Saturday Work - July 8th, 2023 The project will be working on the site this Saturday 7/8/23. Activities will consist of the following: Jonathan May / Friday, July 7, 2023 0 208 Article rating: No rating The general trades contractor will continue interior layout activities. The waterproofing contractor will contue waterproofing efforts in Area B. Read more
Project Update - Week of July 10th 2023 Please see the below project update and list of activities scheduled for the week of July 10th 2023 Jonathan May / Friday, July 7, 2023 0 231 Article rating: No rating The general trades contractor will continue exterior framing & sheathing in Areas A & B. The general trades contractor will continue layout and interior framing on level 2 Areas A & B. The waterproofing contractor will continue installation of waterproofing membrane in Areas A & B. The masonry contractor will continue installation of exterior masonry veneer in Areas A & B The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas D & A, and Level 1 Area D. The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. The fire protection contractor will continue installation of fire protection pipe on Level 1 Area C. The window contractor will continue with installation of the metal windows in Area C & D. Read more
Project Update - Week of July 3rd 2023 Please see the below project update and list of activities scheduled for the week of July 3rd 2023 Tripp McElroy III / Friday, June 30, 2023 0 257 Article rating: No rating Placement of the slab on grade in the gymnasium and lobby area is tentatively scheduled for Thursday 7/6 or Friday 7/7 weather dependant. The general trades contractor will continue exterior framing & sheathing in Areas A & B. The general trades contractor will continue layout and interior framing on level 2 Areas A & B. The waterproofing contractor will continue installation of waterproofing membrane in Areas A & B. The masonry contractor will continue installation of exterior masonry veneer in Areas C & D and commence installation on Areas A & B. The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas D & A, and Level 1 Area D. The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. The fire protection contractor will commence installation of fire protection pipe on Level 1 Area C. The window contractor will commence with installation of the metal windows on Area C of the building. The project will be closed on Tuesday 7/4 due to the holiday. Read more
Project Update - Week of June 19th, 2023 Please see the below project update and list of activities scheduled for the week of June 19th 2023 Jonathan May / Sunday, June 18, 2023 0 238 Article rating: No rating The concrete contractor shall complete the preperation of the Slab on Grades in Area A and Gymnasium of the building. Concrete placement of of the gymnasium is tentatively scheduled for Thursday, 6.22. The misc metals contractor will continue erection of Stair C. The general trades contractor will continue exterior framing in areas A & B. The general trades contractor will continue layout and interior framing on level 2 areas C & D. The general trades contractor will continue layout of interior walls on level 2 A. The waterproofing contractor will continue installation of waterproofing membrane in areas A & B. The masonry contractor will continue installation of exterior masonry veneer in Areas C & D. The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas C, D, & A, and Level 1 Area C. The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. The fire protection contractor will continue installation of fire protection pipe on Level 2 Area A. The roofing contractor will ocmmence installation of the roofing system on the Area B low roof. Read more
Project Update - Week of June 12th, 2023 Please see the below project update and list of activities scheduled for the week of June 12th 2023 Tripp McElroy III / Friday, June 9, 2023 0 263 Article rating: No rating The concrete contractor shall commence with the preperation of the Slab on Grades in Area A and Gymnasium of the building. Concrete placement of Stairs A & D are tentatively scheduled for next week. The misc metals contractor is scheduled to deliver and commence erection of Stair C. The general trades contractor will continue exterior framing in areas A & B. The waterproofing contractor will continue installation of waterproofing membrane in areas A & B. The masonry contractor will continue installation of exterior masonry veneer in Areas C & D. The general trades contractor will continue interior framing in Area C & D Level 2 classroom wings. The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas C, D, & A, and Level 1 Area C. The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and commence in-wall rough-in on Level 2 Areas C & D. The fire protection contractor will continue installation of fire protection pipe on Level 2 Area D. Read more