Saturday Work - August 19th, 2023

The project will be working on the site this Saturday 8/19/23. Activities will consist of the following:

Jonathan May 0 234 Article rating: No rating
  • The general trades contractor shall continue exterior sheathing on the area B west elevation. 
  • The general trades contractor will continue interior insulation and drywall installation on level 2 C & D. 
  • The general trades contractor will continue framing and drywall installation of the electrical rooms. 
  • The mechanical contractor will continue the build-out of the mechanical room. 
  • The mechanical contractor will continue installation of mechanical duct on level 1 area D and A. 
  • The waterproofing contractor will continue waterproofing of the kitchen exterior wall and the area D storefront openings. 

Project Update - Week of August 21st, 2023

Please see the below project update and list of activities scheduled for the week of August 21st, 2023

Jonathan May 0 255 Article rating: No rating
  • The waterproofing contractor will continue waterproofing of the storefront openings. 
  • The masonry contractor will masonry installation on the area B west elevation. 
  • The window contractor will continue window installation in area A. 
  • The roofing contractor will continue instllation of the metel roof edge. 
  • The metal panel contractor will continue metal panel installation on the outdoor learning lab elevations. 
  • The concrete contractor will continue layout and installtion of formwork for interior equipment pads and elevated slabs. 
  • The general trades contractor will continue insulation and drywall installation on level 2 C&D as well as the remaining electric rooms on level 1. 
  • The painting contractor will continue painting of the electric rooms in preperation for the electrical contractor's buildout.
  • The electrical contractor will continue build out of the level 2 and level 1 electrical room buildout including the main electric room.  
  • The electrical contractor will continue in wall rough-in on level 1 areas C & D. 
  • The mechanical contractor will continue duct installation on level 1 area D & A. 
  • The mechanical contractor will continue displacement diffuser installation on level 1. 
  • The mechanical and plumbing contractor will continue insulation installation for pipe and ductwork.
  • The mechanical contractor will continue in-wall rough-in of mechanical control devices on level 1. 
  • The mechanical contracotr will continue mechanical room equipment setting and tie-in of piping. 
  • The fire protection contractor will continue overhead installation of sprinkler pipe on level 1 area A. 
  • The plumbing contractor will continue in-wall rough-in on level 1 areas C & D.  

Saturday Work - August 12th 2023

The project will be working on the site this Saturday 8/12/23. Activities will consist of the following:

Tripp McElroy III 0 278 Article rating: No rating
  • The window contractor shall continue with the installation of perimeter foam and sealant details at the windows in Area C-Level 2.
  • The general trades contractor shall be insulating the exterior walls in Area C-Level 2 and framing & sheathing the walls of the Main Mechanical room.
  • The electrical contractor shall continue with in-wall rough-in in Area A-Level 2 and Area C-Level 1.
  • The plumbing contractor shall continue with in-wall rough-in in Area C-Level 1.

This weekend work schedule has been communicated and coordinated with the Town Manager's Office.

Saturday Work - August 5th 2023

The project will be working on the site this Saturday 8/5/23. Activities will consist of the following:

Jonathan May 0 244 Article rating: No rating
  • The general trades contractor will continue instllation of the low roof skylight framing and blocking. 
  • The plumbing continue will continue with plumbing installation on level 1 area C as well as gas pipping on level 1. 
  • The mechanical piping contractor will continue pipping installation in the mechanical room. 
  • The electrical contractor will continue in-wall rough-in on level 2. 

Project Update - Week of August 7th, 2023

Please see the below project update and list of activities scheduled for the week of August 7th, 2023.

Jonathan May 0 228 Article rating: No rating
  • The general trades contractor will continue drywall and taping of the level 2 area C & D electric rooms.
  • The general trades contractor will continue interior framing on level 1 areas C & D.
  • The general trades contractor will commence interior drywall and insulation on level 2 C.
  • The concrete contractor will form and place the Stair B elevated slab.
  • The concrete contractor will form and place the platform stairs and ramps.
  • The concrete contractor will pour the main electric room slab on grade.
  • The mechanical contractor will continue duct installation on level 1 D & A.
  • The mechanical contractor will continue duct insulation install on level 2.
  • The plumbing contractor will continue in-wall rough in on level 1 C
  • The plumbing contractor will continue gas pipe installation on level 1.
  • The plumbing contractor will commence roof drain tie-in in the gym.
  • The roofing contractor will continue roof edge metal installation.
  • The electrical contractor will continue in-wall rough in on level 2 A and level 1 C.
  • The electrical contractor will continue buildout of the level 2 area C & D electrical rooms.
  • The fireproofing contractor will continue sprinkler pipe installation on level 1 A & B.
  • The masonry contractor will continue masonry veneer installation on A & B exterior elevations.
  • The waterproofing contractor will continue waterproofing membrane on the west elevation of area A & B.
  • The metal panel contractor will continue panel installation on area C & D east bump outs.
  • The metal windows contractor will continue window installation on level 2 A &
RSS
First1213141517192021Last

Theme picker