Saturday Work - October 14th, 2023

The project will be working on the site this Saturday 10/14/23. Activities will consist of the following:

Jonathan May 0 154 Article rating: No rating
  • The electrical contractor will continue power connections of the building's temporary heat equipment. 
  • The plumbing contractor will continue level 1 area A in-wall rough-in. 

Saturday Work - October 7th, 2023

The project will be working on the site this Saturday 10/7/23. Activities will consist of the following:

Jonathan May 0 117 Article rating: No rating
  • The electrical contractor will continue overhead light fixture control installation on level 2 A. 
  • The plumbing contractor will continue level 1 area A in-wall rough-in. 

Project Update - Week of October 10th, 2023

Please see the below project update and list of activities scheduled for the week of 10/9.

Jonathan May 0 102 Article rating: No rating
  • The site contractor will complete kitchen underslab stone preperation and electrical underslab conduit pathways. 
  • The site contractor will continue the Outdoor Learning Lab subgrade preperation of concrete walkways. 
  • The masonry contractor will continue masonry install at the courtyard bumpouts. 
  • The window contractor will continue storefront installation on the classroom wing loop road elevations. 
  • The metal panel contractor will continue the main canopy metal panel ceiling installation. 
  • The general trades contractor will continue interior metal framing and soffit erection on level 1 area A. 
  • The general trades contractor will continue in-wall blocking on level 1 area A. 
  • The general trades contractor will continue drywall and taping on level 1 C. 
  • The painting contractor will continue painting on level 2 area D & A.
  • The ceiling contractor will continue ceiling grid install on level 2 Area C. 
  • The fire protection contractor will continue sprinkler overhead rough-in on level 1 area A & B. 
  • The plumbing contractor will continue pipe insulation on level 1 area D. 
  • The plumbing contractor will continue in-wall rough in on level 1 area A. 
  • The mechanical contractor will continue tie-in of the level 1 area C VAVs. 
  • The mechanical contractor will continue in-wall duct insulation in level 1 A. 
  • The mechanical contractor will continue radiant heat panel installation in the level 2 area A. 
  • The mechanical contractor will continue setting radiant panel into ceiilng grid on level 2 Area C.  
  • The electrical contractor will continue classroom lighting control rough in on level 2 area A.  
  • The electrical contractor will commence light fixture install on level 2 Area C Mock-up room. 
  • The elevator contracotr will commence elevator installation. 

Project Update - Week of October 2. 2023

Please see the below project update and list of activities scheduled for the week of 10/2.

Jonathan May 0 122 Article rating: No rating
  • The site contractor will complete backfill of kitchen underground execation. 
  • The site contractor will commence preperation of the kitchen slab on grade
  • The site contractor will commence the Outdoor Learning Lab subgrade preperation of concrete walkways. 
  • The masonry contractor will continue masonry install at the courtyard bumpouts. 
  • The window contractor will continue storefront installation on the classroom wing courtyard elevations. 
  • The metal panel contractor will continue metal panel installation at the area C south bumpout and the low roof. 
  • The metal panel contractor will commence the main canopy metal panel ceiling installation. 
  • The general trades contrractor will continue interior metal framing on level 1 area A. 
  • The general trades contractor will continue in-wall blocking on level 1 area A. 
  • The general trades contractor will continue hanging drywall on level 1 area C. 
  • The general trades contractor will continue taping on level 1 Area C. 
  • The painting contractor will continue painting on level 2 area D & A.
  • the fire protection contractor will continue sprinkler overhead rough-in on level 1 area A & B. 
  • The plumbing contractor will continue pipe insulation on level 1 area C and D. 
  • The plumbing contractor will continue in-wall rough in on level 1 area A. 
  • The mechanical contractor will continue tie-in of the level 2 VAVs. 
  • The mechanical contractor will commence level 1 VAV tie-in. 
  • The mechanical contractor will continue in-wall duct in level 1 A. 
  • The mechanical contractor will continue radiant heat panel installation in the level 2 area D & A classrooms. 
  • The electrical contractor will commence overhead rough-in in the gym. 
  • The electrical contractor will continue classroom lighting control rough in on level 2 area D & A.  

Saturday Work - September 23rd, 2023

The project will be working on the site this Saturday 9/23/23. Activities will consist of the following:

Jonathan May 0 117 Article rating: No rating
  • The site contractor will commence kitchen underground plumbing excavation
  • The plumbing contractor will continue gas pipe installation to the kitchen. 
  • The plumbing contractor will continue in-wall rough in on level 1 area D. 
  • The electrical contractor will continue lighting control rough in on level 2 area C & D. 
RSS
First34568101112Last

Theme picker