Project Update - Week of June 6th 2022

Tripp McElroy III 0 297 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 6/6.

  • The site contractor shall continue their cut to fill effort of the onsite soil materials at the new track & field area of the project site.   The applicable project consultants shall be onsite to witness these work activities.  
  • Exporting excess materials from the site shall continue this week. 
  • Commence subgrade prep for the retaining walls adjacent to the new athletic track.  The retaining wall block materials are tentatively scheduled to be delivered to the site this week.  This delivery may shift to the following week of 6/13.     
  • The project's groundbreaking event has been rescheduled for Monday 6/6 at 4pm! 

Project Update - Week of May 30th 2022

Tripp McElroy III 0 345 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 5/30.

  • Due to the holiday on Monday 5/30, there will not be any work on the project site.
  • The site contractor shall continue with stripping topsoil activities at the new building location.  
  • Exporting topsoil materials offsite to the Department of Public Works property shall commence on Tuesday 5/31.  This has been coordinated with the department. 
  • The site contractor shall commence their cut to fill effort of the onsite soil materials at the new track & field area of the project site.   The applicable project consultants shall be onsite to witness the start of this work.
  • The project's groundbreaking event is scheduled for Wednesday 6/1 at 4pm! 

Memorial Day Weekend Work Schedule

Tripp McElroy III 0 341 Article rating: 5.0

There will not be any work activities on the project site Friday 5/27 and Monday 5/30.  Due to the upcoming holiday weekend the site contractor has been working extended hours this week to allow Friday 5/27 be a non-work day for their crew.  Monday 5/30 is Memorial Day and recognized as a holiday by the trades.     

Project Update - Week of May 23rd 2022

Tripp McElroy III 0 317 Article rating: 5.0

Please see the below project update and list of activities scheduled for the week of 5/23.

  • The site contractor shall continue with stripping topsoil activities at the new track location.  The project's LSP shall continue on-site monitoring of these activities as required.  
  • Tentatively start exporting topsoil materials offsite to the Department of Public Works property.  This activity may shift to commence the following week of 5/30. 
  • Tree removal is scheduled to commence on Monday 5/23 and will continue through the week.  This crew shall commence their work in the area of the Battery Emergency Storage System (BESS) on the project site, which is adjacent to the existing School District Offices.
  • The site contractor shall commence stripping of topsoil at the new building location this week.  

Project Update - Week of May 13th 2022

Please see the below project update and list of activities scheduled for the week of 5/16.

Jonathan May 0 353 Article rating: 5.0
  • Complete Con-Com and Stormwater Agent inspection of erosion control measures. 
  • The site contractor will begin stripping topsoil at the new track & field location.
  • The site contractor will begin demolition of existing field equipment, fencing, benches, etc.
  • Electrical and plumbing contractors will complete the construction trailer electrical and plumbing hookups. 

 