Project Update - Week of March 27th 2023

Please see the below project update and list of activities scheduled for the week of March 27th 2023

Tripp McElroy III 0 188 Article rating: .3
  • The site contractor shall continue with the installation of drainage infilitration system IT-2 on the South-West side of the site.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking at mechanical equipment and penetration locations.
  • The general trades contractor will continue framing activities including knee walls on the roof levels and beam infills at Areas C & D.  
  • The mechanical contractor shall continue the lay-out and install of equipment sleepers and penetration sleeves on the roof levels of Areas A & B. 
  • The plumbing contractor shall continue the installation of roof drain bodies on Areas C, D & A of the building. 
  • The roofing contractor is scheduled to commence with the installation of roof dense deck and AVB on the roof level of Area C.
  • The concrete contractor is scheduled to place the slabs on deck in Areas C on Wednesday 3/29 and Area D on Friday 3/31.  Concrete deliveries for both of these placements are scheduled to commence at 9AM after the campus drop-off period has completed for the morning.  Due to the concrete finishing effort associated with these activities the work may require an extended day to complete the placement.  This information is currently being communicated and coordinated with the Town Manager's Office and Police Department.  

Project Update - Week of March 20th 2023

Please see the below project update and list of activities scheduled for the week of March 20th 2023

Tripp McElroy III 0 235 Article rating: No rating
  • The site contractor shall continue with the installation of drainage infilitration system IT-2 on the South-West side of the site.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking at mechanical equipment and penetration locations.
  • The general trades contractor will continue framing activities including knee walls on the roof levels and exterior top track on the perimeter of Areas C & A.
  • The concrete contractor shall commence preparation of the slab on deck and installation of rebar and welded wire mesh at the roof-top unit concrete pads on Areas C, D & A of the building.  The placement of these concrete pads are tentatively scheduled for Wednesday 3/22.
  • The mechanical contractor shall commence the lay-out and install of equipment sleepers and penetration sleeves on the roof levels of Areas C & D. 
  • The plumbing contractor shall commence the installation of roof drain bodies on the roof levels of Areas C & D of the building. 
  • The roofing contractor is scheduled to mobilize and deliver to the project site a partial order of roofing materials for Areas C & D of the building on Friday 3/24.

Project Update Week of March 13th 2023

Please see the below project update and list of activities scheduled for the week of March 13th 2023

Jonathan May 0 220 Article rating: No rating
  • The site contractor will begin the installation of drainage infilitration system IT-2 on the South-West side of the site.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking.
  • The general trades contractor will continue framing activities including knee walls on the roof levels and exterior beam infills on the perimeter of Areas C, D, & A.
  • The concrete contractor will continue preparation of the slab on deck and installation of concrete rebar and welded wire mesh in all level 2 areas.
  • The plumbing contractor will continue to layout roof and level 2 openings as well as install level 2 slab on deck sleeves. 
  • The building electrical contractor will continue layout and installation of underslab electrical and telecommunications conduit. 

Project Update - Week of March 6th 2023

Please see the below project update and list of activities scheduled for the week of March 6th 2023

Jonathan May 0 206 Article rating: No rating
  • The site contractor will continue with the installation of drainage infilitration system IT-1A on the South-West side of the site.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking.
  • The general trades contractor shall commence with framing activities including knee walls on the roof levels and exterior beam infills on the perimeter of Areas C & D of the building.  
  • The concrete contractor shall continue and complete forming and placing the reverse isolation boxes located in the slabs on grade of the building this week.  Concrete placements will be weather-temperature dependant.
  • The concrete contractor will continue preparation of the slab on deck and installation of concrete rebar and welded wire mesh in all level 2 areas.
  • The roofing contractor will continue installation of various roof AVB details needed to support the continuation of roof blocking activities. 
  • The building electrical contractor will mobilize to site and layout and installation of underslab electrical and telecommunications conduit. 

Project Update - Week of February 27th 2023

Please see the below project update and list of activities scheduled for the week of February 27th 2023

Tripp McElroy III 0 223 Article rating: No rating
  • The site contractor shall continue the excavation and construction of retaining wall #9 on the South-West side of the site.
  • The site contractor shall commence with the installation of drainage infilitration system IT-1A on the South-West side of the site.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking at the roof levels.  
  • The general trades contractor shall commence with framing activities including knee walls on the roof levels and exterior beam infills on the perimeter of Areas C & D of the building.  
  • The concrete contractor shall continue and complete with forming and placing the reverse isolation boxes located in the slabs on grade of the building this week.  Concrete placements will be weather-temperature dependant.
  • The concrete contractor has rebar and welded wire mesh scheduled for delivery to the site on Wednesday 3/1.  Slab on deck preparation for Areas C & D shall commence once materials arrive and are offloaded to the deck levels.
  • The roofing contractor is scheduled to commence the installation of various roof AVB details needed to support the continuation of roof blocking activites.
RSS
First1314151618202122Last

Theme picker