Project Update - Week of November 27th, 2023

Please see the below project update and list of activities scheduled for the week of 11/27.

Jonathan May 0 176 Article rating: No rating
  • The general trades contractor will continue metal framing activities in the cafeteria and kitchen
  • The generla trades contractor will continue drywall activities on level 1 A, Lobby and admin area. 
  • The general trades contractor will continue taping level 1 area D
  • The general trades contractor will continue insulation and drywall installation of the project areas and stair D
  • The painting contractor will continue initial coats of level 1 classrooms
  • The panting contractor will prime and paint the Platform exposed structure
  • The painting contractor will continue priming of the gym CMU
  • The ceiling contractor will continue ceiling grid on level 1 C. 
  • The ceiling contractor will commence ceiling grid install in the level 2 area C corridor
  • The millwork and casework contractor will commence casework installation on level 2 area C classrooms
  • The fire protection contractor will continue overhead rough in of the cafeteria and platform
  • The fire protection contractor will commence sprinkler head finish install into ceiling tile on level 2 area C
  • The plumbing contractor will continue level 1 area B in wall rough-in and pipe insulation insulation install
  • The mechanical contractor will continue VAV duct connections on level 1 D and A
  • The mechanical contractor will continue setting radiant panels into completed ceiling grid
  • The electrical contractor will continue overhead rough-in on level 1 area B cafeteria
  • The electrical contractor will continue installation of level 2 area c light fixtures
  • The electrical contractor will commence installation of level 2 area d light fixtures
  • The electrical contractor will commence level 2 toilet room light fixture install
  • The tile contractor will continue installation of level 2 single bathrooms
  • The elevator contractor will continue installation and assist other trades work within the elevator pit
  • The metal windows contractor will continue installation of the translucent panel in the gym and over the lobby
  • The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge

Saturday Work - November 18th, 2023

The project will be working on the site this Saturday 11/18/23. Activities will consist of the following:

Jonathan May 0 191 Article rating: No rating
  • The mechanical contractor will continue VAV duct tie-in on level 1 D. 

Project Update - Week of November 20th, 2023

Please see the below project update and list of activities scheduled for the week of November 20th 2023

Jonathan May 0 183 Article rating: No rating
  • The general trades contractor will continue metal framing activities in the cafeteria and kitchen
  • The generla trades contractor will continue drywall activities on level 1 A
  • The general trades contractor will continue taping level 1 area D
  • The general trades contractor will commence drywall of the project areas and the stair D
  • The painting contractor will continue level 2 and level 1 classrooms
  • The panting contractor will prime and paint the Platform exposed structure
  • The ceiling contractor will continue ceiling grid on level 1 C
  • The fire protection contractor will continue overhead rough in of the cafeteria and platform
  • The plumbing contractor will continue level 1 B in wall rough-in and insulation install
  • The mechanical contractor will continue VAV duct connections on level 1 D and A
  • The mechanical contractor will continue setting radiant panels into ceiling grid
  • The mechanical contractor will commence duct tie-in to the roof curbs
  • The electrical contractor will continue overhead rough-in on level 1 area B gym and cafeteria
  • The electrical contractor will continue installation of level 2 area c light fixtures
  • The electrical contractor will commence installation of level 2 area d light fixtures
  • The tile contractor will continue installation of level 2 single bathrooms
  • The elevator contractor will continue installation and assist other trades work within the elevator pit
  • The waterproofing contractor will commence waterproofing of the stem patio ceiling. 
  • The metal windows contractor will continue installation of the translucent panel in the gym
  • The roofing contractor will continue roof system tie-ins to the RTU curbs and installation of the perimeter metal edge

Project Update - Week of November 13th, 2023

Please see the below project update and list of activities scheduled for the week of November 13th 2023

Jonathan May 0 209 Article rating: No rating
  • The metal panel contractor will continue the cafeteria canopy ceiling installation 
  • The general trades contractor will continue metal framing activities in the cafeteria and kitchen
  • The generla trades contractor will continue drywall activities on level 1 A
  • The general trades contractor will continue taping level 1 area D
  • The painting contractor will continue level 2 and level 1 classrooms
  • The painting contractor will continue preperation of the gym CMU for paint
  • The ceiling contractor will commence ceiling grid on level 1
  • The fire protection contractor will continue overhead rough in of the exterior stem patio, cafeteria, and platform
  • The plumbing contractor will continue level 1 A in wall rough-in and insulation install
  • The mechanical contractor will continue VAV duct connections on level 1 D
  • The mechanical contractor will continue setting radiant panels into ceiling grid
  • The electrical contractor will continue overhead rough-in on level 1 area B gym and cafeteria
  • The electrical contractor will continue installation of level 2 lighting area C lighting fixtures
  • The tile contractor will continue installation of level 2 group bathroom floor and wall tile
  • The tile contractor will continue level 2 individual bathroom floor tile
  • The elevator contractor will continue installation and assist other trades work within the elevator pit

Project Update - Week of November 6th, 2023

Please see the below project update and list of activities scheduled for the week of 11/6.

Jonathan May 0 210 Article rating: No rating
  • The site contractor will continue subgrade preperation of the Outdoor Learning Lab
  • The metal panel contractor will continue the main entrance canopy installation 
  • The window contractor will continue final setting and caulking of the storefront frames
  • The general trades contractor will continue layout and metal framing of the level 1 lobby, cafeteria, and gym perimter wall
  • The general trades contractor will continue taping of level 2 and level 1 area C & D
  • The general trades contractor will continue drywall installation on level 1 area D & A 
  • The painting contractor will continue level 2 classrooms and commence level 2 corridors
  • The painting contractor will continue preperation of the gym CMU for paint
  • The ceiling contractor will continue ceiling grid installation on the level 2 auxilary rooms
  • The fire protection contractor will continue overhead rough in of the exterior stem patio
  • The plumbing contractor will continue level 1 A in wall rough-in and insulation install
  • The mechanical contractor will continue VAV duct connections on level 1 C
  • The mechanical contractor will continue setting radiant panels into ceiling grid
  • The mechanical contractor will receive and set roof top unit curbs onto the roof 
  • The roofing contractor will tie the roofing system into the set roof top unit curbs
  • The electrical contractor will continue overhead rough-in on level 1 area B gym and cafeteria
  • The electrical contractor will commence installation of level 2 lighting area C lighting fixtures
  • The tile contractor will continue installation of level 2 group bathroom floor and wall tile
  • The tile contractor will commence level 2 individual bathroom floor tile