Saturday Work - August 20th 2022

Tripp McElroy III 0 311 Article rating: No rating

The project has a street sweeper scheduled for Saturday 8/20 to sweep around the perimeter of the existing Florence Roche Elementary and Middle School South buildings where the underground utility work was completed this summer.     

Project Update - Week of August 15th 2022

Tripp McElroy III 0 287 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of 8/15.

  • Exporting excess materials from the site shall continue this week.   
  • The site contractor shall continue placing the loam materials beneath the new athletic field.
  • The site contractor shall place the top coat of asphalt at the new Athletic Track area on Thursday 8/18. 
  • Prep and placement of the concrete track game pads shall continue this week.
  • Continue with site clean-up and subgrade prep to support asphalt placement at the utility trenches next week.  Asphalt placement is scheduled for Thursday 8/18 and Friday 8/19.  Site restoration and re-establishment of the temporary construction fence line shall commence this week adjacent to the Middle School South building.   
  • The site and electrical contractor shall continue with the construction of the underground electrical & communications ductbank work located in the utility corridor and continue towards Champney Street.        
  • The site contractor shall continue importing and placing structural fill materials in Areas A & B of the new building. 
  • The concrete contractor is scheduled to mobilize on Monday 8/15 and commence lay-out and construction of foundation formwork in Areas C & D of the new building.  The first concrete placement is tentatively scheduled for Thursday 8/18.  
  • The project is scheduled to receive a series of reinforcing steel deliveries on Tuesday 8/16 and Thursday 8/18 of this week to support foundation construction.     

Saturday Work - August 13th 2022

Tripp McElroy III 0 244 Article rating: No rating

The project will be working on the site this Saturday 8/13/22.  Activities will consist of the following: 

  • The site contractor shall continue with spreading the loam material at the new athletic field area.
  • Excavation and sub-grade prep to support the installation of underground electrical conduit shall continue along the South elevation of the new athletic track area.   
  • The site contractor will be continuing with subgrade prep on the utility trenches at the perimeter of the Middle School South building in preparation for paving these trenches the week of 8/15.

This weekend work schedule has been communicated and coordinated with the Town Manager's Office.

Project Update - Week of August 8th 2022

Tripp McElroy III 0 299 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of 8/8.

  • Exporting excess materials from the site shall continue this week.   
  • The site contractor shall complete the spreading of ordinary fill materials and commence placing the loam materials beneath the new athletic field.
  • The site contractor shall fine grade and place the asphalt binder at the new Athletic Track area.
  • Prep and placement of the concrete track game pads shall commence this week.
  • Complete the remaining drainage piping in the utility corridor and continue with site clean-up and subgrade prep to support asphalt placement at the utility trenches next week. 
  • The site and electrical contractor shall commence the construction of the underground electrical & communications ductbank work located in the utility corridor South of the Middle School South Building.        
  • The site contractor shall continue and complete the excavation and sub-grade prep for the concrete foundations in Area C & D of the new building. 
  • Processing of onsite soils from in and around the existing track shall continue this week. 

Saturday Work - August 6th 2022

Tripp McElroy III 0 296 Article rating: No rating

The project will be working on the site this Saturday 8/6/22.  Activities will consist of the following: 

  • The site contractor shall continue with screening loam materials and commence spreading the loam material at the new athletic field area. 
  • The site contractor will be continuing with subgrade prep on the utility trenches at the perimeter of the Middle School South building in preparation for paving these trenches the week of 8/8.
  • The site contractor shall continue with excavation and sub-grade prep for the concrete foundations in Area C of the new building. 

This weekend work schedule has been communicated and coordinated with the Town Manager's Office.

RSS