Saturday Work - July 8th, 2023

The project will be working on the site this Saturday 7/8/23. Activities will consist of the following:

Jonathan May 0 208 Article rating: No rating
  • The general trades contractor will continue interior layout activities. 
  • The waterproofing contractor will contue waterproofing efforts in Area B.

Project Update - Week of July 10th 2023

Please see the below project update and list of activities scheduled for the week of July 10th 2023

Jonathan May 0 231 Article rating: No rating
  • The general trades contractor will continue exterior framing & sheathing in Areas A & B. 
  • The general trades contractor will continue layout and interior framing on level 2 Areas A & B. 
  • The waterproofing contractor will continue installation of waterproofing membrane in Areas A & B. 
  • The masonry contractor will continue installation of exterior masonry veneer in Areas A & B
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas D & A, and Level 1 Area D. 
  • The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. 
  • The fire protection contractor will continue installation of fire protection pipe on Level 1 Area C. 
  • The window contractor will continue with installation of the metal windows in Area C & D.

Project Update - Week of July 3rd 2023

Please see the below project update and list of activities scheduled for the week of July 3rd 2023

Tripp McElroy III 0 257 Article rating: No rating
  • Placement of the slab on grade in the gymnasium and lobby area is tentatively scheduled for Thursday 7/6 or Friday 7/7 weather dependant. 
  • The general trades contractor will continue exterior framing & sheathing in Areas A & B. 
  • The general trades contractor will continue layout and interior framing on level 2 Areas A & B. 
  • The waterproofing contractor will continue installation of waterproofing membrane in Areas A & B. 
  • The masonry contractor will continue installation of exterior masonry veneer in Areas C & D and commence installation on Areas A & B. 
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas D & A, and Level 1 Area D. 
  • The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. 
  • The fire protection contractor will commence installation of fire protection pipe on Level 1 Area C. 
  • The window contractor will commence with installation of the metal windows on Area C of the building.
  • The project will be closed on Tuesday 7/4 due to the holiday.

Project Update - Week of June 19th, 2023

Please see the below project update and list of activities scheduled for the week of June 19th 2023

Jonathan May 0 238 Article rating: No rating
  • The concrete contractor shall complete the preperation of the Slab on Grades in Area A and Gymnasium of the building.
  • Concrete placement of of the gymnasium is tentatively scheduled for Thursday, 6.22. 
  • The misc metals contractor will continue erection of Stair C. 
  • The general trades contractor will continue exterior framing in areas A & B. 
  • The general trades contractor will continue layout and interior framing on level 2 areas C & D. 
  • The general trades contractor will continue layout of interior walls on level 2 A. 
  • The waterproofing contractor will continue installation of waterproofing membrane in areas A & B. 
  • The masonry contractor will continue installation of exterior masonry veneer in Areas C & D. 
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas C, D, & A, and Level 1 Area C. 
  • The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and continue in-wall rough-in on Level 2 Areas C & D. 
  • The fire protection contractor will continue installation of fire protection pipe on Level 2 Area A. 
  • The roofing contractor will ocmmence installation of the roofing system on the Area B low roof. 

Project Update - Week of June 12th, 2023

Please see the below project update and list of activities scheduled for the week of June 12th 2023

Tripp McElroy III 0 263 Article rating: No rating
  • The concrete contractor shall commence with the preperation of the Slab on Grades in Area A and Gymnasium of the building.
  • Concrete placement of Stairs A & D are tentatively scheduled for next week.
  • The misc metals contractor is scheduled to deliver and commence erection of Stair C. 
  • The general trades contractor will continue exterior framing in areas A & B. 
  • The waterproofing contractor will continue installation of waterproofing membrane in areas A & B.
  • The masonry contractor will continue installation of exterior masonry veneer in Areas C & D. 
  • The general trades contractor will continue interior framing in Area C & D Level 2 classroom wings. 
  • The mechanical contractor will continue installation of overhead mechanical duct and piping on Level 2 Area A and Level 1 C. 
  • The plumbing contractor will continue installation of overhead and in-wall plumbing piping on Level 2 Areas C, D, & A, and Level 1 Area C. 
  • The electrical contractor will continue installation of overhead rough-in on Level 2 Area A and commence in-wall rough-in on Level 2 Areas C & D. 
  • The fire protection contractor will continue installation of fire protection pipe on Level 2 Area D.