Project Update - Week of September 19th 2022

Jonathan May 0 271 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of September 19th 2022. 

  • The irrigation with complete final position of irrigation heads. 
  • The track surface contractor will begin placing of the synthetic track surface. 
  • The electrical contractor in coordiantion with GELD will complete the ductbanks to Champney Street and connect to the new utility poles provided by GELD. 
  • The concrete contractor will continue forming and placing concrete foundations in Areas A & B.  
  • Concrete placements are tentatively scheduled for Monday, 9/19, Wednesday, 9/21, and Friday, 9/23. 
  • The site contractor will continue exterior insulation install and backfill of the foundation walls in Areas C & D.  
  • The site contractor will continue foundation excavation of Areas A & B. 
  • The site contractor will continue utility installation below the proposed perimeter access road.
  • The site contractor will continue various grading activities around the site. 

Town of Groton Special Town Meeting Information

Tripp McElroy III 0 279 Article rating: No rating

The Town of Groton Special Town Meeting is MONDAY, September 12, 2022 at 7:00 p.m. at the Groton Middle School Performing Arts Center

The purpose of the meeting is to request authorization to increase the borrowing for the Florence Roche Elementary School Project by $9.5 million.

 

To review the VIDEO OF THE INFORMATION SESSION (presented at the FRBC, last night, 09/08/22) please see the link below:

https://us02web.zoom.us/.../KlQBkfAldgZGXO7aYDZlGSIxVO0Kt...

Passcode: #4AZLdhK

 

For those with Kids - BABYSITTING IS AVAILABLE (6:30 PM until end of Meeting, Ages 5 thru 12) - SIGN UP BELOW:

https://docs.google.com/.../1bAjArPe839hJpimQ9jzokQW.../edit

Project Update - Week of September 5th 2022

Tripp McElroy III 0 271 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of 9/5.  

  • The fencing contractor will commence with the fence installation on the West side of the new track and field. 
  • The electrical contractor will continue with the electrical work to support power to the new athletic field shed location.
  • The site contractor shall commence prepping and raking out the atheltic field loam in preparation for Sod materials to be delivered the week of 9/12.
  • The track surfacing contractor is scheduled to mobilize to the project site on Tuesday 9/6 and commence their pre-work inspection of the track surface.
  • The electrical and site contractors will continue the electrical ductbank installation towards the BESS system pad. 
  • The site contractor will continue various grading activities around the site.
  • The site contractor shall continue with foundation insulation installation and back-filling activities in Areas C & D. 
  • The concrete contractor will continue and complete foundation construction for the classroom wings in Areas C & D. 
  • The site contractor will continue to excavate for foundations in Areas A & B. 
  • The contractor shall commence with the construction of footings in Area A.
  • The concrete contractor is scheduled to receive a rebar delivery for Area A on Wednesday 9/7 and Anchor Bolts for Area A on Friday 9/9.  
  • Concrete placements are tentatively scheduled for Wednesday 9/7 and Friday 9/9.
  • Due to the Labor Day holiday on Monday 9/5 there will not be any work activities onsite.

Project Update - Week of August 29th 2022

Jonathan May 0 251 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of 8/29.

  • Exporting excess materials from the site shall continue this week.   
  • The fencing contractor will complete the athletic field retaining wall fence installation. 
  • The irrigation system will be completed
  • The drainage structure covers will be installed
  • The electrical contractor will commence providing power to the new athletic field shed location 
  • The concrete contractor will continue foundation construction for the classroom wings Area C & D. 
  • The site contractor will continue to excavate the Area A & B foundations. 
  • The electrical and site contractors will continue the electrical ductbank installation down Champney Street. 
  • The site contractor will continue various grading activities around the site. 

Project Update - Week of August 22nd 2022

Tripp McElroy III 0 303 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 8/22.

  • Exporting excess materials from the site shall continue this week.   
  • Complete the construction of the long jump pits at the new track area. 
  • Commence the installation of the irrigation system in the new athletic field.
  • Continue with site restoration and re-establishment of the temporary construction fence line shall continue this week adjacent to the Middle School South building.   
  • The site and electrical contractor shall continue with the construction of the underground electrical & communications ductbank working South on the site towards Champney Street. 
  • The site contractor shall continue with excavation and subgrade prep for concrete foundations in Area A of the building.      
  • The site contractor shall continue importing and placing structural fill materials in Area B of the new building. 
  • The concrete contractor shall continue construction of foundation formwork in Area C  and commence in Area A of the new building.  Foundation wall construction shall commence in Area D of the new building.  Concrete placements are tentatively scheduled for Wednesday 8/24 and Friday 8/26 this week.  