Saturday Work - April 6th, 2024 The project will be working on the site this Saturday 4/6/24. Activities will consist of the following: Jonathan May / Friday, April 5, 2024 0 140 Article rating: No rating The general trades contractor will continue misc. tapping activities on level 1. The general trades contractor will continue framing the stem patio ceiling. The general trades contractor will commence removal of the loading dock platform. Read more
Project Update - Week of April 8th, 2024 Please see the below project update and list of activities scheduled for the week of April 8th, 2024 Jonathan May / Friday, April 5, 2024 0 130 Article rating: No rating The site contractor will continue preperation of the perimeter road landscape area and the rain garden. The concrete contractor will continue setting expansion joints for the outdoor learning lab concrete. The concrete contractor will continue forming of the front entrance CIP stairs. The waterproofing contractor will continue caulking of exterior masonry and metal panel joints. The general trades contractor will continue metal framing of the outdoor stem patio ceiling. The general trades contractor will continue level 1 door and hardware installation. The resilient flooring contractor will continue the level 1 corridor flooring. The painting contractor will continue final painting of the level 2. The painting contractor will continue final caulking of all windows. The painting contractor will continue painting of level 1. The ceiling contractor will continue the lobby ceiling grid and panel installation. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1. The millwork and casework contractor will commence installation of the cafeteria acoustic panels. The millwork and casework contractor will commence the platform subfloor installation and the media center seating. The plumbing contractor will continue level 1 classroom sink installation. The mechanical contractor will continue with project commissioning. The controls contractor will continue integrating equipment into the building management system. The electrical contractor will continue installation of the lobby light fixtures. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 The specialties contractor will continue installation of the toilet accessories and partitions. The misc. metals contractor will continue installation of the interior handrails. The epoxy flooring contractor will continue the kitchen floor installation. The shade contractor will continue shade installation in the level 1 classrooms. Read more
Project Update - Week of April 1st, 2024 Please see the below project update and list of activities scheduled for the week of April 1st, 2024 Jonathan May / Friday, March 29, 2024 0 136 Article rating: No rating The site contractor will continue the outdoor learning lab site preparation and commence the perimeter road landscape area preparation. The waterproofing contractor will continue caulking of exterior masonry and metal panel joints. The general trades contractor will commence metal framing of the outdoor stem patio ceiling. The concrete contractor will commence forming of the outdoor learning lab exterior flatwork. The general trades contractor will continue level 1 door and hardware installation. The resilient flooring contractor will continue the level 1 corridor flooring. The painting contractor will continue final painting of the level 2. The painting contractor will continue final caulking of all windows. The ceiling contractor will continue the lobby ceiling grid and panel installation. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1. The millwork and casework contractor will continue level 1 admin area casework install. The millwork and casework contractor will commence installation of the cafeteria acoustic panels. The plumbing contractor will continue level 1 classroom sink installation. The mechanical contractor will install the RTU catwalks. The mechanical contractor will install the radiant heat panels in the lobby. The mechanical contractor will continue with initial factory startup of the RTUs. The controls contractor will continue integrating equipment into the building management system. The electrical contractor will continue installation of the lobby light fixtures. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 The specialties contractor will continue installation of the toilet accessories and partitions. The misc. metals contractor will continue installation of the interior handrails. The epoxy flooring contractor will continue the kitchen floor installation. The shade contractor will continue shade installation in the level 2 classrooms. The gym flooring contractor will continue the gym floor installation. Read more
Saturday Work - March 23, 2024 The project will be working on the site this Saturday 3/23/24. Activities will consist of the following: Jonathan May / Friday, March 22, 2024 0 135 Article rating: No rating The painting contractor will focus on caulking of the level 2 windows. Read more
Project Update - Week of March 25th, 2024 Please see the below project update and list of activities scheduled for the week of March 25th, 2024 Jonathan May / Friday, March 22, 2024 0 135 Article rating: No rating The site contractor will continue the outdoor learning lab site preperation. The general trades contrctor will continue installation of interior and exterior expansion joints. The waterproofing contrator will continue caulking of exterior masonry and metal panel joints. The concrete contractor will continue forming the front entrance stair foundations and outdoor learning lab concrete sidewalks. The masonry contractor will continue erecting the final masonry elevation at the project's loading and trashout area. The general trades contractor will continue level 1 door and hardware installation. The general trades contractor will continue taping of stair A closure walls. The resilient flooring contractor will continue the level 2 corridor flooring and commence level 1 corridor. The painting contractor will continue final painting of the level 2 area C classrooms. The painting contractor will continue final caulking of all windows. The ceiling contractor will continue kitchen and lobby ceiling installation. The ceiling contractor will continue coordinating with the MEP trade partners for ceiling tile device installation on level 1 and 2. The millwork and casework contractor will continue level 1 admin area casework install. The plumbing contractor will continue level 1 classroom sink installation. The mechanical contractor will install the RTU catwalks. The mechanical contractor will install the radiant heat panels in the lobby. The electrical contractor will continue installation of the lobby and kitchen light fixtures. The electrical contractor will continue initial inspections and testing of the fire alarm system. The fire protection contractor will continue setting fire protection heads into completed ceilings on level 1 The specialties contractor will continue installation of the toilet partitions. The misc. metals contractor will continue installation of the interior handrails. The epoxy flooring contractor will commence the kitchen floor installation. The shade contractor will commence shade installation in the level 2 classrooms. The gym flooring contractor will commence the gym subfloor installation. Read more