Project Update - Week of August 15th 2022 Tripp McElroy III / Friday, August 12, 2022 0 229 Article rating: No rating Please see the below project update and list of activities scheduled for the week of 8/15. Exporting excess materials from the site shall continue this week. The site contractor shall continue placing the loam materials beneath the new athletic field. The site contractor shall place the top coat of asphalt at the new Athletic Track area on Thursday 8/18. Prep and placement of the concrete track game pads shall continue this week. Continue with site clean-up and subgrade prep to support asphalt placement at the utility trenches next week. Asphalt placement is scheduled for Thursday 8/18 and Friday 8/19. Site restoration and re-establishment of the temporary construction fence line shall commence this week adjacent to the Middle School South building. The site and electrical contractor shall continue with the construction of the underground electrical & communications ductbank work located in the utility corridor and continue towards Champney Street. The site contractor shall continue importing and placing structural fill materials in Areas A & B of the new building. The concrete contractor is scheduled to mobilize on Monday 8/15 and commence lay-out and construction of foundation formwork in Areas C & D of the new building. The first concrete placement is tentatively scheduled for Thursday 8/18. The project is scheduled to receive a series of reinforcing steel deliveries on Tuesday 8/16 and Thursday 8/18 of this week to support foundation construction. Read more
Saturday Work - August 13th 2022 Tripp McElroy III / Friday, August 12, 2022 0 173 Article rating: No rating The project will be working on the site this Saturday 8/13/22. Activities will consist of the following: The site contractor shall continue with spreading the loam material at the new athletic field area. Excavation and sub-grade prep to support the installation of underground electrical conduit shall continue along the South elevation of the new athletic track area. The site contractor will be continuing with subgrade prep on the utility trenches at the perimeter of the Middle School South building in preparation for paving these trenches the week of 8/15. This weekend work schedule has been communicated and coordinated with the Town Manager's Office. Read more
Project Update - Week of August 8th 2022 Tripp McElroy III / Friday, August 5, 2022 0 234 Article rating: No rating Please see the below project update and list of activities scheduled for the week of 8/8. Exporting excess materials from the site shall continue this week. The site contractor shall complete the spreading of ordinary fill materials and commence placing the loam materials beneath the new athletic field. The site contractor shall fine grade and place the asphalt binder at the new Athletic Track area. Prep and placement of the concrete track game pads shall commence this week. Complete the remaining drainage piping in the utility corridor and continue with site clean-up and subgrade prep to support asphalt placement at the utility trenches next week. The site and electrical contractor shall commence the construction of the underground electrical & communications ductbank work located in the utility corridor South of the Middle School South Building. The site contractor shall continue and complete the excavation and sub-grade prep for the concrete foundations in Area C & D of the new building. Processing of onsite soils from in and around the existing track shall continue this week. Read more
Saturday Work - August 6th 2022 Tripp McElroy III / Thursday, August 4, 2022 0 234 Article rating: No rating The project will be working on the site this Saturday 8/6/22. Activities will consist of the following: The site contractor shall continue with screening loam materials and commence spreading the loam material at the new athletic field area. The site contractor will be continuing with subgrade prep on the utility trenches at the perimeter of the Middle School South building in preparation for paving these trenches the week of 8/8. The site contractor shall continue with excavation and sub-grade prep for the concrete foundations in Area C of the new building. This weekend work schedule has been communicated and coordinated with the Town Manager's Office. Read more
Project Update - Week of August 1st 2022 Tripp McElroy III / Friday, July 29, 2022 0 188 Article rating: No rating Please see the below project update and list of activities scheduled for the week of 8/1. The site contractor shall continue their cut to fill effort of the onsite soil materials at the new track & field area of the project site. The applicable project consultants shall be onsite to witness these work activities. Exporting excess materials from the site shall continue this week. The site contractor shall continue with the installation of drainage piping and structures in the utility corridor between the existing Florence Roche and Middle School South buildings. Connection and tie-in of a new water valve is scheduled to occur on Tuesday 8/2. This shut-down affects the water service to the Middle School South building. This work and shut-down has been communicated and coordinated with the School District, Town Water Dept and Fire Dept. The site contractor shall continue with screening and amending onsite loam materials to be used at and around the new atheltic field. Rough grading of the new track sub-grade shall continue and be completed next week. Fine grading activities are scheduled to commence at the end of next week. The site contractor shall commence excavation and sub-grade prep for the concrete foundations in Area C of the new building. Processing of onsite soils from in and around the existing track shall commence on Monday. Read more