Project Update - Week of February 27th 2023

Please see the below project update and list of activities scheduled for the week of February 27th 2023

Tripp McElroy III 0 198 Article rating: No rating
  • The site contractor shall continue the excavation and construction of retaining wall #9 on the South-West side of the site.
  • The site contractor shall commence with the installation of drainage infilitration system IT-1A on the South-West side of the site.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking at the roof levels.  
  • The general trades contractor shall commence with framing activities including knee walls on the roof levels and exterior beam infills on the perimeter of Areas C & D of the building.  
  • The concrete contractor shall continue and complete with forming and placing the reverse isolation boxes located in the slabs on grade of the building this week.  Concrete placements will be weather-temperature dependant.
  • The concrete contractor has rebar and welded wire mesh scheduled for delivery to the site on Wednesday 3/1.  Slab on deck preparation for Areas C & D shall commence once materials arrive and are offloaded to the deck levels.
  • The roofing contractor is scheduled to commence the installation of various roof AVB details needed to support the continuation of roof blocking activites.

Project Update - Week of February 20th 2023

Tripp McElroy III 0 175 Article rating: No rating
  • The site contractor shall complete the installation of drainage infilitration system IT-1B on the South-West side of the site.
  • The site contractor shall re-commence and complete the 24" drainage line on the South-West side of the site. 
  • The site contractor shall re-commence the excavation and construction of retaining wall #9 on the South-West side of the site.
  • The general trades contractor shall continue with the lay-out and installation of perimeter roof blocking on Area A of the building.  
  • The concrete contractor shall continue with forming and placing the reverse isolation boxes located in the slabs on grade of the building this week.
  • There will not be any work activities on the project site Monday 2/20 due to the President's Day Holiday. 

Project Update - Week of February 13th 2023

Please see the below project update and list of activities scheduled for the week of February 13th 2023

Tripp McElroy III 0 180 Article rating: No rating
  • The site contractor shall continue with the installation of drainage infilitration system IT-1B on the South-West side of the site.
  • The site contractor shall commence with the removal of unsuitable soil materials on Wednesday 2/15 and is tentatively scheduled to be completed by the end of the week.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking on Areas C & D of the building.  
  • The concrete contractor shall commence with forming and placing the reverse isolation boxes located in the slabs on grade of the building this week.
  • There will not be any work activities on the project site Monday 2/20 due to the President's Day Holiday. 

Project Update - Week of February 6th 2023

Please see the below project update and list of activities scheduled for the week of February 6th 2023

Tripp McElroy III 0 190 Article rating: 5.0
  • The site contractor shall commence with the installation of crushed stone materials below the slab on grade in Area C of the building.
  • The structural steel contractor shall continue with decking & detailing activities in Area B of the building.  Portions of this work is weather dependant.  They will commence with demobilizing activites on the project site.  
  • The general trades contractor shall commence with the lay-out and installation of roof blocking on Area C of the building.  
  • The roofing contractor is scheduled to complete the set-up of safety railings on the roof levels of the building next week. 

Project Update - Week of January 30th 2023

Please see the below project update and list of activities scheduled for the week of January 30th 2023

Tripp McElroy III 0 189 Article rating: No rating
  • The site contractor shall continue with the excavation and installation of drainage lines in the outdoor learning space between Areas C & D of the building.   
  • The structural steel contractor shall continue with decking & detailing activities in Areas A & B of the building.  Portions of this work is weather dependant.   
  • The general trades contractor shall continue with mobilizing activities, including the delivery of a storage container and building materials to support safety items and roof blocking to the project site.
  • The roofing contractor is scheduled to have a crane onsite Thursday 2/2 to hoist and commence set-up of safety railings on the roof levels of the building. 
RSS
First1112131416181920Last

Theme picker