Project Update - Week of January 23rd 2023

Please see the below project update and list of activities scheduled for the week of January 23rd 2023

Tripp McElroy III 0 183 Article rating: No rating
  • The site contractor shall commence with the excavation and installation of drainage lines in the outdoor learning space between Areas C & D of the building.   
  • The structural steel contractor shall continue with decking & detailing activities in Area A of the building and is scheduled to commence these activities in Area B of the building.   
  • The structural steel contractor is scheduled to complete steel erection activities in Area B of the building next week.
  • The project has steel joist deliveries scheduled for Tuesday 1/24 and Wednesday 1/25 for the Cafeteria area of the building.
  • The general trades contractor shall continue with mobilizing activities on the project site.

Revised Topping Off Beam Signing Schedule

Tripp McElroy III 0 174 Article rating: No rating

Due to the inclement weather today (1/13/23) the project has closed the beam signing area to the public. 

The project will have the beam signing area open to the public on Monday 1/16 from 7:30AM - 3:00PM to offer an additional opportunity to sign the beam.   

Project Update - Week of January 16th 2023

Please see the below project update and list of activities scheduled for the week of January 16th 2023

Tripp McElroy III 0 175 Article rating: No rating
  • The site contractor shall continue with the excavation and sub-grade prep to construct the site retaining wall along the projects site access road. 
  • The structural steel contractor shall continue with welding & detailing activities for Areas C & D of the building.
  • The structural steel contractor shall continue with decking & detailing activities in Area A of the building.   
  • The structural steel contractor shall continue with steel erection in Area B of the building.
  • The project has structural steel and/or metal deck deliveries scheduled for Monday 1/16 through Wednesday 1/18 and Friday 1/20.
  • The general trades contractor is scheduled to mobilize onsite Tuesday 1/17 and commence stair tower construction to provide access to all floor levels in Areas C & D of the building. 
  • The project's Steel Topping Off Ceremony is scheduled for Tuesday 1/17 at 9:30AM.  Please refer to the School District's website for additional information about the event.  

Project Update - Week of January 9th 2023

Please see the below project update and list of activities scheduled for the week of January 9th 2023

Tripp McElroy III 0 189 Article rating: No rating
  • The site contractor shall continue with the excavation and sub-grade prep to construct the site retaining wall along the projects site access road. 
  • The structural steel contractor shall continue with welding & detailing activities for Area C of the building.
  • The structural steel contractor is scheduled to commence welding of the composite nelson studs for Area D of the building.  Note this is a weather dependant activity. 
  • The structural steel contractor shall continue steel erection for Area A of the building and commence decking & detailing activities in this area. 
  • The project has structural steel and/or metal deck deliveries scheduled for Monday 1/9 through Thursday 1/12.

Project Update - Week of December 19th 2022

Please see the below project update and list of activities scheduled for the week of December 19th 2022

Jonathan May 0 190 Article rating: No rating
  • The electrical enabling contractor shall complete permanent power conduit installation to the main electric room. 
  • The site contractor shall continue with the excavation and installation of the new drainage line and structures along the projects site access road. 
  • The structural steel contractor will mobilize to site and begin receiving steel deliveries. 
  • The structural steel contractor shall commence steel erection of the Area C Classroom Wing. 
RSS
First1213141517192021Last

Theme picker