Project Update - Week of May 1st 2023

Please see the below project update and list of activities scheduled for the week of May 1st 2023

Tripp McElroy III 0 170 Article rating: No rating
  • The site contractor shall complete the excavation and sub-grade prep for the remaining UG electrical in Area B of the building.
  • The site contractor will continue with the backfill of crushed stone and compaction in Area A in preparation for slab on grade prep.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking at mechanical equipment and penetration locations on Areas A & B of the building.
  • The general trades contractor will continue layout, framing & sheathing of exterior walls on the 1st & 2nd levels of Areas C & D. 
  • The general trades contractor shall set and secure the hollow metal door frames in the gymnasium walls.
  • The concrete contractor shall continue with slab on grade prep activities in Area A & B of the building.
  • The mechanical contractor will continue with the lay-out of duct hangers on the second level of Areas C & D of the building and continue with the installation of ductwork & mechanical piping.
  • The plumbing contractor will continue with the lay-out and installation of plumbing piping on the second level of Areas C & D of the building. 
  • The roofing contractor shall continue with the installation of roof dense deck and AVB on Areas A & B of the building.  
  • The electrical contractor shall continue with the installation of temp power and lighting provisions on the first level of Areas C & D of the building.
  • The electrical contractor shall commence with in-wall electrical rough-in at the gymnasium CMU walls.
  • The masonry contractor shall commence construction of the CMU walls in the gymnasium. 
  • The waterproofing contractor shall commence with the installation of the waterproofing membrane on the exterior walls of Area C of the building. 

Saturday Work - April 29th 2023

The project will be working on the site this Saturday 4/29/23. Activities will consist of the following:

Tripp McElroy III 0 177 Article rating: No rating
  • The mechanical contractor shall continue with the installation of mechanical piping on the second level of Area C in the building.
  • The landscape contractor will be performing spring maintenance on the lawn areas at the perimeter of the new athletic track.   

This weekend work schedule has been communicated and coordinated with the Town Manager's Office.

Project Update - Week of April 24th 2023

Please see the below project update and list of activities scheduled for the week of April 24th 2023

Tripp McElroy III 0 161 Article rating: No rating
  • The site contractor will continue with the excavation and sub-grade prep for the remaining UG plumbing and UG electrical in Area B of the building.
  • The site contractor will commence with backfill of crushed stone and compaction in Area A in preparation for slab on grade prep.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking at mechanical equipment and penetration locations on Areas A & B of the building.
  • The general trades contractor will continue layout and framing of exterior walls on the 1st & 2nd levels of Areas C & D. 
  • The concrete contractor shall continue with the installation of toe-boards at the perimeter of the slabs on deck in Areas A & B. 
  • The mechanical contractor will continue with the lay-out of duct hangers on the second level of Areas C & D of the building and commence with the installation of ductwork.
  • The plumbing contractor will continue with the lay-out of duct hangers on the second level of Areas C & D of the building. 
  • The roofing contractor shall continue with the installation of roof dense deck and AVB on Areas A & B of the building.  The roofing contractor is scheduled to have a crane onsite on Monday 4/24 to hoist roofing materials up to the roof levels. 
  • The electrical contractor shall continue with the installation of temp power and lighting provisions on the second level of Areas C & D of the building.
  • The masonry contractor shall continue construction of the CMU elevator shaft and commence layout for the gymnasium walls. 
  • The waterproofing contractor shall continue the waterproofing membrane installation at the top of the foundation walls in Area B of the building. 

Project Update - Week of April 17th 2023

Please see the below project update and list of activities scheduled for the week of April 17th 2023

Tripp McElroy III 0 156 Article rating: No rating
  • The site contractor will complete placing and compacting gravel for the entrance road way.  Fine grading and paving of this roadway is scheduled to occur Tuesday 4/18 through Friday 4/21 while the District is on Spring Break.
  • The site contractor will install the remaining drain line that is located in the existing bus loop at the perimeter of the existing Florence Roche building.  This work will be installed and paved while the District is on Spring Break.  This work has been communicated and coordinated with the District.
  • The site contractor will continue with the excavation and sub-grade prep for the remaining UG plumbing and UG electrical in Area B of the building.
  • The general trades contractor shall continue with the lay-out and installation of roof blocking at mechanical equipment and penetration locations on Areas A & B of the building.
  • The general trades contractor will continue layout and framing of exterior walls on the 2nd level of Areas C & D.  This activity shall commence on the 1st level of Areas C & D this week. 
  • The concrete contractor is scheduled to place the slabs on grade for Area C on Tuesday 4/18 and Area D on Friday 4/21.
  • The mechanical contractor will continue with the lay-out of duct hangers on the second level of Areas C & D of the building.
  • The plumbing contractor will continue with the installation of roof drain bodies on Areas A & B of the building and UG plumbing in Area B of the building. 
  • The roofing contractor shall continue with the installation of roof dense deck and AVB on Areas A & B of the building.
  • The electrical contractor shall continue with the installation of temp power and lighting provisions on the second level of Areas C & D of the building.
  • The masonry contractor shall commence construction of the CMU elevator shaft. 
  • The waterproofing contractor shall continue the waterproofing membrane installation at the top of the foundation walls in Area D. 

Project Update - Week of April 10th, 2023

Please see the below project update and list of activities scheduled for the week of April 10th, 2023

Jonathan May 0 167 Article rating: No rating
  • The site contractor will continue placing and compacting gravel for the entrance road way.  Paving of this area is scheduled for the week of 4/17 while the District is on Spring Break.
  • The site contractor will continue with the excavation and sub-grade prep for the remaining UG plumbing in Area B of the building.
  • The site contractor will continue preperation of the classroom wing slab on grade. 
  • The general trades contractor shall continue with the lay-out and installation of roof blocking at mechanical equipment and penetration locations.
  • The concrete contractor will prepare to place the slab on deck for Level 2 Area A & B. 
  • The general trades contractor will continue layout and framing of exterior walls on the 2nd level classroom wings. 
  • The mechanical contractor will continue with the lay-out of duct hangers on the second level of Area C of the building.
  • The plumbing contractor will continue with the installation of roof drain bodies on Areas A & B of the building. 
  • The plumbing contractor will continue with the installation of UG plumbing in Area B of the building.
  • The roofing contractor shall continue with the installation of roof dense deck and AVB on the roof.
  • The electrical contractor shall commence with the installation of temp power and lighting provisions on the second level of Area C of the building.
  • The masonry contractor shall commence errection of the CMU elevator shaft. 
  • The waterproofing contractor shall commence the waterproofing membrane installation at the top of the foundation wall. 