Project Update - Week of December 12th, 2022

Tripp McElroy III 0 191 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of December 12th 2022. 

  • The electrical enabling contractor shall complete the rough-in and prep to support future temporary power needs on the project and shall commence with clean-up and demoblizing from the project site.
  • The site contractor shall continue with the excavation and installation of the new drainage line, structures and water quality units on the West elevation of the new building. 
  • The site contractor is scheduled to tag the existing trees scheduled for removal along the existing Florence Roche parking lot on the South elevation of the project site.

Project Update - Week of December 5th, 2022

Tripp McElroy III 0 210 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of December 5th 2022. 

  • The plumbing enabling contractor shall commence with clean-up and demoblizing from the project site.
  • The site contractor shall commence with the continuation of sewer line on the West elevation of the new building.  This work continues the new sewer line that was stubbed into the project site over the Summer from the Middle School utility corridor work.  
  • The site contractor shall commence with the excavation and installation of the new drainage line and structures on the West elevation of the new building. 
  • The site contractor is scheduled to tag the existing trees scheduled for removal along the existing Florence Roche parking lot on the South elevation of the project site.
  • Temporary fence shall be relocated to seperate the new athletic track and field from the new building project site.  

Project Update - Week of November 21st 2022

Tripp McElroy III 0 203 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of November 21st 2022. 

  • The site contractor will continue with installation of foundation insulation and backfill of foundation walls in Area B of the building.
  • The site contractor shall continue with backfilling to subgrade in Area A, and continue with excavation and sub-grade prep for UG Plumbing in this area.
  • The site contractor shall continue and complete the installation of drainage infiltration system #3 and associated drainage structures.  This work has been communicated and coordinated with the District accordingly.  
  • The plumbing enabling contractor shall continue with lay-out and installation of UG Plumbing in Area A of the building.
  • Groton Electric Light Department is tentatively scheduled to commence the pulling of their primary cable from the new utility poles adjacent to Champney Street to the new transformer pad location on Monday 11/21.  Team is awaiting confirmation from GELD on this schedule.
  • Due to the Thanksgiving holiday no work will occur on the project site Thursday 11/24 and Friday 11/25.  Happy Thanksgiving! 

Project Update - Week of November 14th 2022

Tripp McElroy III 0 193 Article rating: No rating

Please see the below project update and list of activities scheduled for the week of November 14th 2022. 

  • The site contractor will continue with installation of foundation insulation and backfill of foundation walls in Area B of the building.
  • The site contractor shall continue with backfilling to subgrade in Area A, and continue with excavation and sub-grade prep for UG Plumbing in this area.
  • The site contractor shall commence with the excavation and installation of drainage infiltration system #3 and associated drainage structures on Monday 11/14.  This work has been communicated and coordinated with the District accordingly.  
  • The balance of the drainage infilitration systems are scheduled to be delivered to the project site for storage on Tuesday 11/15.    
  • The concrete contractor will continue and complete clean-up and demobilization efforts this week.
  • The plumbing enabling contractor shall continue with lay-out and installation of UG Plumbing in Area A of the building.
  • Groton Electric Light Department is tentatively scheduled to commence the pulling of their primary cable from the new utility poles adjacent to Champney Street to the new transformer pad location on Monday 11/14.  Team is awaiting confirmation from GELD on this schedule.  

Saturday Work - November 5th 2022

Tripp McElroy III 0 225 Article rating: No rating

The project will be working on the site this Saturday 11/5/22.  Activities will consist of the following: 

  • The site contractor shall be prepping and raking the loam at the perimeter of the long jump areas and placing the hydroseed.    

This weekend work schedule has been communicated and coordinated with the Town Manager's Office.

RSS
First1314151618202122Last

Theme picker