  • The athletic field storage shed construction shall be completed.  
  • The site contractor will be completing general clean-up and placing remaining loam materials around the long jump areas and other misc landscape areas at the perimeter of the track.  Seeding of these lawn areas is tentatively scheduled for the end of the week.   
  • The site contractor will continue with installation of foundation insulation and backfill of foundation walls in Area B.  
  • The site contractor will continue with excavation and sub-grade prep for interior footings in Area B at the Gymnasium.
  • The site contractor will continue with excavation of underground plumbing trenches in Area D of the building.
  • The site contractor shall continue with the installation of the underground sewer line on the South elevation of the building located in the perimeter access road.
  • The site contractor shall continue with the excavation and construction of retaining wall #2 on the South elevation of the building. 
  • The concrete contractor will continue forming and pouring the loading dock foundation walls. 
  • The concrete contractor will continue forming and placing the interior footings in Area B at the Gymnasium.
  • The plumbing enabling contractor shall continue with the installation of the underground plumbing in Area D of the building.
  • The electrical enabling contractor shall continue with the electrical ductbank installation from a previously installed manhole to the BESS vault location.   

Project Update - Week of October 17th 2022

Tripp McElroy III 0 213 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of October 17th 2022. 

  • The athletic field storage shed construction shall be completed.  
  • The site contractor will be completing general clean-up and placing remaining loam materials around the long jump areas and other misc landscape areas at the perimeter of the track.  Seeding of these lawn areas is tentatively scheduled for the end of the week.   
  • The site contractor will continue with installation of foundation insulation and backfill of foundation walls in Area B.  
  • The site contractor will continue with excavation and sub-grade prep for interior isolated footings in Area A.
  • The site contractor will complete back-filling of the underground plumbing trenches in Area C and shall commence with excavation for underground plumbing in Area D of the building.
  • The site contractor shall commence with the installation of the underground sewer line on the South elevation of the building located in the perimeter access road.
  • The site contractor shall commence with the excavation and construction of retaining wall #2 on the South elevation of the building. 
  • The concrete contractor will continue reinforcing, forming and placing portions of the loading dock foundation walls. 
  • The concrete contractor will continue forming and placing the interior isolated footings in Area A.
  • The plumbing enabling contractor shall commence with the installation of the underground plumbing in Area D. 

Project Update - Week of October 11th 2022

Jonathan May 0 210 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of October 11th 2022. 

  • The athletic track line stripper will commence track markings. 
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas B.  
  • The site contractor will commence loading dock footing backfill. 
  • The site contractor will continue installation of the site drainage system below the proposed perimeter access road.
  • The site contractor will continue installation of the site water utility system below the proposed perimeter access road. 
  • The site contractor will continue various grading activities around the site.
  • The site contractor will continue underslab plumbing excavation. 
  • The site contractor will prep and set the BESS system vault and transformer pad. 
  • The concrete contractor will continue forming and placing the loading dock and site wall foundation. 
  • The concrete contractor will continue pouring the interior gym strip footing. 
  • The concrete contractor will continue forming and placing the Area A & B interior concrete foundations.
  • The plumbing enabling contractor will continue layout and installation of the underslab plumbing in Area C.  

Project Update - Week of October 3rd 2022

Jonathan May 0 222 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of October 3rd 2022. 

  • The track surface contractor will continue the track surface installation
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas A & B.  
  • The site contractor will continue foundation excavation of the Area B site wall, the loading dock, and the gym interior strip footing. 
  • The site contractor will continue installation of the site drainage system below the proposed perimeter access road.
  • The site contractor will continue installation of the site water utility system below the proposed perimeter access road. 
  • The site contractor will continue various grading activities around the site.
  • The site contractor will begin building underslab plumbing excavation. 
  • The concrete contractor will continue forming and placing perimeter concrete foundations in Area B. 
  • The concrete contractor will begin forming and installing rebar for the loading dock deep footing. 
  • The concrete contractor will continue pouring the interior gym strip footing. 
  • The concrete contractor will continue forming and placing the Area A & B interior concrete foundations.
  • The plumbing enabling contractor will begin layout and installation of the underslab plumbing in Area C.  

Project Update - Week of September 26th 2022

Jonathan May 0 212 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of September 26th 2022. 

  • The track surface contractor will finalize layout and commence the track surface installation.
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas A & B.  
  • The site contractor will continue foundation excavation of Area B. 
  • The site contractor will continue installation of the site drainage system below the proposed perimeter access road.
  • The site contractor will continue installation of the site water utility system below the proposed perimeter access road. 
  • The site contractor will continue various grading activities around the site.
  • The concrete contractor will continue forming and placing perimeter concrete foundations in Area B. 
  • The concrete contractor will continue forming and placing the Area A & B interior concrete foundations.

 