring contractor will continue the level 2 corridor flooring and commence level 1 corridor. 
  • The painting contractor will continue final painting of the level 2 area C classrooms.
  • The painting contractor will continue final caulking of all windows.  
  • The ceiling contractor will continue kitchen and lobby ceiling installation. 
  • The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2.
  • The millwork and casework contractor will continue level 1 admin area casework install. 
  • The plumbing contractor will continue level 1 classroom sink installation.  
  • The mechanical contractor will install the RTU catwalks.
  • The mechanical contractor will install the radiant heat panels in the lobby. 
  • The electrical contractor will continue installation of the lobby and kitchen light fixtures. 
  • The electrical contractor will continue initial inspections and testing of the fire alarm system. 
  • The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1  
  • The specialties contractor will continue installation of the toilet partitions. 
  • The misc. metals contractor will continue installation of the interior handrails. 
  • The epoxy flooring contractor will commence the kitchen floor installation. 
  • The shade contractor will commence shade installation in the level 2 classrooms. 
  • The gym flooring contractor will commence the gym subfloor installation. 